Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Arapaho, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 10Number of bridges
  • 72ft / 22.0mTotal length
  • $9,066,000Total costs
  • 7,194Total average daily traffic
  • 1,649Total average daily truck traffic
  • 11,510Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Arapaho
  • No street view available for this location

New bridges in Arapaho, OK - historical statistics
  • New bridges - historical statistics
  • 11920-1929
  • 11940-1949
  • 31980-1989
  • 11990-1999
  • 22000-2009
  • 22010-2019
Average Bridge Truck Traffic in Arapaho, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 20.0%Excellent
  • 60.0%Good
  • 10.0%Satisfactory
  • 10.0%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 20.0%Very good
  • 60.0%Good
  • 10.0%Satisfactory
  • 10.0%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 20.0%Very good
  • 60.0%Good
  • 10.0%Satisfactory
  • 10.0%Serious
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 10.0%Very good
  • 70.0%Good
  • 10.0%Satisfactory
  • 10.0%Poor
Find on map >>   Show street view

Structure Number: 975,  Location: 1.2E 2.9N OF ARAPAHO (Lat: 35.620000,  Lng: -98.933481),  Route carried "on" structure: County highway N2280,  Year Built: 1920,  Status: Posted for load,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 24 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 38 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.0m (13.1ft),  Curb-To-Curb Width: 4.5m (14.8ft),  Out-to-Out Width: 4.7m (15.4ft)

Condition: Deck: Poor,  Superstructure: Poor,  Substructure: Serious,  Channel: Poor,  Operating Rating: 2.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 1.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.45m (14.60ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Critical Feature Inspection Date: September 2020,  Bridge Improvement Cost: $114,000,  Roadway Improvement Cost: $62,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 11106,  Location: 0.2 MI W JCT. U.S.183 (Lat: 35.638539,  Lng: -98.963858),  Route carried "on" structure: State highway 33,  Year Built: 1949,  Year Reconstructed: 2014,  Status: Open,  Structure Length: 3.69m (12.11ft),  Average Daily Traffic: 720 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,152 (year 2040),  Design Load: HL 93,  Features Intersected: BEAVER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 60.255,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.4m (40.7ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Excellent,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 77.1 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.89m (22.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $581,000,  Roadway Improvement Cost: $959,000,  Total Project Cost: $1,627,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 21986,  Location: 5.3 MI N JCT I-40 BUS. (Lat: 35.590881,  Lng: -98.960075),  Route carried "on" structure: US 183,  Year Built: 1988,  Status: Open,  Structure Length: 3.05m (10.01ft),  Average Daily Traffic: 2,900 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 4,640 (year 2040),  Design Load: HS 20,  Features Intersected: DRY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.544,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.23m (20.44ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $925,000,  Roadway Improvement Cost: $1,527,000,  Total Project Cost: $2,591,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22033,  Location: 8.1 MI N JCT I-40 BUS. (Lat: 35.631356,  Lng: -98.960047),  Route carried "on" structure: US 183,  Year Built: 1986,  Status: Open,  Structure Length: 5.09m (16.70ft),  Average Daily Traffic: 2,900 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 4,640 (year 2040),  Design Load: HS 20,  Features Intersected: BEAVER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.065,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 16.8m (55.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 70.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.17m (26.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,169,000,  Roadway Improvement Cost: $1,928,000,  Total Project Cost: $3,272,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22133,  Location: .5 W 1.2 N OF ARAPAHO (Lat: 35.594978,  Lng: -98.966283),  Route carried "on" structure: County highway E0980,  Year Built: 1989,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Inventory Rating: 68.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.99m (9.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $153,000,  Roadway Improvement Cost: $84,000,  Total Project Cost: $241,000 ( Estimate for 2015),  Deck Structure Type: Open Grating
Find on map >>   Show street view

Structure Number: 23767,  Location: 1.0 S 1.4 W OF SUNSET (Lat: 35.578417,  Lng: -98.992606),  Route carried "on" structure: County highway 2006C,  Year Built: 1994,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 320 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.837,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.29m (10.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $92,000,  Total Project Cost: $266,000 ( Estimate for 2015),  Deck Structure Type: Open Grating
Find on map >>   Show street view

Structure Number: 27168,  Location: 1.2E .3S OF ARAPAHO (Lat: 35.574158,  Lng: -98.933364),  Route carried "on" structure: County highway N2280,  Year Built: 2002,  Status: Open,  Structure Length: 1.55m (5.09ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 58.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $192,000,  Roadway Improvement Cost: $96,000,  Total Project Cost: $320,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 29047,  Location: .6E 1.2N OF ARAPAHO (Lat: 35.595150,  Lng: -98.942997),  Route carried "on" structure: County highway E0980,  Year Built: 2008,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: BEAVER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.9m (39.0ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.34m (4.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $130,000,  Roadway Improvement Cost: $65,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 29879,  Location: 2.7W; 3.2N OF ARAPAHO (Lat: 35.623889,  Lng: -99.003056),  Route carried "on" structure: County highway E0960,  Year Built: 2010,  Status: Open,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.0m (59.1ft),  Curb-To-Curb Width: 8.4m (27.6ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 40.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $88,000,  Roadway Improvement Cost: $44,000,  Total Project Cost: $299,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 30951,  Location: .5E OF ARAPAHO (Lat: 35.580556,  Lng: -98.945556),  Route carried "on" structure: County highway E0990,  Year Built: 2015,  Status: Open,  Structure Length: 2.38m (7.81ft),  Average Daily Traffic: 325 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 520 (year 2040),  Design Load: HS 20,  Features Intersected: BEAVER CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 22.3m (73.2ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Excellent,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 88.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Deck Structure Type: Concrete Cast-file-Place
Discuss Arapaho, Oklahoma (OK) on our hugely popular Oklahoma forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.