Bridge Statistics for Blair, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 23Number of bridges
  • 82ft / 25.2mTotal length
  • $5,664,000Total costs
  • 5,810Total average daily traffic
  • 850Total average daily truck traffic
  • 9,296Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Blair
  • No street view available for this location

New bridges in Blair, OK - historical statistics
  • New bridges - historical statistics
  • 61930-1939
  • 61940-1949
  • 31950-1959
  • 11980-1989
  • 31990-1999
  • 12000-2009
  • 22010-2019
  • 12020-2022
Reconstructed bridges in Blair, OK - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11980-1989
  • 11990-1999
  • 02000-2009
  • 12010-2019
Average Bridge Daily Traffic in Blair, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 5.9%Very good
  • 47.1%Good
  • 47.1%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 5.9%Very good
  • 58.8%Good
  • 35.3%Satisfactory
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 5.9%Very good
  • 29.4%Good
  • 52.9%Satisfactory
  • 11.8%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 8.7%Very good
  • 26.1%Good
  • 56.5%Satisfactory
  • 8.7%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 16.7%Very good
  • 66.7%Good
  • 16.7%Satisfactory
Find on map >>   Show street view

Structure Number: 3545,  Location: .1 MI S OF GREER C/L (Lat: 34.810833,  Lng: -99.335000),  Route carried "on" structure: County highway N2040,  Year Built: 1932,  Year Reconstructed: 1980,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 4,200 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 6,720 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 16.5m (54.1ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $51,000,  Roadway Improvement Cost: $25,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 5306,  Location: 9. S 1.9 E OF GRANITE (Lat: 34.827467,  Lng: -99.344347),  Route carried "on" structure: County highway E1510,  Year Built: 1937,  Status: Open,  Structure Length: 1.55m (5.09ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.4m (14.4ft),  Curb-To-Curb Width: 8.1m (26.6ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.36m (14.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $223,000,  Roadway Improvement Cost: $122,000,  Total Project Cost: $354,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 5687,  Location: 1.0 W 3.2. S BLAIR (Lat: 34.748003,  Lng: -99.352411),  Route carried "on" structure: County highway N2030,  Year Built: 1938,  Status: Open,  Structure Length: 0.82m (2.69ft),  Average Daily Traffic: 30 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 48 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.7m (25.3ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.11m (10.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $159,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $251,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 5766,  Location: .8 S .8 W OF BLAIR (Lat: 34.768975,  Lng: -99.349050),  Route carried "on" structure: County highway E1550,  Year Built: 1938,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.4m (7.9ft),  Curb-To-Curb Width: 7.7m (25.3ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.86m (9.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $146,000,  Roadway Improvement Cost: $80,000,  Total Project Cost: $231,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 6709,  Location: 1.1 S 1. W OF BLAIR (Lat: 34.764336,  Lng: -99.352642),  Route carried "on" structure: County highway N2030,  Year Built: 1939,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 30 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 48 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 8.4m (27.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $149,000,  Roadway Improvement Cost: $82,000,  Total Project Cost: $236,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Other
Find on map >>   Show street view

Structure Number: 7225,  Location: .4 N 3. W OF BLAIR (Lat: 34.787333,  Lng: -99.388072),  Route carried "on" structure: County highway N2010,  Year Built: 1939,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.31m (14.14ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $220,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $350,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 8389,  Location: 1.0 W 1.6 S OF BLAINE (Lat: 34.757642,  Lng: -99.352542),  Route carried "on" structure: County highway N2030,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 30 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 48 (year 2040),  Features Intersected: CREEK / IRRIGATION
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.6m (31.5ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 29.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.46m (11.35ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $177,000,  Roadway Improvement Cost: $97,000,  Total Project Cost: $280,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 8426,  Location: 1.8 S .4 W OF BLAIR (Lat: 34.754381,  Lng: -99.343686),  Route carried "on" structure: County highway E1560,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: CREEK / IRRIGATION
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 23.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 14.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.46m (11.35ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $177,000,  Roadway Improvement Cost: $97,000,  Total Project Cost: $280,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 8427,  Location: .1 W .8 S OF BLAIR (Lat: 34.768906,  Lng: -99.336514),  Route carried "on" structure: County highway E1550,  Year Built: 1940,  Status: Posted for load,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK / IRRIGATION
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 29.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.46m (11.35ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $177,000,  Roadway Improvement Cost: $97,000,  Total Project Cost: $280,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 885,  Location: 0.5 S 0.8 E BLAIR (Lat: 34.768836,  Lng: -99.318006),  Route carried "on" structure: County highway 3394C,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: IRRIGATION CANAL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 22.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 11.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 4.27m (14.01ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Other Special Inspection Date: May 2021,  Bridge Improvement Cost: $218,000,  Roadway Improvement Cost: $120,000,  Total Project Cost: $347,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 9102,  Location: 1 N 0.8 E OF BLAIR (Lat: 34.798089,  Lng: -99.321728),  Route carried "on" structure: County highway E1530,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 60 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 96 (year 2040),  Features Intersected: IRRIGATION CANAL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.5m (24.6ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 20.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 9.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.31m (14.14ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $220,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $350,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 10521,  Location: 9. S 2.7 E OF GRANITE (Lat: 34.827369,  Lng: -99.329811),  Route carried "on" structure: County highway E1510,  Year Built: 1946,  Status: Posted for load,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: H 10,  Features Intersected: IRRIGATION CANAL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 18.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 9.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.27m (14.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $218,000,  Roadway Improvement Cost: $120,000,  Total Project Cost: $347,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 11764,  Location: 3.1 MILES W BLAIR (Lat: 34.783636,  Lng: -99.389878),  Route carried "on" structure: County highway 3317,  Year Built: 1950,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 320 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.57m (11.71ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1204,  Location: 0.2 MI W OF BLAIR (Lat: 34.783531,  Lng: -99.338006),  Route carried "on" structure: County highway 3317,  Year Built: 1950,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 320 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.114,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.22m (13.85ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 20401,  Location: 3 W .1 MI S OF BLAIR (Lat: 34.782022,  Lng: -99.388081),  Route carried "on" structure: County highway 3311,  Year Built: 1983,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 70 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 112 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.929,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.46m (11.35ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 23307,  Location: 7TH STREET & .7 W HUGHES (Lat: 34.776250,  Lng: -99.332958),  Route carried "on" structure: County highway E1545,  Year Built: 1950,  Year Reconstructed: 2010,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 5.8m (19.0ft),  Out-to-Out Width: 5.8m (19.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.29m (10.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $92,000,  Total Project Cost: $266,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 23308,  Location: TAYLOR & 6 TH. STREET (Lat: 34.777367,  Lng: -99.330606),  Route carried "on" structure: County highway N2044,  Year Built: 1997,  Year Reconstructed: 2002,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.064,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 99.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.35m (10.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $171,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $271,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 24947,  Location: STONEHOCKER & 6ST (Lat: 34.777347,  Lng: -99.331800),  Route carried "on" structure: County highway N2042,  Year Built: 1997,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 320 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.16m (3.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $80,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 25014,  Location: 2.4 N 1.5 W OF BLAIR (Lat: 34.812833,  Lng: -99.363453),  Route carried "on" structure: County highway E1520,  Year Built: 1996,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 40 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 64 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 98.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 59.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $156,000,  Roadway Improvement Cost: $86,000,  Total Project Cost: $246,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 28041,  Location: 1.5W 1.2N OFBLAIR (Lat: 34.798194,  Lng: -99.361436),  Route carried "on" structure: County highway E1530,  Year Built: 2005,  Status: Posted for load,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.80m (2.62ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $80,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 30114,  Location: 9S .4E OF GRANITE (Lat: 34.827500,  Lng: -99.369722),  Route carried "on" structure: County highway E1510,  Year Built: 2012,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.4m (14.4ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Total Project Cost: $225,000,  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 31921,  Location: .5S 1W OF BLAIR (Lat: 34.774036,  Lng: -99.352689),  Route carried "on" structure: County highway N2030,  Year Built: 2017,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.9m (48.9ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.3m (27.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 49.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 31977,  Location: 1S 1.4W of SH19/US283 JCT (Lat: 34.769167,  Lng: -99.358611),  Route carried "on" structure: County highway E1550,  Year Built: 2020,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Design Load: HL 93,  Features Intersected: BITTER CREEK TRIB.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.553,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 12.9m (42.3ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 54.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020