Bridge Statistics for Center Point, Alabama (AL)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 19Number of bridges
  • 85ft / 25.8mTotal length
  • $14,461,000Total costs
  • 81,455Total average daily traffic
  • 4,618Total average daily truck traffic
  • 106,405Total future (year 2030) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Center Point
  • No street view available for this location

New bridges in Center Point, AL - historical statistics
  • New bridges - historical statistics
  • 11910-1919
  • 11960-1969
  • 41970-1979
  • 71980-1989
  • 51990-1999
  • 12010-2019
Average Bridge Daily Traffic in Center Point, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 44.4%Good
  • 44.4%Satisfactory
  • 11.1%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 44.4%Good
  • 44.4%Satisfactory
  • 11.1%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 44.4%Good
  • 44.4%Satisfactory
  • 11.1%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 5.3%Very good
  • 15.8%Good
  • 47.4%Satisfactory
  • 31.6%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 10.0%Excellent
  • 40.0%Good
  • 30.0%Satisfactory
  • 20.0%Fair
Find on map >>   Show street view

Structure Number: 8396,  Location: AL 75 * FIVE MI CK (Lat: 33.613056,  Lng: -86.686389),  Route carried "on" structure: State highway 75,  Year Built: 1964,  Status: Open,  Structure Length: 2.15m (7.05ft),  Average Daily Traffic: 32,440 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 40,135 (year 2041),  Design Load: H 15,  Features Intersected: FIVE MI CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.299,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 35.4m (116.1ft),  Skew: 24 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 304.8m (1,000.0ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.95m (9.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $3,096,000,  Roadway Improvement Cost: $310,000,  Total Project Cost: $3,406,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10637,  Location: .5 MI W OLD SPRINGVILLE (Lat: 33.634714,  Lng: -86.664569),  Route carried "on" structure: County highway 341,  Year Built: 1912,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 2,502 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 4,000 (year 2040),  Features Intersected: FIVE MILE CREEK,  Facility Carried by Structure: MARY VANN LANE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Material/Design: Concrete continuous,  Design/Construction: Frame,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.89m (6.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $298,000,  Roadway Improvement Cost: $30,000,  Total Project Cost: $328,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10823,  Location: JCT BIG MTN RD (Lat: 33.623500,  Lng: -86.663700),  Route carried "on" structure: County highway 157,  Year Built: 1972,  Status: Open,  Structure Length: 1.95m (6.40ft),  Average Daily Traffic: 8,560 (year 2021),  Truck Traffic: 15%,  Average Future Daily Traffic: 11,950 (year 2041),  Design Load: HS 20,  Features Intersected: DRY CREEK,  Facility Carried by Structure: BREWSTER ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.6m (21.7ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 8.9m (29.2ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 9.0m (29.5ft),  Out-to-Out Width: 9.6m (31.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 51.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.69m (8.83ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $572,000,  Roadway Improvement Cost: $57,000,  Total Project Cost: $629,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10824,  Location: 115 FT S BREWSTER ROAD (Lat: 33.622756,  Lng: -86.665142),  Route carried "on" structure: County highway 329,  Year Built: 1973,  Status: Open,  Structure Length: 1.95m (6.40ft),  Average Daily Traffic: 687 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,000 (year 2041),  Design Load: HS 20,  Features Intersected: DRY CREEK,  Facility Carried by Structure: PINE HILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 9.0m (29.5ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 6.8m (22.3ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 51.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.69m (8.83ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $443,000,  Roadway Improvement Cost: $44,000,  Total Project Cost: $487,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 12239,  Location: CENTER POINT (Lat: 33.629117,  Lng: -86.673800),  Route carried "on" structure: County highway 343,  Year Built: 1979,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 5,080 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 6,800 (year 2041),  Design Load: HS 20,  Features Intersected: FIVE MILE CRK TRIBUTARY,  Facility Carried by Structure: POLLY REED ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.5m (21.3ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.8m (22.3ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.9m (29.2ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 23.6 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.51m (4.95ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $322,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $354,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 12338,  Location: 500' W CARSON ROAD (Lat: 33.632400,  Lng: -86.704133),  Route carried "on" structure: County highway ,  Year Built: 1980,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 3,868 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 4,020 (year 2040),  Design Load: HS 20,  Features Intersected: TARRANT SPRING BRANCH,  Facility Carried by Structure: MARLIN SPRINGS RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.3m (50.2ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 9.9m (32.5ft),  Out-to-Out Width: 10.8m (35.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 50.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.27m (7.45ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $545,000,  Roadway Improvement Cost: $55,000,  Total Project Cost: $600,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 12436,  Location: JCT WOOD DRIVE CIRCLE (Lat: 33.666164,  Lng: -86.668175),  Route carried "on" structure: County highway 347,  Year Built: 1980,  Status: Open,  Structure Length: 0.92m (3.02ft),  Average Daily Traffic: 2,610 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 3,650 (year 2041),  Design Load: HS 20,  Features Intersected: TURKEY CREEK TRIBUTARY,  Facility Carried by Structure: WOOD DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.1m (13.5ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 48.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.59m (5.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $1,643,000,  Roadway Improvement Cost: $164,000,  Total Project Cost: $1,807,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 12437,  Location: 100' W SWEENY HOLLOW RD (Lat: 33.666267,  Lng: -86.665872),  Route carried "on" structure: County highway 347,  Year Built: 1980,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 2,735 (year 2018),  Truck Traffic: 5%,  Average Future Daily Traffic: 3,825 (year 2038),  Design Load: HS 20,  Features Intersected: DRY CREEK,  Facility Carried by Structure: WOOD DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.5m (31.2ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.7m (15.4ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.68m (5.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $893,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $982,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1252,  Location: JCT SWEENY HOLLOW RD (Lat: 33.671917,  Lng: -86.665417),  Route carried "on" structure: County highway ,  Year Built: 1981,  Status: Open,  Structure Length: 1.03m (3.38ft),  Average Daily Traffic: 50 (year 2018),  Average Future Daily Traffic: 70 (year 2038),  Design Load: HS 20,  Features Intersected: DRY BRANCH,  Facility Carried by Structure: GREEN CREST DR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.2m (23.6ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 64.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.70m (5.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $226,000,  Roadway Improvement Cost: $23,000,  Total Project Cost: $249,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1403,  Location: 100FT W SERENE ROAD (Lat: 33.627381,  Lng: -86.670889),  Route carried "on" structure: County highway 340,  Year Built: 1986,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 5,350 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 7,450 (year 2041),  Design Load: HS 20,  Features Intersected: FIVE MILE CREEK,  Facility Carried by Structure: POLLY REED ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.6m (21.7ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.6m (47.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 8.9m (29.2ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 49.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.27m (7.45ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $498,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $548,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 14956,  Location: 6.1 MI.N.FLA.LINE (Lat: 31.071167,  Lng: -85.692850),  Route carried "on" structure: State highway 167,  Year Built: 1989,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 3,100 (year 2013),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,420 (year 2033),  Design Load: HS 20,  Features Intersected: BURCH BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.777,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 57.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $942,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $1,036,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 14964,  Location: 1.4 MI E INT RT 253 * 251 (Lat: 32.282881,  Lng: -88.099289),  Route carried "on" structure: County highway 253,  Year Built: 1989,  Status: Open,  Structure Length: 2.07m (6.79ft),  Average Daily Traffic: 425 (year 1996),  Truck Traffic: 15%,  Average Future Daily Traffic: 450 (year 2036),  Design Load: HS 20,  Features Intersected: CANE CREEK,  Facility Carried by Structure: CO RD 42 - EDNA R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 67.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.84m (9.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $506,000,  Roadway Improvement Cost: $51,000,  Total Project Cost: $557,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 15224,  Location: 1.6 MI. S. OF CO. RD. 64 (Lat: 30.578517,  Lng: -87.904756),  Route carried "on" structure: County highway 98,  Year Built: 1990,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 3,516 (year 2018),  Truck Traffic: 1%,  Average Future Daily Traffic: 4,746 (year 2038),  Design Load: HS 20,  Features Intersected: RED GULLEY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.38m (4.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $636,000,  Roadway Improvement Cost: $64,000,  Total Project Cost: $700,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 15309,  Location: 5 MI W. OF GENEVA (Lat: 31.028783,  Lng: -85.959294),  Route carried "on" structure: County highway ,  Year Built: 1971,  Year Reconstructed: 1994,  Status: Posted for load,  Structure Length: 2.15m (7.05ft),  Average Daily Traffic: 55 (year 2020),  Average Future Daily Traffic: 73 (year 2040),  Features Intersected: SANDY CREEK,  Facility Carried by Structure: SANDY CREEK RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 23.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 17.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.94m (9.65ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: April 2020,  Other Special Inspection Date: April 2021,  Bridge Improvement Cost: $323,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $355,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 15336,  Location: 1 MI W LIBERTY HILLCHURCH (Lat: 31.088989,  Lng: -86.440283),  Route carried "on" structure: County highway ,  Year Built: 1991,  Status: Posted for load,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 60 (year 1994),  Average Future Daily Traffic: 86 (year 2030),  Features Intersected: DEVIL HEAD CREEK,  Facility Carried by Structure: COUNTY DIRT RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 17.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 12.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.59m (5.22ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: July 2020,  Other Special Inspection Date: July 2021,  Bridge Improvement Cost: $174,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $191,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 16674,  Location: 0.25MI N BREWSTER RD (Lat: 33.627136,  Lng: -86.659419),  Route carried "on" structure: County highway ,  Year Built: 1993,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 1,156 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 1,250 (year 2041),  Design Load: HS 20,  Features Intersected: FIVEMILE CREEK TRIBUTARY,  Facility Carried by Structure: WESTRIDGE DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.9m (22.6ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 18.0m (59.1ft),  Out-to-Out Width: 18.6m (61.0ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 60.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.30m (4.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $450,000,  Roadway Improvement Cost: $45,000,  Total Project Cost: $495,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 16675,  Location: 0.25MI N BREWSTER RD (Lat: 33.627644,  Lng: -86.659253),  Route carried "on" structure: County highway ,  Year Built: 1993,  Status: Open,  Structure Length: 1.51m (4.95ft),  Average Daily Traffic: 731 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 900 (year 2041),  Design Load: HS 20,  Features Intersected: FIVEMILE CREEK TRIBUTARY,  Facility Carried by Structure: WESTRIDGE DRIVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.6m (21.7ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.4m (14.4ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 17.4m (57.1ft),  Out-to-Out Width: 18.0m (59.1ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 58.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.19m (7.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $884,000,  Roadway Improvement Cost: $88,000,  Total Project Cost: $972,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 16695,  Location: 1.0MI SE AL HWY 75 (Lat: 33.672233,  Lng: -86.665289),  Route carried "on" structure: County highway 10,  Year Built: 1995,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 8,280 (year 2021),  Truck Traffic: 15%,  Average Future Daily Traffic: 11,280 (year 2041),  Design Load: HS 20,  Features Intersected: DRY BRANCH,  Facility Carried by Structure: SWEENY HOLLOW RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.5m (21.3ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.2m (10.5ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.2m (40.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 59.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $379,000,  Roadway Improvement Cost: $38,000,  Total Project Cost: $417,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 20598,  Location: SUN VALLEY AND TUPELO RD (Lat: 33.639967,  Lng: -86.699822),  Route carried "on" structure: County highway ,  Year Built: 2012,  Status: Open,  Structure Length: 0.85m (2.79ft),  Average Daily Traffic: 250 (year 2018),  Average Future Daily Traffic: 300 (year 2038),  Design Load: HS 20,  Features Intersected: TARRANT SPRINGS BRANCH,  Facility Carried by Structure: TUPELO ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 10.5m (34.4ft),  Out-to-Out Width: 11.1m (36.4ft)

Condition: Channel: Very good,  Culverts: Excellent,  Operating Rating: 55.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Superior to present desirable criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.52m (4.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $316,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $348,000 ( Estimate for 2022)
Discuss Center Point, Alabama (AL) on our hugely popular Alabama forum.