Bridge Statistics for Fall City, Washington (WA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 20Number of bridges
  • 200ft / 60.7mTotal length
  • $36,130,000Total costs
  • 122,088Total average daily traffic
  • 11,109Total average daily truck traffic
  • 174,795Total future (year 2038) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Fall City
  • No street view available for this location

New bridges in Fall City, WA - historical statistics
  • New bridges - historical statistics
  • 11930-1939
  • 91940-1949
  • 11950-1959
  • 21980-1989
  • 21990-1999
  • 42000-2009
  • 12020-2022
Average Bridge Daily Traffic in Fall City, WA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 15.8%Very good
  • 36.8%Good
  • 36.8%Satisfactory
  • 5.3%Fair
  • 5.3%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 10.5%Very good
  • 57.9%Good
  • 26.3%Satisfactory
  • 5.3%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 21.1%Very good
  • 42.1%Good
  • 21.1%Satisfactory
  • 15.8%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 80.0%Very good
  • 10.0%Good
  • 10.0%Satisfactory
Find on map >>   Show street view

Structure Number: BK,  Location: 3.0 N JCT SR 202 (Lat: 47.606333,  Lng: -121.913917),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.828,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 34.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $354,000,  Roadway Improvement Cost: $71,000,  Total Project Cost: $707,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1380A,  Location: 11.5 E JCT SR 520 (Lat: 47.580000,  Lng: -121.936667),  Route carried "on" structure: State highway 202,  Year Built: 1930,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Daily Traffic: 7,905 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 11,161 (year 2039),  Design Load: H 15,  Features Intersected: PATTERSON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 30.948,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.5m (41.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $286,000,  Roadway Improvement Cost: $57,000,  Total Project Cost: $571,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 2999A,  Location: 0.2 N JCT SR 202 (Lat: 47.572528,  Lng: -121.887639),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 8.87m (29.10ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.386,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 17,  Length of Maximum Span: 5.2m (17.1ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 1.0m (3.3ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 9.9m (32.5ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Very good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.87m (29.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $1,862,000,  Roadway Improvement Cost: $372,000,  Total Project Cost: $3,725,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2999B,  Location: 0.5 N JCT SR 202 (Lat: 47.575500,  Lng: -121.890444),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.789,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Poor,  Superstructure: Good,  Substructure: Fair,  Channel: Very good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $333,000,  Roadway Improvement Cost: $67,000,  Total Project Cost: $666,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2999C,  Location: 0.7 N JCT SR 202 (Lat: 47.577786,  Lng: -121.892783),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.078,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.9m (39.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2018,  Bridge Improvement Cost: $442,000,  Roadway Improvement Cost: $88,000,  Total Project Cost: $883,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2999D,  Location: 0.8 N JCT SR 202 (Lat: 47.578600,  Lng: -121.893589),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.207,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $354,000,  Roadway Improvement Cost: $71,000,  Total Project Cost: $707,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2999E,  Location: 1.1 N JCT SR 202 (Lat: 47.582806,  Lng: -121.897808),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 2.93m (9.61ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.754,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 47.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.93m (9.61ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: September 2018,  Bridge Improvement Cost: $653,000,  Roadway Improvement Cost: $131,000,  Total Project Cost: $1,306,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2999F,  Location: 1.2 N JCT SR 202 (Lat: 47.584583,  Lng: -121.899603),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.996,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.5m (18.0ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.9m (39.0ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2018,  Bridge Improvement Cost: $524,000,  Roadway Improvement Cost: $105,000,  Total Project Cost: $1,049,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2999G,  Location: 1.4 N JCT SR 202 (Lat: 47.586164,  Lng: -121.901217),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.205,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.8m (38.7ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: September 2018,  Bridge Improvement Cost: $469,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $938,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 2999I,  Location: 2.1 N JCT SR 202 (Lat: 47.594581,  Lng: -121.910669),  Route carried "on" structure: State highway 203,  Year Built: 1945,  Status: Open,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: H 15,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.380,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 11.9m (39.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 44.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.10m (6.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $469,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $938,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 11599A,  Location: 14.0 E JCT SR 520 (Lat: 47.567861,  Lng: -121.887611),  Route carried "on" structure: State highway 202,  Year Built: 1980,  Status: Open,  Structure Length: 12.77m (41.90ft),  Average Daily Traffic: 12,633 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 17,837 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: SNOQUALMIE RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 34.987,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 48.8m (160.1ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 0.0m,  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 19.1m (62.7ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 53.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 12.77m (41.90ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: August 2018,  Underwater Inspection Date: September 2020,  Bridge Improvement Cost: $5,196,000,  Roadway Improvement Cost: $1,039,000,  Total Project Cost: $10,391,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 12947A,  Location: 1.8 N JCT SR 202 (Lat: 47.590806,  Lng: -121.905833),  Route carried "on" structure: State highway 203,  Year Built: 1986,  Status: Open,  Structure Length: 6.40m (21.00ft),  Average Daily Traffic: 7,783 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 10,989 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.865,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 12.8m (42.0ft),  Curb-To-Curb Width: 10.1m (33.1ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 82.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.40m (21.00ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: August 2018,  Bridge Improvement Cost: $1,428,000,  Roadway Improvement Cost: $286,000,  Total Project Cost: $2,856,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 19269C,  Location: 12.1 E JCT SR 520 (Lat: 47.577603,  Lng: -121.925611),  Route carried "on" structure: State highway 202,  Year Built: 2020,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 12,172 (year 2016),  Truck Traffic: 8%,  Average Future Daily Traffic: 19,062 (year 2038),  Design Load: HL 93,  Features Intersected: PATTERSON CRK EAST TRIB
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 31.801,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 72.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 56.1 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.73m (2.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $173,000,  Roadway Improvement Cost: $35,000,  Total Project Cost: $346,000 ( Estimate for 2014)
Find on map >>   Show street view

Structure Number: 80714,  Location: 0.1 MI S OF SR-202 (Lat: 47.581750,  Lng: -121.942778),  Route carried "on" structure: County highway 83510,  Year Built: 1951,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 10 (year 2019),  Truck Traffic: 10%,  Average Future Daily Traffic: 120 (year 2039),  Design Load: H 15,  Features Intersected: PATTERSON CREEK,  Facility Carried by Structure: 300TH AVE SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Skew: 3 degrees,  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 5.8m (19.0ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 35.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.94m (3.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2019,  Bridge Improvement Cost: $322,000,  Roadway Improvement Cost: $64,000,  Total Project Cost: $645,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 8638,  Location: 300 FT N OF FALL CITY RD (Lat: 47.554456,  Lng: -121.900222),  Route carried "on" structure: County highway 83010,  Year Built: 1998,  Status: Open,  Structure Length: 3.81m (12.50ft),  Average Daily Traffic: 1,563 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,825 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: RAGING RIVER,  Facility Carried by Structure: 328 WAY SE
Minimum Vertical Clearance: 5.03m (16.50ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 36.6m (120.1ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.6m (38.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 27.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 16.5 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.81m (12.50ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Critical Feature Inspection Date: April 2021,  Bridge Improvement Cost: $900,000,  Roadway Improvement Cost: $180,000,  Total Project Cost: $1,800,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 86442,  Location: 0.25 MI S OF SR-202 (Lat: 47.564111,  Lng: -121.889472),  Route carried "on" structure: County highway 98906,  Year Built: 1998,  Status: Open,  Structure Length: 6.07m (19.91ft),  Average Daily Traffic: 9,092 (year 2019),  Truck Traffic: 5%,  Average Future Daily Traffic: 12,500 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: RAGING RIVER,  Facility Carried by Structure: PRESTON FALL CITY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 1,  Length of Maximum Span: 35.7m (117.1ft),  Curb or Sidewalk Widths: Left: 1.9m (6.2ft),  Right: 0.0m,  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 14.7m (48.2ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Channel: Very good,  Operating Rating: 24.3 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 18.8 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.07m (19.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $1,672,000,  Roadway Improvement Cost: $334,000,  Total Project Cost: $3,343,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 87564,  Location: 0.3 MI W OF SR-203 (Lat: 47.574850,  Lng: -121.890908),  Route carried "on" structure: County highway 88010,  Year Built: 2007,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 150 (year 2019),  Truck Traffic: 5%,  Average Future Daily Traffic: 300 (year 2039),  Design Load: HS 25 or greater,  Features Intersected: DRAINAGE DITCH,  Facility Carried by Structure: CW NEAL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $638,000,  Roadway Improvement Cost: $128,000,  Total Project Cost: $1,277,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 87565,  Location: 0.4 MI NE OF SR-203 (Lat: 47.574747,  Lng: -121.882814),  Route carried "on" structure: County highway 88000,  Year Built: 2007,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 95 (year 2019),  Truck Traffic: 5%,  Average Future Daily Traffic: 300 (year 2039),  Design Load: HS 20,  Features Intersected: RUTHERFORD SLOUGH,  Facility Carried by Structure: SE 39TH PL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 7.4m (24.3ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 68.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.25m (4.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $623,000,  Roadway Improvement Cost: $125,000,  Total Project Cost: $1,246,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 87795,  Location: 0.8 MI N OF SR-202 (Lat: 47.587206,  Lng: -121.929169),  Route carried "on" structure: County highway 67950,  Year Built: 2008,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 338 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 400 (year 2040),  Design Load: HL 93,  Features Intersected: PATTERSON CREEK,  Facility Carried by Structure: 310TH AVE SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 76.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $714,000,  Roadway Improvement Cost: $143,000,  Total Project Cost: $1,429,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 87798,  Location: 0.2 MI NO OF SR-202 (Lat: 47.580833,  Lng: -121.931917),  Route carried "on" structure: County highway 67990,  Year Built: 2008,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 300 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 400 (year 2040),  Design Load: HL 93,  Features Intersected: PATTERSON CREEK,  Facility Carried by Structure: 308TH AVE SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 7.2m (23.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 84.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.31m (4.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $654,000,  Roadway Improvement Cost: $131,000,  Total Project Cost: $1,307,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing