Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Lobelville, Tennessee (TN)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 41Number of bridges
  • 666ft / 203mTotal length
  • $21,376,000Total costs
  • 25,916Total average daily traffic
  • 1,654Total average daily truck traffic
  • 41,698Total future (year 2039) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Lobelville
  • No street view available for this location

New bridges in Lobelville, TN - historical statistics
  • New bridges - historical statistics
  • 31930-1939
  • 11940-1949
  • 41950-1959
  • 41960-1969
  • 61970-1979
  • 161980-1989
  • 51990-1999
  • 12000-2009
  • 12010-2019
Average Bridge Daily Traffic in Lobelville, TN
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 11.8%Very good
  • 29.4%Good
  • 5.9%Satisfactory
  • 52.9%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 17.6%Very good
  • 17.6%Good
  • 5.9%Satisfactory
  • 58.8%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 17.6%Very good
  • 11.8%Good
  • 23.5%Satisfactory
  • 47.1%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 36.6%Very good
  • 7.3%Good
  • 29.3%Satisfactory
  • 26.8%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 12.5%Good
  • 87.5%Fair
Find on map >>   Show street view

Structure Number: 68017770001,  Location: 5.5 M. S. LOBELVILLE. (Lat: 35.708350,  Lng: -87.774983),  Route carried "on" structure: County highway 1777,  Year Built: 1980,  Status: Open,  Structure Length: 6.68m (21.92ft),  Average Daily Traffic: 358 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 688 (year 2041),  Design Load: HS 20,  Features Intersected: CANE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.097,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 21.9m (71.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 47.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 68017770003,  Location: 1 M. SE. LOBELVILLE. (Lat: 35.749767,  Lng: -87.773700),  Route carried "on" structure: County highway 1777,  Year Built: 1972,  Status: Open,  Structure Length: 1.07m (3.51ft),  Average Daily Traffic: 358 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 688 (year 2041),  Design Load: HS 20,  Features Intersected: LAGOON BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.099,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 4 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.4m (21.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 71.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.07m (3.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $90,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $136,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 68017770005,  Location: 0.5 M. W. LOBELVILLE. (Lat: 35.760600,  Lng: -87.774650),  Route carried "on" structure: County highway 1777,  Year Built: 1962,  Status: Open,  Structure Length: 21.76m (71.39ft),  Average Daily Traffic: 715 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,144 (year 2041),  Design Load: H 15,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.451,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 1 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 8,  Number Of Approach Spans: 3,  Length of Maximum Span: 29.0m (95.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 33.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 21.76m (71.39ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: April 2021,  Underwater Inspection Date: May 2017,  Bridge Improvement Cost: $954,000,  Roadway Improvement Cost: $96,000,  Total Project Cost: $1,432,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 68017920001,  Location: 7 M. N. LINDEN. (Lat: 35.668333,  Lng: -87.814350),  Route carried "on" structure: County highway 1792,  Year Built: 1985,  Status: Open,  Structure Length: 14.33m (47.01ft),  Average Daily Traffic: 113 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 181 (year 2041),  Design Load: HS 20,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.467,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 28.3m (92.8ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Good,  Channel: Very good,  Operating Rating: 65.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: High priority of corrective action,  Length Of Structure Improvement: 14.33m (47.01ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: June 2021,  Underwater Inspection Date: July 2021,  Bridge Improvement Cost: $735,000,  Roadway Improvement Cost: $74,000,  Total Project Cost: $1,103,000 ( Estimate for 2021),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 68017920003,  Location: BRUSH CREEK RD-PERRY CO (Lat: 35.652183,  Lng: -87.766667),  Route carried "on" structure: County highway 1792,  Year Built: 1996,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 113 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 181 (year 2041),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.437,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 12.3m (40.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Assigned rating based on Load Factor Design (LFD) reported in metric tons,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned rating based on Load Factor Design (LFD) reported in metric tons,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 680A0540001,  Location: 3.5 M. W. LOBELVILLE. (Lat: 35.775233,  Lng: -87.860617),  Route carried "on" structure: County highway 54,  Year Built: 1980,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 110 (year 2022),  Truck Traffic: 3%,  Average Future Daily Traffic: 176 (year 2041),  Design Load: HS 20,  Features Intersected: CROOKED CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.101,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.16m (3.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $181,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $272,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 680A0680001,  Location: 2.5 M. S. LOBELVILLE. (Lat: 35.716167,  Lng: -87.801100),  Route carried "on" structure: County highway 68,  Year Built: 1970,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 70 (year 2022),  Truck Traffic: 3%,  Average Future Daily Traffic: 112 (year 2041),  Features Intersected: PINKHOOK BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.537,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.8m (22.3ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 64.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.76m (2.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $113,000,  Roadway Improvement Cost: $12,000,  Total Project Cost: $170,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A0990001,  Location: 6 M. N. LOBELVILLE. (Lat: 35.812267,  Lng: -87.798489),  Route carried "on" structure: County highway 302,  Year Built: 1988,  Status: Open,  Structure Length: 11.19m (36.71ft),  Average Daily Traffic: 80 (year 2022),  Truck Traffic: 8%,  Average Future Daily Traffic: 128 (year 2041),  Design Load: HS 20,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.552,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 29.0m (95.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Very good,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 49.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 30.5 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: April 2021,  Underwater Inspection Date: August 2020,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 680A0990003,  Location: 7 M. N. LOBELVILLE. (Lat: 35.817067,  Lng: -87.795900),  Route carried "on" structure: County highway 302,  Year Built: 1993,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 80 (year 2022),  Truck Traffic: 8%,  Average Future Daily Traffic: 128 (year 2041),  Design Load: HS 20,  Features Intersected: POOLE LAKE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.196,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.1m (43.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.0m (26.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 52.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 680A1000001,  Location: 5 M. NW. LOBELVILLE. (Lat: 35.801450,  Lng: -87.811433),  Route carried "on" structure: County highway 304,  Year Built: 1972,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 80 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 128 (year 2041),  Features Intersected: TERRAPIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.327,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 58.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $144,000,  Roadway Improvement Cost: $15,000,  Total Project Cost: $217,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1010003,  Location: 3.5 M NW OF LOBELVILLE (Lat: 35.800650,  Lng: -87.827583),  Route carried "on" structure: County highway 101,  Year Built: 1984,  Status: Open,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 70 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 112 (year 2041),  Design Load: HS 20,  Features Intersected: RED BANK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.867,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 48.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 680A1020001,  Location: 6.2 M. N. LOBELVILLE. (Lat: 35.810111,  Lng: -87.805533),  Route carried "on" structure: County highway 303,  Year Built: 1984,  Status: Open,  Structure Length: 1.71m (5.61ft),  Average Daily Traffic: 100 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 160 (year 2041),  Design Load: HS 20,  Features Intersected: TERRAPIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.657,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 55.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 680A1020003,  Location: 6.5 M. NW. LOBELVILLE. (Lat: 35.808317,  Lng: -87.833000),  Route carried "on" structure: County highway 303,  Year Built: 1984,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 90 (year 2022),  Truck Traffic: 3%,  Average Future Daily Traffic: 144 (year 2041),  Design Load: HS 20,  Features Intersected: RED BANK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.073,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 55.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1020005,  Location: 6.5 M. NW. LOBELVILLE. (Lat: 35.808983,  Lng: -87.819133),  Route carried "on" structure: County highway 303,  Year Built: 1980,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 90 (year 2022),  Truck Traffic: 3%,  Average Future Daily Traffic: 144 (year 2041),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.237,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 55.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1080001,  Location: 2.5 M. N. LOBELVILLE (Lat: 35.795167,  Lng: -87.763383),  Route carried "on" structure: County highway 108,  Year Built: 1978,  Status: Open,  Structure Length: 1.86m (6.10ft),  Average Daily Traffic: 40 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 64 (year 2041),  Features Intersected: LOST CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.182,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 6.5m (21.3ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1090001,  Location: 5 M. N. LOBELVILLE. (Lat: 35.792800,  Lng: -87.774000),  Route carried "on" structure: County highway 109,  Year Built: 1989,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 60 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 96 (year 2039),  Design Load: HS 20,  Features Intersected: LOST CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.068,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 61.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1090003,  Location: RUSSELL CREEK RD (Lat: 35.766800,  Lng: -87.735733),  Route carried "on" structure: County highway 109,  Year Built: 1991,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 160 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 256 (year 2041),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.170,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $75,000,  Roadway Improvement Cost: $8,000,  Total Project Cost: $113,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 680A1110001,  Location: 1 M N OF LOBELVILLE (Lat: 35.784350,  Lng: -87.773433),  Route carried "on" structure: County highway 111,  Year Built: 1985,  Status: Open,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 300 (year 2022),  Truck Traffic: 6%,  Average Future Daily Traffic: 480 (year 2041),  Design Load: HS 20,  Features Intersected: BUFFALO RIVER OVERFLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021
Find on map >>   Show street view

Structure Number: 680A1110003,  Location: .1 M E JCT SR13&A111 (Lat: 35.784200,  Lng: -87.773667),  Route carried "on" structure: County highway 111,  Year Built: 1985,  Status: Open,  Structure Length: 9.14m (29.99ft),  Average Daily Traffic: 300 (year 2022),  Truck Traffic: 6%,  Average Future Daily Traffic: 480 (year 2041),  Design Load: HS 20,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.034,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.14m (29.99ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: April 2021,  Underwater Inspection Date: August 2020,  Bridge Improvement Cost: $1,431,000,  Roadway Improvement Cost: $144,000,  Total Project Cost: $2,147,000 ( Estimate for 2021),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 680A1130001,  Location: 1 M.E.SR13-LOBELVILLE (Lat: 35.749817,  Lng: -87.771500),  Route carried "on" structure: County highway 113,  Year Built: 1984,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 50 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 80 (year 2041),  Design Load: HS 20,  Features Intersected: LAGOON BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.177,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1130003,  Location: 1.5 M.E.SR13-LOBELVILLE (Lat: 35.748300,  Lng: -87.763200),  Route carried "on" structure: County highway 113,  Year Built: 1984,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 50 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 80 (year 2041),  Design Load: HS 20,  Features Intersected: LAGOON BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 58.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1180001,  Location: 4 M. SE.-LOBELVILLE. (Lat: 35.701083,  Lng: -87.747283),  Route carried "on" structure: County highway 118,  Year Built: 1991,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 260 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 416 (year 2041),  Design Load: HS 20,  Features Intersected: LOWER SINKING CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.018,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021
Find on map >>   Show street view

Structure Number: 680A1220001,  Location: 0.1 M. W. SR50- N. LINDEN (Lat: 35.701533,  Lng: -87.804383),  Route carried "on" structure: County highway 122,  Year Built: 1968,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 120 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 192 (year 2041),  Features Intersected: KINGS BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.106,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.8m (22.3ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 64.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $51,000,  Roadway Improvement Cost: $6,000,  Total Project Cost: $77,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A1230001,  Location: 1 M.W. SR13-N. OF LINDEN (Lat: 35.704350,  Lng: -87.816483),  Route carried "on" structure: County highway 123,  Year Built: 1979,  Status: Open,  Structure Length: 1.43m (4.69ft),  Average Daily Traffic: 80 (year 2022),  Truck Traffic: 7%,  Average Future Daily Traffic: 128 (year 2041),  Design Load: HS 20,  Features Intersected: KINGS BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.257,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 4 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 5.6m (18.4ft),  Out-to-Out Width: 6.9m (22.6ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 89.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 680A1300001,  Location: .3 M S SR50 @ CO LINE (Lat: 35.699550,  Lng: -87.747083),  Route carried "on" structure: County highway 130,  Year Built: 2008,  Status: Open,  Structure Length: 7.36m (24.15ft),  Average Daily Traffic: 130 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 208 (year 2041),  Design Load: HL 93,  Features Intersected: CANE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.084,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 24.4m (80.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 58.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 680A1340001,  Location: 3.5 M. N. LINDEN. (Lat: 35.664567,  Lng: -87.808083),  Route carried "on" structure: County highway 134,  Year Built: 1984,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 50 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 80 (year 2041),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.018,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 58.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 680A2250001,  Location: 2.4 M. NW. LOBELVILLE. (Lat: 35.790417,  Lng: -87.815833),  Route carried "on" structure: County highway 101,  Year Built: 1989,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 70 (year 2022),  Truck Traffic: 4%,  Average Future Daily Traffic: 112 (year 2041),  Design Load: HS 20,  Features Intersected: TERRAPIN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.615,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.8m (25.6ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 61.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 680A3070001,  Location: 1.5 M S OF SR 50 (Lat: 35.713250,  Lng: -87.864083),  Route carried "on" structure: County highway 307,  Year Built: 1993,  Status: Posted for load,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 20 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 32 (year 2041),  Features Intersected: S FK TOM'S CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.185,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 3.0m (9.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 4.3m (14.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 15.6 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 12.0 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.89m (6.20ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Critical Feature Inspection Date: April 2021,  Bridge Improvement Cost: $346,000,  Roadway Improvement Cost: $35,000,  Total Project Cost: $520,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 68S63890003,  Location: 7.2 M. NE. LINDEN. (Lat: 35.668483,  Lng: -87.793067),  Route carried "on" structure: County highway 1792,  Year Built: 1960,  Status: Posted for load,  Structure Length: 2.74m (8.99ft),  Average Daily Traffic: 113 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 181 (year 2042),  Design Load: HS 20,  Features Intersected: BRUSH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.203,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 6.9m (22.6ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Fair,  Operating Rating: 27.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 16.2 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 2.74m (8.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $173,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $260,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 68SR0130001,  Location: NEAR FLATWOODS COMMUNITY (Lat: 35.487917,  Lng: -87.834367),  Route carried "on" structure: State highway 13,  Year Built: 2013,  Status: Open,  Structure Length: 29.50m (96.78ft),  Average Daily Traffic: 666 (year 2020),  Truck Traffic: 9%,  Average Future Daily Traffic: 1,066 (year 2041),  Design Load: HL 93,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 4.86m (15.94ft),  Kilometerpoint: 2.784,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 45.7m (149.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.6m (41.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 58.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 68SR0130007,  Location: .3 MI. S. OF LOBLEVILLE (Lat: 35.691783,  Lng: -87.804167),  Route carried "on" structure: State highway 13,  Year Built: 1934,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 3,403 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 5,445 (year 2041),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 29.081,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $154,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $232,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 68SR0130009,  Location: IN LOBELVILLE CITY LIMITS (Lat: 35.702233,  Lng: -87.799617),  Route carried "on" structure: State highway 13,  Year Built: 1931,  Year Reconstructed: 2002,  Status: Open,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 2,535 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,056 (year 2041),  Design Load: HS 20,  Features Intersected: KING BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 30.320,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.6m (47.9ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Fair,  Channel: Very good,  Operating Rating: 59.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.49m (4.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $324,000,  Roadway Improvement Cost: $33,000,  Total Project Cost: $487,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 68SR0130011,  Location: IN LOBLEVILLE CITY LIMITS (Lat: 35.714417,  Lng: -87.796700),  Route carried "on" structure: State highway 13,  Year Built: 1956,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 2,610 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,176 (year 2041),  Design Load: HS 20,  Features Intersected: PIN HOOK BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 31.752,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $171,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $257,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 68SR0130013,  Location: IN LOBELVILLE CITY LIMITS (Lat: 35.744083,  Lng: -87.809733),  Route carried "on" structure: State highway 13,  Year Built: 1956,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 2,470 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 3,952 (year 2041),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.470,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 32.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.07m (6.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $532,000,  Roadway Improvement Cost: $54,000,  Total Project Cost: $799,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 68SR0130015,  Location: IN LOBLEVILLE CITY LIMIT (Lat: 35.754183,  Lng: -87.803817),  Route carried "on" structure: State highway 13,  Year Built: 1956,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 2,470 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 3,952 (year 2041),  Design Load: HS 20,  Features Intersected: EDWARDS BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 36.870,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $171,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $257,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 68SR0130017,  Location: 2.4 MI N. OF LOBELVILLE (Lat: 35.811000,  Lng: -87.777950),  Route carried "on" structure: State highway 13,  Year Built: 1952,  Status: Posted for load,  Structure Length: 30.57m (100.30ft),  Average Daily Traffic: 2,470 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 3,952 (year 2042),  Design Load: H 15,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 45.593,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Number Of Approach Spans: 28,  Length of Maximum Span: 24.4m (80.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 26.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 20.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 30.57m (100.30ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: April 2021,  Underwater Inspection Date: August 2020,  Bridge Improvement Cost: $7,870,000,  Roadway Improvement Cost: $788,000,  Total Project Cost: $11,806,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 68SR0130019,  Location: 1.5 MI N OF HUMPHREYS CO. (Lat: 35.819517,  Lng: -87.782933),  Route carried "on" structure: State highway 13,  Year Built: 1949,  Status: Open,  Structure Length: 2.07m (6.79ft),  Average Daily Traffic: 2,351 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 3,762 (year 2041),  Design Load: HS 20,  Features Intersected: SIMMONS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 46.639,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 7.0m (23.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 9.2m (30.2ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 62.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.84m (9.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $727,000,  Roadway Improvement Cost: $73,000,  Total Project Cost: $1,091,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 68SR0500001,  Location: 0.15 MI. E. OF SR-13 (Lat: 35.708233,  Lng: -87.797433),  Route carried "on" structure: State highway 438,  Year Built: 1975,  Status: Open,  Structure Length: 23.26m (76.31ft),  Average Daily Traffic: 847 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,355 (year 2041),  Design Load: HS 20,  Features Intersected: BUFFALO RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 32.638,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 8,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 33.4 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 22.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 60 months,  Inspection Date: April 2021,  Underwater Inspection Date: August 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 68SR0500003,  Location: 2 MILES W.OF SR013 (Lat: 35.708250,  Lng: -87.760017),  Route carried "on" structure: State highway 438,  Year Built: 1985,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 591 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 946 (year 2041),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 36.114,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.1m (33.1ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021
Find on map >>   Show street view

Structure Number: 68SR0500005,  Location: 2.5 MI. E. OF SR-13 (Lat: 35.704950,  Lng: -87.755383),  Route carried "on" structure: State highway 438,  Year Built: 1968,  Status: Open,  Structure Length: 9.51m (31.20ft),  Average Daily Traffic: 591 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 946 (year 2041),  Design Load: HS 20,  Features Intersected: CANE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 36.677,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 24.1m (79.1ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 64.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 68SR1000001,  Location: 4.3 MI. NE. OF LINDEN (Lat: 35.651567,  Lng: -87.767200),  Route carried "on" structure: State highway 100,  Year Built: 1930,  Status: Open,  Structure Length: 4.36m (14.30ft),  Average Daily Traffic: 682 (year 2020),  Truck Traffic: 8%,  Average Future Daily Traffic: 1,091 (year 2041),  Design Load: HS 20,  Features Intersected: BRUSH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.784,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 9.5m (31.2ft),  Out-to-Out Width: 10.2m (33.5ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 63.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Discuss Lobelville, Tennessee (TN) on our hugely popular Tennessee forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.