Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Monroe, Washington (WA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 25Number of bridges
  • 502ft / 153mTotal length
  • $106,850,000Total costs
  • 220,286Total average daily traffic
  • 17,444Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Monroe
  • No street view available for this location

New bridges in Monroe, WA - historical statistics
  • New bridges - historical statistics
  • 41950-1959
  • 11960-1969
  • 51970-1979
  • 21980-1989
  • 51990-1999
  • 22000-2009
  • 52010-2019
  • 12020-2022
Average Bridge Daily Traffic in Monroe, WA
Average Bridge Truck Traffic in Monroe, WA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 34.8%Very good
  • 43.5%Good
  • 8.7%Satisfactory
  • 4.3%Fair
  • 4.3%Poor
  • 4.3%Serious
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 30.4%Very good
  • 47.8%Good
  • 17.4%Satisfactory
  • 4.3%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 30.4%Very good
  • 52.2%Good
  • 13.0%Satisfactory
  • 4.3%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 11.8%Very good
  • 58.8%Good
  • 29.4%Satisfactory
Find on map >>   Show street view

Structure Number: 3695A,  Location: 0.4 E JCT SR 203 (Lat: 47.857278,  Lng: -121.961444),  Route carried "on" structure: US 2,  Year Built: 1950,  Status: Open,  Structure Length: 4.30m (14.11ft),  Average Daily Traffic: 20,905 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 30,270 (year 2039),  Design Load: HS 20,  Features Intersected: WOODS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 24.736,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Concrete continuous,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 17.1m (56.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 10.7m (35.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 38.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.30m (14.11ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,128,000,  Roadway Improvement Cost: $226,000,  Total Project Cost: $2,256,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 4825B,  Location: 4.1 N KING CO (Lat: 47.828806,  Lng: -121.970278),  Route carried "on" structure: State highway 203,  Year Built: 1954,  Status: Open,  Structure Length: 2.71m (8.89ft),  Average Daily Traffic: 12,084 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 17,497 (year 2039),  Design Load: HS 15,  Features Intersected: DRAINAGE OVERFLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.486,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.1m (33.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 10.4m (34.1ft)

Condition: Deck: Serious,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 29.5 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.71m (8.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $712,000,  Roadway Improvement Cost: $142,000,  Total Project Cost: $1,424,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 5294A,  Location: 5.1 N KING CO (Lat: 47.843194,  Lng: -121.969472),  Route carried "on" structure: State highway 203,  Year Built: 1957,  Status: Open,  Structure Length: 7.74m (25.39ft),  Average Daily Traffic: 14,746 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 21,352 (year 2039),  Design Load: HS 20,  Features Intersected: HASKELL SLOUGH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 37.079,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 17.1m (56.1ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 68.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.74m (25.39ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $2,032,000,  Roadway Improvement Cost: $406,000,  Total Project Cost: $4,064,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 5294B,  Location: 5.3 N KING CO (Lat: 47.845383,  Lng: -121.970367),  Route carried "on" structure: State highway 203,  Year Built: 1957,  Status: Open,  Structure Length: 17.74m (58.20ft),  Average Daily Traffic: 14,500 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 20,996 (year 2039),  Design Load: HS 20,  Features Intersected: SKYKOMISH RIVER
Minimum Vertical Clearance: 4.78m (15.68ft),  Kilometerpoint: 37.337,  Lanes on structure: 2,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 3,  Length of Maximum Span: 103.6m (339.9ft),  Curb or Sidewalk Widths: Left: 0.8m (2.6ft),  Right: 0.8m (2.6ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Deck: Poor,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 57.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 17.74m (58.20ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Critical Feature Inspection Date: March 2020,  Bridge Improvement Cost: $4,656,000,  Roadway Improvement Cost: $931,000,  Total Project Cost: $9,312,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Epoxy Overlay
Find on map >>   Show street view

Structure Number: 8761A,  Location: 9.1 E JCT SR 9 (Lat: 47.848528,  Lng: -122.007806),  Route carried "on" structure: State highway 522,  Year Built: 1970,  Status: Open,  Structure Length: 8.60m (28.22ft),  Average Daily Traffic: 14,856 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 21,511 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: W MAIN STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 37.256,  Lanes on structure: 2,  Lanes under structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 5 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 36.0m (118.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.3m (40.4ft)

Condition: Deck: Very good,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.60m (28.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,256,000,  Roadway Improvement Cost: $451,000,  Total Project Cost: $4,512,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 8761B,  Location: 10.0 E JCT SR 9 (Lat: 47.857306,  Lng: -121.991139),  Route carried "on" structure: State highway 522,  Year Built: 1970,  Status: Open,  Structure Length: 10.55m (34.61ft),  Average Daily Traffic: 10,503 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 15,208 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: 179TH SE & 154TH SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.850,  Lanes on structure: 2,  Lanes under structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 51.8m (169.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.6m (41.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.55m (34.61ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: May 2018,  Bridge Improvement Cost: $2,976,000,  Roadway Improvement Cost: $595,000,  Total Project Cost: $5,951,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 8857A,  Location: 10.6 E JCT SR 9 (Lat: 47.862361,  Lng: -121.984083),  Route carried "on" structure: State highway 522,  Year Built: 1971,  Status: Open,  Structure Length: 10.70m (35.10ft),  Average Daily Traffic: 13,686 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 19,817 (year 2039),  Design Load: HS 20+Mod,  Features Intersected: US 2 & BN RR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 39.606,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 32.0m (105.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.6m (41.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.70m (35.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,808,000,  Roadway Improvement Cost: $562,000,  Total Project Cost: $5,616,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 17938A,  Location: JCT US 2 (Lat: 47.862000,  Lng: -121.984194),  Route carried "on" structure: Ramp State highway 522,  Year Built: 2011,  Status: Open,  Structure Length: 21.49m (70.51ft),  Average Daily Traffic: 7,319 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 10,597 (year 2039),  Design Load: HL 93,  Features Intersected: BNSF RR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.531,  Lanes on structure: 1,  Owner: State Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 68.6m (225.1ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 52.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 40.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 21.49m (70.51ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Critical Feature Inspection Date: November 2021,  Bridge Improvement Cost: $4,089,000,  Roadway Improvement Cost: $818,000,  Total Project Cost: $8,178,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 18128C,  Location: 9.1 E JCT SR 9 (Lat: 47.848528,  Lng: -122.008139),  Route carried "on" structure: State highway 522,  Year Built: 2012,  Status: Open,  Structure Length: 8.53m (27.99ft),  Average Daily Traffic: 14,856 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 21,511 (year 2039),  Design Load: HL 93,  Features Intersected: W MAIN ST (164TH ST SE)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 37.240,  Lanes on structure: 2,  Lanes under structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 5 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 36.6m (120.1ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.7m (44.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 67.7 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 52.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.53m (27.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,464,000,  Roadway Improvement Cost: $493,000,  Total Project Cost: $4,928,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 18128D,  Location: 10.0 E JCT SR 9 (Lat: 47.857444,  Lng: -121.991222),  Route carried "on" structure: State highway 522,  Year Built: 2013,  Status: Open,  Structure Length: 10.42m (34.19ft),  Average Daily Traffic: 10,503 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 15,208 (year 2039),  Design Load: HL 93,  Features Intersected: 179TH SE & 154TH SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 38.850,  Lanes on structure: 2,  Lanes under structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 45.7m (149.9ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 50.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 39.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present desirable criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.42m (34.19ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: May 2018,  Bridge Improvement Cost: $3,010,000,  Roadway Improvement Cost: $602,000,  Total Project Cost: $6,019,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 18128E,  Location: 7.9 E JCT SR 9 (Lat: 47.834331,  Lng: -122.021981),  Route carried "on" structure: State highway 522,  Year Built: 2012,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 29,711 (year 2019),  Truck Traffic: 7%,  Average Future Daily Traffic: 43,021 (year 2039),  Design Load: HS 20,  Features Intersected: WILDLIFE CROSSING
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 35.309,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 25.0m (82.0ft),  Skew: 31 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 25.3m (83.0ft),  Out-to-Out Width: 39.0m (128.0ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 96.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 96.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.79m (2.59ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $437,000,  Roadway Improvement Cost: $87,000,  Total Project Cost: $874,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 81529,  Location: 1.0 NW JCT SR 203 (Lat: 47.821983,  Lng: -121.991253),  Route carried "on" structure: County highway 25190,  Year Built: 1970,  Year Reconstructed: 1989,  Status: Open,  Structure Length: 2.32m (7.61ft),  Average Daily Traffic: 146 (year 2017),  Truck Traffic: 21%,  Average Future Daily Traffic: 250 (year 2038),  Design Load: HS 15,  Features Intersected: RILEY SLOUGH,  Facility Carried by Structure: TUALCO LOOP RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.2m (17.1ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 5.3m (17.4ft),  Out-to-Out Width: 5.7m (18.7ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 34.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.62m (8.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $1,307,000,  Roadway Improvement Cost: $261,000,  Total Project Cost: $2,614,000 ( Estimate for 2014),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 83004,  Location: 2.9 N KING CO LINE (Lat: 47.809917,  Lng: -122.014036),  Route carried "on" structure: County highway 92655,  Year Built: 1983,  Status: Open,  Structure Length: 8.44m (27.69ft),  Average Daily Traffic: 1,754 (year 2019),  Truck Traffic: 12%,  Average Future Daily Traffic: 4,000 (year 2042),  Design Load: HS 20,  Features Intersected: TRIB. SNOQUALMIE RIVER,  Facility Carried by Structure: HIGH BRIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 9 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 34.1m (111.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.5m (31.2ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 8.75m (28.71ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $4,362,000,  Roadway Improvement Cost: $872,000,  Total Project Cost: $8,725,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 83106,  Location: 5.5 NW JCT SR 2 (Lat: 47.901394,  Lng: -121.875458),  Route carried "on" structure: Spur County highway 52100,  Year Built: 1960,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 529 (year 2019),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,000 (year 2042),  Design Load: H 15,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: OLD PIPELINE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 7.1m (23.3ft),  Out-to-Out Width: 7.4m (24.3ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 49.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.25m (4.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $623,000,  Roadway Improvement Cost: $125,000,  Total Project Cost: $1,246,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 85763,  Location: 3.5 NE JCT SR 2 (Lat: 47.869825,  Lng: -121.893575),  Route carried "on" structure: County highway 95784,  Year Built: 1990,  Status: Open,  Structure Length: 5.03m (16.50ft),  Average Daily Traffic: 3,232 (year 2018),  Truck Traffic: 12%,  Average Future Daily Traffic: 5,000 (year 2042),  Design Load: HS 20,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: FLORENCE ACRES RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.3m (37.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 28.3m (92.8ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.2m (43.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 59.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.33m (17.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Bridge Improvement Cost: $2,660,000,  Roadway Improvement Cost: $532,000,  Total Project Cost: $5,320,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 85889,  Location: 0.35 E MAIN ST (Lat: 47.855278,  Lng: -121.962722),  Route carried "on" structure: ServiceCity street 790,  Year Built: 1991,  Status: Open,  Structure Length: 2.26m (7.41ft),  Average Daily Traffic: 200 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 300 (year 2043),  Design Load: HS 20,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: BUCK ISLAND ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.3m (69.9ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 48.0 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 26.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.56m (8.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,277,000,  Roadway Improvement Cost: $255,000,  Total Project Cost: $2,554,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 85958,  Location: 4.9 NE JCT SR 2 (Lat: 47.902228,  Lng: -121.907842),  Route carried "on" structure: County highway 94758,  Year Built: 1991,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 1,481 (year 2019),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,000 (year 2043),  Design Load: HS 20,  Features Intersected: WEST FORK WOODS CREEK,  Facility Carried by Structure: WOODS CR RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.3m (46.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 83.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $882,000,  Roadway Improvement Cost: $176,000,  Total Project Cost: $1,763,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 86129,  Location: 4.6 N KING CO LINE (Lat: 47.821347,  Lng: -122.039536),  Route carried "on" structure: County highway 92655,  Year Built: 1994,  Status: Open,  Structure Length: 2.83m (9.28ft),  Average Daily Traffic: 1,688 (year 2019),  Truck Traffic: 14%,  Average Future Daily Traffic: 4,000 (year 2042),  Design Load: HS 25 or greater,  Features Intersected: RICCI CREEK,  Facility Carried by Structure: HIGH BRIDGE RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 25.9m (85.0ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 59.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.14m (10.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $1,566,000,  Roadway Improvement Cost: $313,000,  Total Project Cost: $3,131,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 86223,  Location: 1.3 W JCT SR 203 (Lat: 47.803458,  Lng: -122.003431),  Route carried "on" structure: County highway 92555,  Year Built: 1996,  Status: Open,  Structure Length: 12.98m (42.59ft),  Average Daily Traffic: 2,317 (year 2019),  Truck Traffic: 15%,  Average Future Daily Traffic: 4,000 (year 2042),  Design Load: HS 25 or greater,  Features Intersected: SNOQUALMIE RIVER,  Facility Carried by Structure: CRESCENT LAKE RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.1m (33.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 2,  Number Of Approach Spans: 1,  Length of Maximum Span: 71.6m (234.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 71.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 13.29m (43.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $6,627,000,  Roadway Improvement Cost: $1,325,000,  Total Project Cost: $13,254,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 86356,  Location: 0.1 N JCT SR2 (Lat: 47.868319,  Lng: -121.990750),  Route carried "on" structure: County highway 45230,  Year Built: 1985,  Status: Open,  Structure Length: 1.55m (5.09ft),  Average Daily Traffic: 3,540 (year 2019),  Truck Traffic: 11%,  Average Future Daily Traffic: 5,000 (year 2043),  Design Load: HS 20,  Features Intersected: PEDESTRIAN TUNNEL,  Facility Carried by Structure: 179TH AV SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Aluminum, Iron,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.4m (21.0ft)

Condition: Culverts: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 72.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.86m (6.10ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $927,000,  Roadway Improvement Cost: $185,000,  Total Project Cost: $1,854,000 ( Estimate for 2014)
Find on map >>   Show street view

Structure Number: 87174,  Location: 0.3 NE JCT SR2 (Lat: 47.859700,  Lng: -121.959289),  Route carried "on" structure: County highway 92666,  Year Built: 2004,  Status: Open,  Structure Length: 2.50m (8.20ft),  Average Daily Traffic: 10,056 (year 2017),  Truck Traffic: 9%,  Average Future Daily Traffic: 15,000 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: OLD OWEN RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 23.2m (76.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 60.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.80m (9.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,398,000,  Roadway Improvement Cost: $280,000,  Total Project Cost: $2,797,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Galvanized Reinforcing
Find on map >>   Show street view

Structure Number: 87552,  Location: 4.6 NE JCT SR 2 (Lat: 47.877644,  Lng: -121.873658),  Route carried "on" structure: County highway 95784,  Year Built: 2007,  Status: Open,  Structure Length: 2.50m (8.20ft),  Average Daily Traffic: 1,783 (year 2018),  Truck Traffic: 15%,  Average Future Daily Traffic: 3,000 (year 2041),  Design Load: HS 25 or greater,  Features Intersected: WOODS CREEK,  Facility Carried by Structure: FLORENCE ACRES RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 23.2m (76.1ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.80m (9.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $1,398,000,  Roadway Improvement Cost: $280,000,  Total Project Cost: $2,797,000 ( Estimate for 2014),  Deck Structure Type: Other,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Deck Protection: Galvanized Reinforcing
Find on map >>   Show street view

Structure Number: 89114,  Location: 1.0 N SR2 (Lat: 47.879939,  Lng: -122.007408),  Route carried "on" structure: Spur City street 790,  Year Built: 2019,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 100 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 200 (year 2041),  Design Load: HL 93,  Features Intersected: Unnamed Wetland,  Facility Carried by Structure: 167th Ave SE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 9.6m (31.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 41.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.07m (3.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $532,000,  Roadway Improvement Cost: $106,000,  Total Project Cost: $1,064,000 ( Estimate for 2014),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 89158,  Location: 1.4 SW JCT SR 203 (Lat: 47.820058,  Lng: -121.986381),  Route carried "on" structure: County highway 92555,  Year Built: 2020,  Status: Open,  Structure Length: 6.31m (20.70ft),  Average Daily Traffic: 1,136 (year 2017),  Truck Traffic: 12%,  Average Future Daily Traffic: 1,500 (year 2039),  Design Load: HL 93,  Features Intersected: RILEY SLOUGH-SKYKOMISH R,  Facility Carried by Structure: TUALCO RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.001,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.9m (85.0ft),  Curb-To-Curb Width: 9.9m (32.5ft),  Out-to-Out Width: 10.9m (35.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 60.6 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 39.2 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.61m (21.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $3,298,000,  Roadway Improvement Cost: $660,000,  Total Project Cost: $6,597,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Galvanized Reinforcing
Find on map >>   Show street view

Structure Number: 8857A,  Location: 8.3 E JCT SR 9 (Lat: 47.862361,  Lng: -121.984083),  Route carried "under" structure: US 2,  Year Built: 1971,  Structure Length: 0. m,  Average Daily Traffic: 28,655 (year 2019),  Truck Traffic: 7%,  Features Intersected: US 2 & BN RR
Minimum Vertical Clearance: 7.87m (25.82ft),  Kilometerpoint: 22.965,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 32.0m (105.0ft)

Discuss Monroe, Washington (WA) on our hugely popular Washington forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.