  • National Bridge Inventory (NBI) Statistics
  • 20Number of bridges
  • 272ft / 82.6mTotal length
  • $29,544,000Total costs
  • 24,039Total average daily traffic
  • 2,179Total average daily truck traffic
  • 32,621Total future (year 2030) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for River Falls
  • No street view available for this location

New bridges in River Falls, AL - historical statistics
  • New bridges - historical statistics
  • 11920-1929
  • 41960-1969
  • 21970-1979
  • 21980-1989
  • 51990-1999
  • 62000-2009
Reconstructed bridges in River Falls, AL - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11970-1979
  • 11980-1989
  • 21990-1999
  • 12000-2009
Average Bridge Daily Traffic in River Falls, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 5.6%Excellent
  • 33.3%Very good
  • 27.8%Good
  • 22.2%Satisfactory
  • 11.1%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 11.1%Excellent
  • 27.8%Very good
  • 22.2%Good
  • 22.2%Satisfactory
  • 16.7%Fair
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 22.2%Very good
  • 27.8%Good
  • 27.8%Satisfactory
  • 22.2%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 25.0%Very good
  • 25.0%Good
  • 30.0%Satisfactory
  • 20.0%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 50.0%Good
  • 50.0%Satisfactory
Find on map >>   Show street view

Structure Number: 8014,  Location: 2 MILES N.OF RIVER FALLS (Lat: 31.375700,  Lng: -86.545000),  Route carried "on" structure: County highway 59,  Year Built: 1963,  Status: Open,  Structure Length: 0.62m (2.03ft),  Average Daily Traffic: 150 (year 1994),  Truck Traffic: 5%,  Average Future Daily Traffic: 205 (year 2032),  Design Load: H 15,  Features Intersected: GUNTER MILL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 67.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $273,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $300,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 8406,  Location: 3 MI WEST OF GANTT (Lat: 31.414467,  Lng: -86.534958),  Route carried "on" structure: County highway 82,  Year Built: 1964,  Status: Posted for load,  Structure Length: 17.25m (56.59ft),  Average Daily Traffic: 730 (year 1994),  Truck Traffic: 5%,  Average Future Daily Traffic: 937 (year 2030),  Design Load: H 15,  Features Intersected: PATSALIGA RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Skew: 3 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Number Of Approach Spans: 9,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 17.96m (58.92ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2021,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $3,572,000,  Roadway Improvement Cost: $357,000,  Total Project Cost: $3,929,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 11304,  Location: 1/2 MI SW US 84 (Lat: 31.348503,  Lng: -86.602544),  Route carried "on" structure: County highway 21,  Year Built: 1928,  Year Reconstructed: 1975,  Status: Open,  Structure Length: 1.74m (5.71ft),  Average Daily Traffic: 110 (year 1994),  Truck Traffic: 5%,  Average Future Daily Traffic: 143 (year 2030),  Design Load: H 15,  Features Intersected: CAMP CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.7m (25.3ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 45.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 28.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.44m (8.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $418,000,  Roadway Improvement Cost: $42,000,  Total Project Cost: $460,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 13599,  Location: 2.2 MI.W.US 29 (Lat: 31.338133,  Lng: -86.521867),  Route carried "on" structure: US 84,  Year Built: 1985,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 8,630 (year 2013),  Truck Traffic: 10%,  Average Future Daily Traffic: 11,578 (year 2033),  Design Load: HS 20,  Features Intersected: PRESTWOOD MILL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 208.470,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.9m (62.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Fair,  Culverts: Good,  Operating Rating: 60.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $968,000,  Roadway Improvement Cost: $97,000,  Total Project Cost: $1,065,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 13808,  Location: 1 MI E OF PLAINER MILL R (Lat: 31.365053,  Lng: -86.572931),  Route carried "on" structure: County highway ,  Year Built: 1961,  Year Reconstructed: 1986,  Status: Posted for load,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 140 (year 1994),  Truck Traffic: 1%,  Average Future Daily Traffic: 172 (year 2030),  Features Intersected: NO NAME BRANCH,  Facility Carried by Structure: COUNTY DIRT RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 17.2 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 12.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.59m (5.22ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: October 2020,  Other Special Inspection Date: October 2021,  Bridge Improvement Cost: $174,000,  Roadway Improvement Cost: $17,000,  Total Project Cost: $191,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 15628,  Location: 4 MI. E. RED LEVEL (Lat: 31.417811,  Lng: -86.543700),  Route carried "on" structure: County highway ,  Year Built: 1975,  Status: Posted for load,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 50 (year 1994),  Average Future Daily Traffic: 70 (year 2030),  Features Intersected: PATSALIGA CREEK BRANCH,  Facility Carried by Structure: COUNTY DIRT RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.8m (51.8ft),  Curb-To-Curb Width: 3.7m (12.1ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 4.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 3.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.27m (7.45ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: Febuary 2021,  Other Special Inspection Date: Febuary 2022,  Bridge Improvement Cost: $187,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $206,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 15762,  Location: 1 MI W. OF ANDALUSIA (Lat: 31.348383,  Lng: -86.530933),  Route carried "on" structure: US 84,  Year Built: 1993,  Status: Open,  Structure Length: 22.40m (73.49ft),  Average Daily Traffic: 10,280 (year 2013),  Truck Traffic: 10%,  Average Future Daily Traffic: 13,791 (year 2033),  Design Load: HS 20,  Features Intersected: CONECUH RIVER
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 206.920,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 24.4m (80.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 6,  Length of Maximum Span: 42.7m (140.1ft),  Curb-To-Curb Width: 23.7m (77.8ft),  Out-to-Out Width: 24.5m (80.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 50.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 22.40m (73.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $12,289,000,  Roadway Improvement Cost: $1,229,000,  Total Project Cost: $13,518,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 15883,  Location: 1 MI. S US 84 (Lat: 31.338767,  Lng: -86.581581),  Route carried "on" structure: County highway ,  Year Built: 1993,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 140 (year 1994),  Truck Traffic: 1%,  Average Future Daily Traffic: 172 (year 2030),  Design Load: HS 20,  Features Intersected: CAMP CREEK,  Facility Carried by Structure: CO. DIRT ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 71.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $317,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $349,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 1711,  Location: 3.2KM N OF ANDALUSIA (Lat: 31.346328,  Lng: -86.504392),  Route carried "on" structure: County highway ,  Year Built: 1996,  Status: Open,  Structure Length: 2.07m (6.79ft),  Average Daily Traffic: 140 (year 1994),  Truck Traffic: 2%,  Average Future Daily Traffic: 179 (year 2030),  Design Load: HS 20,  Features Intersected: PRESTWOOD CREEK,  Facility Carried by Structure: COUNTY DIRT ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 75.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 2.84m (9.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $526,000,  Roadway Improvement Cost: $53,000,  Total Project Cost: $579,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 17243,  Location: 1/2 M EAST OLD HWY 55 (Lat: 31.365611,  Lng: -86.531278),  Route carried "on" structure: County highway 59,  Year Built: 1970,  Year Reconstructed: 1998,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 440 (year 1995),  Truck Traffic: 14%,  Average Future Daily Traffic: 654 (year 2032),  Design Load: HS 20,  Features Intersected: GUNTER MILL CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 74.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $351,000,  Roadway Improvement Cost: $35,000,  Total Project Cost: $386,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 17245,  Location: 1 MI. SW GNATT (Lat: 31.385833,  Lng: -86.507500),  Route carried "on" structure: County highway 59,  Year Built: 1998,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 440 (year 1994),  Truck Traffic: 14%,  Average Future Daily Traffic: 574 (year 2035),  Design Load: HS 20,  Features Intersected: BRANCH INTO POINT A LAKE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 75.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.38m (4.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $283,000,  Roadway Improvement Cost: $28,000,  Total Project Cost: $311,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 17413,  Location: N OF 84 IN RIVER FALLS (Lat: 31.361622,  Lng: -86.538556),  Route carried "on" structure: County highway 107,  Year Built: 1999,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 320 (year 1994),  Truck Traffic: 5%,  Average Future Daily Traffic: 431 (year 2035),  Design Load: HS 20,  Features Intersected: UNNAMED TRIBUTARY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Excellent,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 67.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.38m (4.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $283,000,  Roadway Improvement Cost: $28,000,  Total Project Cost: $311,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 17481,  Location: 16 TH. SECTION ROAD (Lat: 31.393331,  Lng: -86.552447),  Route carried "on" structure: County highway 23,  Year Built: 1965,  Year Reconstructed: 1998,  Status: Open,  Structure Length: 5.18m (16.99ft),  Average Daily Traffic: 210 (year 1994),  Truck Traffic: 8%,  Average Future Daily Traffic: 287 (year 2035),  Design Load: HS 20,  Features Intersected: BUCK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 71.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 6.21m (20.37ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,149,000,  Roadway Improvement Cost: $115,000,  Total Project Cost: $1,264,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 17519,  Location: 1.8MI NORTH OF 84WEST (Lat: 31.367633,  Lng: -86.590650),  Route carried "on" structure: County highway 21,  Year Built: 2001,  Status: Open,  Structure Length: 2.07m (6.79ft),  Average Daily Traffic: 163 (year 2001),  Truck Traffic: 12%,  Average Future Daily Traffic: 187 (year 2030),  Design Load: HS 20,  Features Intersected: ADAMS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Good,  Operating Rating: 71.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.84m (9.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $584,000,  Roadway Improvement Cost: $58,000,  Total Project Cost: $642,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 17525,  Location: 1.7 MILES SOUTH OF 84 (Lat: 31.325708,  Lng: -86.555664),  Route carried "on" structure: County highway 59,  Year Built: 2001,  Status: Open,  Structure Length: 4.57m (14.99ft),  Average Daily Traffic: 610 (year 2000),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,037 (year 2030),  Design Load: HS 20,  Features Intersected: ADAMS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 78.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 46.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.57m (18.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $1,184,000,  Roadway Improvement Cost: $118,000,  Total Project Cost: $1,302,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 17946,  Location: 1MILE NE RIVER FALLS (Lat: 31.369800,  Lng: -86.524214),  Route carried "on" structure: County highway 59,  Year Built: 2002,  Status: Open,  Structure Length: 14.02m (46.00ft),  Average Daily Traffic: 832 (year 2001),  Truck Traffic: 4%,  Average Future Daily Traffic: 1,413 (year 2034),  Design Load: HS 20,  Features Intersected: PATSALIGA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 35.1m (115.2ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Good,  Channel: Good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 14.82m (48.62ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 48 months,  Inspection Date: August 2020,  Underwater Inspection Date: August 2020,  Bridge Improvement Cost: $3,048,000,  Roadway Improvement Cost: $305,000,  Total Project Cost: $3,353,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 18202,  Location: 1.5M N84 ON CR68 (Lat: 31.347911,  Lng: -86.504986),  Route carried "on" structure: County highway ,  Year Built: 2000,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 264 (year 1999),  Average Future Daily Traffic: 344 (year 2030),  Design Load: HS 20,  Features Intersected: PRESTWOOD CREEK,  Facility Carried by Structure: COUNTY DIRTROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Very good,  Superstructure: Excellent,  Substructure: Very good,  Channel: Good,  Operating Rating: 71.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.38m (4.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $255,000,  Roadway Improvement Cost: $26,000,  Total Project Cost: $281,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 18428,  Location: 1 1/2 MI SW OF RIVER FALL (Lat: 31.334444,  Lng: -86.560092),  Route carried "on" structure: County highway ,  Year Built: 2001,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 210 (year 1994),  Average Future Daily Traffic: 242 (year 2030),  Design Load: HS 20,  Features Intersected: ADAMS CREEK,  Facility Carried by Structure: COUNTY DIRTROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.4m (27.6ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Very good,  Operating Rating: 74.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $340,000,  Roadway Improvement Cost: $34,000,  Total Project Cost: $374,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 19662,  Location: 4 MILE WEST OF ANDALUSIA (Lat: 31.293997,  Lng: -86.577814),  Route carried "on" structure: County highway ,  Year Built: 2005,  Status: Open,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 50 (year 2006),  Average Future Daily Traffic: 75 (year 2030),  Design Load: HS 20,  Features Intersected: NO NAME BRACH,  Facility Carried by Structure: COUNTY DIRT ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 74.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $316,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $348,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 20037,  Location: 1 MI EAST OF RIVER FALLS (Lat: 31.360278,  Lng: -86.528611),  Route carried "on" structure: County highway 59,  Year Built: 1983,  Year Reconstructed: 2007,  Status: Posted for load,  Structure Length: 2.29m (7.51ft),  Average Daily Traffic: 130 (year 1994),  Average Future Daily Traffic: 130 (year 2032),  Features Intersected: NO NAME CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 5.1m (16.7ft),  Out-to-Out Width: 5.1m (16.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 16.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 12.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.11m (10.20ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: January 2021,  Other Special Inspection Date: January 2022,  Bridge Improvement Cost: $341,000,  Roadway Improvement Cost: $34,000,  Total Project Cost: $375,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber