Bridge Statistics for Shade Gap, Pennsylvania (PA)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 10Number of bridges
  • 46ft / 13.6mTotal length
  • $4,210,000Total costs
  • 10,530Total average daily traffic
  • 749Total average daily truck traffic
  • 12,368Total future (year 2032) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Shade Gap
  • No street view available for this location

New bridges in Shade Gap, PA - historical statistics
  • New bridges - historical statistics
  • 1Before 1900
  • 11920-1929
  • 31930-1939
  • 11940-1949
  • 31960-1969
  • 11990-1999
Reconstructed bridges in Shade Gap, PA - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11970-1979
  • 01980-1989
  • 21990-1999
  • 32000-2009
  • 12010-2019
  • 12020-2022
Average Bridge Daily Traffic in Shade Gap, PA
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 11.1%Excellent
  • 22.2%Very good
  • 22.2%Good
  • 11.1%Satisfactory
  • 33.3%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 44.4%Good
  • 11.1%Satisfactory
  • 22.2%Fair
  • 11.1%Poor
  • 11.1%Serious
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 11.1%Very good
  • 33.3%Good
  • 44.4%Satisfactory
  • 11.1%Fair
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 30.0%Good
  • 50.0%Satisfactory
  • 20.0%Fair
Find on map >>   Show street view

Structure Number: 18611,  Location: 168 FEET NORTH OF SR 2006 (Lat: 40.187694,  Lng: -77.856064),  Route carried "on" structure: State highway 35,  Year Built: 1935,  Status: Open,  Structure Length: 2.04m (6.69ft),  Average Daily Traffic: 697 (year 2022),  Truck Traffic: 8%,  Average Future Daily Traffic: 976 (year 2032),  Design Load: H 20,  Features Intersected: SHADE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.624,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 9.8m (32.2ft),  Curb-To-Curb Width: 7.0m (23.0ft),  Out-to-Out Width: 8.0m (26.2ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 41.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.60m (8.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $70,000,  Roadway Improvement Cost: $264,000,  Total Project Cost: $947,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 18665,  Location: 1.2 MILE NORTH OF SR 2007 (Lat: 40.168814,  Lng: -77.863494),  Route carried "on" structure: US 522,  Year Built: 1966,  Year Reconstructed: 2008,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 2,205 (year 2020),  Truck Traffic: 11%,  Average Future Daily Traffic: 2,796 (year 2032),  Design Load: H 20,  Features Intersected: TANNERY RUN
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 10.054,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 4.6m (15.1ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Inventory Rating: 99.8 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.90m (2.95ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $28,000,  Roadway Improvement Cost: $136,000,  Total Project Cost: $376,000
Find on map >>   Show street view

Structure Number: 18666,  Location: 1.3 MILE NORTH OF TR 641 (Lat: 40.192244,  Lng: -77.884603),  Route carried "on" structure: US 522,  Year Built: 1968,  Year Reconstructed: 2004,  Status: Open,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 4,432 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,895 (year 2032),  Design Load: HS 20+Mod,  Features Intersected: CRAIG RUN
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 14.405,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 5 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.0m (45.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 12.3m (40.4ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 67.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric
Find on map >>   Show street view

Structure Number: 18683,  Location: 0.5 MILE EAST OF TR 35 (Lat: 40.179042,  Lng: -77.855517),  Route carried "on" structure: State highway 641,  Year Built: 1933,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 2,182 (year 2022),  Truck Traffic: 5%,  Average Future Daily Traffic: 2,629 (year 2032),  Design Load: H 20,  Features Intersected: TR. SHADE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.043,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.4m (21.0ft),  Curb-To-Curb Width: 9.2m (30.2ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Fair,  Operating Rating: 47.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.90m (2.95ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $35,000,  Roadway Improvement Cost: $196,000,  Total Project Cost: $469,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 18805,  Location: 1 MI.W.OF SHADE GAP (Lat: 40.186792,  Lng: -77.855203),  Route carried "on" structure: State highway ,  Year Built: 1961,  Year Reconstructed: 2010,  Status: Open,  Structure Length: 1.95m (6.40ft),  Average Daily Traffic: 381 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 247 (year 2032),  Design Load: HS 20,  Features Intersected: SHADE CREEK,  Facility Carried by Structure: SR 2006
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.9m (62.0ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 10.2m (33.5ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 93.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.70m (8.86ft),  Designated Inspection Frequency: Every 48 months,  Inspection Date: December 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 18807,  Location: 1.5 MI.N.OF DECORUM (Lat: 40.120697,  Lng: -77.861044),  Route carried "on" structure: State highway ,  Year Built: 1937,  Year Reconstructed: 2006,  Status: Open,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 129 (year 2022),  Truck Traffic: 9%,  Average Future Daily Traffic: 173 (year 2032),  Design Load: HL 93,  Features Intersected: TRIB TO NB L AUGHWICK CR,  Facility Carried by Structure: T312 PLEASANT HILL
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.011,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Fair,  Operating Rating: 82.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.10m (3.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $41,000,  Roadway Improvement Cost: $232,000,  Total Project Cost: $558,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Galvanized Reinforcing
Find on map >>   Show street view

Structure Number: 18908,  Location: 0.75 MI NW OF SHADE GAP (Lat: 40.188989,  Lng: -77.874169),  Route carried "on" structure: City street ,  Year Built: 1990,  Year Reconstructed: 2020,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 99 (year 2020),  Truck Traffic: 1%,  Average Future Daily Traffic: 127 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: SHADE CREEK,  Facility Carried by Structure: T358, COVERED BR R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Excellent,  Superstructure: Fair,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 95.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.60m (5.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $15,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $206,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 18909,  Location: 2 Miles NW of Shade Gap (Lat: 40.205908,  Lng: -77.878072),  Route carried "on" structure: City street ,  Year Built: 1896,  Year Reconstructed: 2012,  Status: Posted for load,  Structure Length: 2.04m (6.69ft),  Average Daily Traffic: 143 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 183 (year 2041),  Design Load: H 20,  Features Intersected: SHADE CREEK,  Facility Carried by Structure: T358, COVERED BR R
Minimum Vertical Clearance: 3.35m (10.99ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.2m (63.0ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 3.8m (12.5ft),  Out-to-Out Width: 4.1m (13.5ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 2.60m (8.53ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: November 2020,  Other Special Inspection Date: November 2020,  Bridge Improvement Cost: $70,000,  Roadway Improvement Cost: $264,000,  Total Project Cost: $947,000,  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 18913,  Location: 2 MI.SE.OF SHADE GAP (Lat: 40.167986,  Lng: -77.844717),  Route carried "on" structure: City street ,  Year Built: 1920,  Year Reconstructed: 1990,  Status: Posted for load,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 50 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 70 (year 2041),  Design Load: HS 25 or greater,  Features Intersected: SHADE CREEK,  Facility Carried by Structure: T316, APPLEBY ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: Town or Township Highway Agency,  Approaching Roadway Width: 4.0m (13.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 4.5m (14.8ft),  Out-to-Out Width: 4.8m (15.7ft)

Condition: Deck: Fair,  Superstructure: Serious,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 13.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 8.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.20m (3.94ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 6 months,  Inspection Date: June 2021,  Other Special Inspection Date: June 2021,  Deck Structure Type: Open Grating
Find on map >>   Show street view

Structure Number: 18914,  Location: 1.5 MI.NE.OF SHADE GAP (Lat: 40.195161,  Lng: -77.845814),  Route carried "on" structure: City street ,  Year Built: 1948,  Year Reconstructed: 1981,  Status: Posted for load,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 212 (year 2021),  Truck Traffic: 1%,  Average Future Daily Traffic: 272 (year 2041),  Design Load: HS 20,  Features Intersected: THREE LICK CREEK,  Facility Carried by Structure: T-344,HARPERS ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.6m (38.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 35.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 20.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 1.50m (4.92ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2021,  Other Special Inspection Date: June 2021,  Bridge Improvement Cost: $52,000,  Roadway Improvement Cost: $264,000,  Total Project Cost: $707,000,  Deck Structure Type: Open Grating
Discuss Shade Gap, Pennsylvania (PA) on our hugely popular Pennsylvania forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.