Bridge Statistics for Temple, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 10Number of bridges
  • 135ft / 41.2mTotal length
  • $11,363,000Total costs
  • 5,840Total average daily traffic
  • 856Total average daily truck traffic
  • 9,304Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Temple
  • No street view available for this location

New bridges in Temple, OK - historical statistics
  • New bridges - historical statistics
  • 31930-1939
  • 41980-1989
  • 11990-1999
  • 22010-2019
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 14.3%Very good
  • 71.4%Good
  • 14.3%Satisfactory
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 85.7%Very good
  • 14.3%Satisfactory
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 14.3%Very good
  • 57.1%Good
  • 28.6%Satisfactory
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 30.0%Very good
  • 40.0%Good
  • 10.0%Satisfactory
  • 20.0%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 33.3%Very good
  • 33.3%Satisfactory
  • 33.3%Fair
Find on map >>   Show street view

Structure Number: 4114,  Location: 4.3 S & E JCT SH65 (Lat: 34.231667,  Lng: -98.202222),  Route carried "on" structure: State highway 5,  Year Built: 1934,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 540 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 864 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.854,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 11.3m (37.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 54.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 6731,  Location: 3. E 2.4 N OF SH 5 (Lat: 34.309472,  Lng: -98.261469),  Route carried "on" structure: County highway 1755C,  Year Built: 1939,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.3m (24.0ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 6783,  Location: 2. S 2.7 E OF SH 5A (Lat: 34.246108,  Lng: -98.285722),  Route carried "on" structure: County highway E1910,  Year Built: 1939,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 37.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.66m (8.73ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $136,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2233,  Location: 3.8 MI W JCT SH 65 (Lat: 34.275000,  Lng: -98.301944),  Route carried "on" structure: State highway 5,  Year Built: 1989,  Status: Open,  Structure Length: 3.05m (10.01ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 18.762,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.23m (20.44ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $533,000,  Roadway Improvement Cost: $879,000,  Total Project Cost: $1,492,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22385,  Location: 3.4 MI W JCT SH 65 (Lat: 34.275000,  Lng: -98.294722),  Route carried "on" structure: State highway 5,  Year Built: 1989,  Status: Open,  Structure Length: 6.58m (21.59ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: HS 20,  Features Intersected: EAST CACHE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 19.422,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 22.9m (75.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.37m (30.74ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $756,000,  Roadway Improvement Cost: $1,248,000,  Total Project Cost: $2,118,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22387,  Location: 2.6 MI W JCT SH 65 (Lat: 34.275278,  Lng: -98.283333),  Route carried "on" structure: State highway 5,  Year Built: 1989,  Status: Open,  Structure Length: 6.89m (22.60ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.484,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 22.9m (75.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 69.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.60m (31.50ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $773,000,  Roadway Improvement Cost: $1,275,000,  Total Project Cost: $2,163,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22413,  Location: 2.8 MI W JCT SH 65 (Lat: 34.275278,  Lng: -98.288333),  Route carried "on" structure: State highway 5,  Year Built: 1989,  Status: Open,  Structure Length: 18.29m (60.01ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: HS 20,  Features Intersected: EAST CACHE CREEK O'FLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.015,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 30.5m (100.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Good,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 18.29m (60.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2020,  Bridge Improvement Cost: $1,345,000,  Roadway Improvement Cost: $2,219,000,  Total Project Cost: $3,766,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 23468,  Location: 8. S 2.3 E OF SH 53 (Lat: 34.246264,  Lng: -98.187208),  Route carried "on" structure: County highway E1910,  Year Built: 1993,  Status: Open,  Structure Length: 2.23m (7.32ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 6 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.3m (69.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Channel: Very good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.28m (17.32ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $270,000,  Roadway Improvement Cost: $148,000,  Total Project Cost: $430,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 29341,  Location: 3E 2.7S OF SH-5A / SH-5 (Lat: 34.235556,  Lng: -98.278889),  Route carried "on" structure: County highway N2640,  Year Built: 2011,  Status: Open,  Structure Length: 0.67m (2.20ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 120 (year 2040),  Design Load: HS 20,  Features Intersected: TRIB TO EAST CACHE CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.4m (11.2ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 12.2m (40.0ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 54.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.74m (2.43ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $225,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $300,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 3122,  Location: 3E 4.7S JCT SH53/SH64 (Lat: 34.294178,  Lng: -98.174194),  Route carried "on" structure: County highway N2700,  Year Built: 2017,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HL 93,  Features Intersected: WAURIKA LAKE TRIB.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.2m (49.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 57.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Discuss Temple, Oklahoma (OK) on our hugely popular Oklahoma forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.