Bridge Statistics for Williston, Tennessee (TN)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 10Number of bridges
  • 52ft / 15.9mTotal length
  • $1,142,000Total costs
  • 7,379Total average daily traffic
  • 288Total average daily truck traffic
  • 13,617Total future (year 2040) average daily traffic
  • National Bridge Inventory (NBI) Registered Bridges for Williston
  • No street view available for this location

New bridges in Williston, TN - historical statistics
  • New bridges - historical statistics
  • 21950-1959
  • 51960-1969
  • 11990-1999
  • 12010-2019
  • 12020-2022
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 16.7%Very good
  • 16.7%Good
  • 50.0%Satisfactory
  • 16.7%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 16.7%Very good
  • 16.7%Good
  • 66.7%Satisfactory
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 16.7%Very good
  • 16.7%Good
  • 16.7%Satisfactory
  • 33.3%Fair
  • 16.7%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 20.0%Good
  • 70.0%Satisfactory
  • 10.0%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 25.0%Good
  • 50.0%Satisfactory
  • 25.0%Fair
Find on map >>   Show street view

Structure Number: 240A1580001,  Location: 2.0 MI NE JCT SR76&SR193 (Lat: 35.169917,  Lng: -89.338472),  Route carried "on" structure: County highway 2707,  Year Built: 1964,  Status: Posted for load,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 549 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 878 (year 2041),  Design Load: H 15,  Features Intersected: BLACK CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.154,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 8.8m (28.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 240A1790001,  Location: 2.9 MI SW JCT SR76&SR193 (Lat: 35.148250,  Lng: -89.417889),  Route carried "on" structure: County highway 179,  Year Built: 1964,  Status: Posted for load,  Structure Length: 1.71m (5.61ft),  Average Daily Traffic: 10 (year 2022),  Truck Traffic: 1%,  Average Future Daily Traffic: 16 (year 2041),  Features Intersected: SHAWS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.645,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 4.9m (16.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 5.7m (18.7ft),  Out-to-Out Width: 6.1m (20.0ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 20.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 15.3 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $104,000,  Roadway Improvement Cost: $11,000,  Total Project Cost: $157,000 ( Estimate for 2021),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 240A3500001,  Location: 3.0 MI SE JCT SR76&SR194 (Lat: 35.115500,  Lng: -89.360028),  Route carried "on" structure: County highway 350,  Year Built: 1960,  Status: Posted for load,  Structure Length: 1.19m (3.90ft),  Average Daily Traffic: 150 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 240 (year 2040),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.426,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 6.6m (21.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 23.4 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 12.6 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.19m (3.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $95,000,  Roadway Improvement Cost: $10,000,  Total Project Cost: $143,000 ( Estimate for 2020),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 240A3500003,  Location: 2.9 MI SE JCT SR76&SR193 (Lat: 35.114556,  Lng: -89.368667),  Route carried "on" structure: County highway 350,  Year Built: 1965,  Status: Posted for load,  Structure Length: 2.04m (6.69ft),  Average Daily Traffic: 150 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 240 (year 2041),  Design Load: H 15,  Features Intersected: WATKINS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.235,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 8.5m (27.9ft),  Curb-To-Curb Width: 6.2m (20.3ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.04m (6.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $159,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $239,000 ( Estimate for 2021),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 240A3500005,  Location: WATKINS DR. (Lat: 35.114556,  Lng: -89.390917),  Route carried "on" structure: County highway 350,  Year Built: 2016,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 150 (year 2022),  Truck Traffic: 2%,  Average Future Daily Traffic: 240 (year 2040),  Design Load: HL 93,  Features Intersected: HARGISS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.282,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 20.7m (67.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 24S81080001,  Location: 4.7 MI.SW.OF SOMERVILLE (Lat: 35.189778,  Lng: -89.408167),  Route carried "on" structure: State highway 195,  Year Built: 1959,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,135 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,480 (year 2040),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.198,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $69,000,  Roadway Improvement Cost: $7,000,  Total Project Cost: $104,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 24S81080003,  Location: 3.8 MI.SW.OF SOMERVILLE (Lat: 35.191778,  Lng: -89.388500),  Route carried "on" structure: State highway 195,  Year Built: 1960,  Status: Open,  Structure Length: 0.70m (2.30ft),  Average Daily Traffic: 1,135 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,480 (year 2040),  Design Load: H 15,  Features Intersected: OVERFLOW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.065,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 42.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $69,000,  Roadway Improvement Cost: $7,000,  Total Project Cost: $104,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 24S81080005,  Location: 3.7 MI.SW.OF SOMERVILLE (Lat: 35.191722,  Lng: -89.387333),  Route carried "on" structure: State highway 195,  Year Built: 1958,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 1,135 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,480 (year 2040),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 7.178,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 7.5m (24.6ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 55.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.49m (4.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $263,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $395,000 ( Estimate for 2020),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 24S81130033,  Location: 3.1 MI E JCT SR76&SR193 (Lat: 35.155361,  Lng: -89.313583),  Route carried "on" structure: County highway 1442,  Year Built: 2021,  Status: Open,  Structure Length: 2.74m (8.99ft),  Average Daily Traffic: 352 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 563 (year 2041),  Design Load: HL 93,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 15.112,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Single/Spread,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 27.4m (89.9ft),  Curb-To-Curb Width: 7.9m (25.9ft),  Out-to-Out Width: 8.6m (28.2ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 44.1 metric tons,  Method Used To Determine Operating Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Assigned ratings based on Load and Resistance Factor Design (LRFD) reported by rating factor (RF) using HL93 loadings,  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 24SR0760011,  Location: 5.5 MILES NORTH OF MOSCOW (Lat: 35.138056,  Lng: -89.374361),  Route carried "on" structure: State highway 76,  Year Built: 1998,  Status: Open,  Structure Length: 1.76m (5.77ft),  Average Daily Traffic: 2,613 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,000 (year 2040),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 8.868,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 3 degrees,  Material/Design: Concrete continuous,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 15.1m (49.5ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 89.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing