Bridge Statistics for Enid, Oklahoma (OK)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 133Number of bridges
  • 932ft / 284mTotal length
  • $83,202,000Total costs
  • 399,142Total average daily traffic
  • 44,020Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Enid
  • No street view available for this location

New bridges in Enid, OK - historical statistics
  • New bridges - historical statistics
  • 81920-1929
  • 81930-1939
  • 21940-1949
  • 251950-1959
  • 361960-1969
  • 91970-1979
  • 141980-1989
  • 81990-1999
  • 82000-2009
  • 132010-2019
  • 22020-2022
Reconstructed bridges in Enid, OK - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 21950-1959
  • 71960-1969
  • 31970-1979
  • 31980-1989
  • 11990-1999
  • 42000-2009
Average Bridge Daily Traffic in Enid, OK
Average Bridge Truck Traffic in Enid, OK
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 10.5%Very good
  • 38.6%Good
  • 26.3%Satisfactory
  • 21.1%Fair
  • 1.8%Poor
  • 1.8%Failed
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 13.8%Very good
  • 31.0%Good
  • 43.1%Satisfactory
  • 8.6%Fair
  • 1.7%Serious
  • 1.7%Failed
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 8.6%Very good
  • 22.4%Good
  • 32.8%Satisfactory
  • 25.9%Fair
  • 6.9%Poor
  • 1.7%Serious
  • 1.7%Failed
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 11.0%Very good
  • 39.8%Good
  • 33.1%Satisfactory
  • 11.9%Fair
  • 4.2%Poor
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 5.9%Very good
  • 35.3%Good
  • 45.6%Satisfactory
  • 5.9%Fair
  • 2.9%Poor
  • 4.4%Serious
Find on map >>   Show street view

Structure Number: 83,  Location: 2.2E 2.7S OF HUNTER (Lat: 36.524567,  Lng: -97.622353),  Route carried "on" structure: County highway N3020,  Year Built: 1926,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Operating Rating: 68.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.63m (11.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $185,000,  Roadway Improvement Cost: $102,000,  Total Project Cost: $294,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 1227,  Location: 7E 2.8S OF LAHOMA (Lat: 36.350133,  Lng: -97.961542),  Route carried "on" structure: County highway N2830,  Year Built: 1922,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 50 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 80 (year 2040),  Features Intersected: SPRING CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.8m (19.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb-To-Curb Width: 6.3m (20.7ft),  Out-to-Out Width: 6.9m (22.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.28m (10.76ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $168,000,  Roadway Improvement Cost: $92,000,  Total Project Cost: $265,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 1396,  Location: AT US 64/30 ST OLD US64 (Lat: 36.390736,  Lng: -97.829997),  Route carried "on" structure: City street E0430,  Year Built: 1924,  Status: Posted for load,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 250 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 400 (year 2040),  Design Load: H 15,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 6.1m (20.0ft),  Out-to-Out Width: 6.8m (22.3ft)

Condition: Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.75m (15.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $243,000,  Roadway Improvement Cost: $134,000,  Total Project Cost: $387,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1418,  Location: 3.5 MI SE of BOULANGER (Lat: 36.916739,  Lng: -96.198708),  Route carried "on" structure: County highway 5756C,  Year Built: 1925,  Status: Posted for load,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 10,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.0m (23.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 5.5m (18.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Poor,  Channel: Poor,  Operating Rating: 29.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 17.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $139,000,  Roadway Improvement Cost: $77,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1419,  Location: 1N of LENAPAH (Lat: 36.868111,  Lng: -95.635344),  Route carried "on" structure: County highway N4135,  Year Built: 1925,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Out-to-Out Width: 10.1m (33.1ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 45.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 153,  Location: 7.3 MI N JCT US 412 (Lat: 36.485478,  Lng: -97.872567),  Route carried "on" structure: US 60,  Year Built: 1925,  Year Reconstructed: 1964,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 5,000 (year 2020),  Truck Traffic: 16%,  Average Future Daily Traffic: 8,000 (year 2040),  Design Load: H 20,  Features Intersected: SAND CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.747,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 25.6m (84.0ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 47.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.07m (3.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $240,000,  Roadway Improvement Cost: $395,000,  Total Project Cost: $671,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1695,  Location: 1.2 S 0.8 E OF CASTLE (Lat: 35.453378,  Lng: -96.370694),  Route carried "on" structure: County highway N3730,  Year Built: 1926,  Year Reconstructed: 1959,  Status: Temporarily open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 70 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 112 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Failed,  Superstructure: Failed,  Substructure: Failed,  Channel: Fair,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.34m (10.96ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2020,  Bridge Improvement Cost: $171,000,  Roadway Improvement Cost: $94,000,  Total Project Cost: $270,000 ( Estimate for 2015),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 1696,  Location: 7.W 1.6S OF BURNS FLAT (Lat: 35.324886,  Lng: -99.294011),  Route carried "on" structure: County highway N2070,  Year Built: 1926,  Status: Posted for load,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 5.6m (18.4ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Serious,  Channel: Satisfactory,  Operating Rating: 18.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 13.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 30.0 - 39.9% below),  Length Of Structure Improvement: 3.63m (11.91ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2021,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $185,000,  Roadway Improvement Cost: $102,000,  Total Project Cost: $294,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 3832,  Location: 3S 4.3E US81/US64 (Lat: 36.347231,  Lng: -97.812258),  Route carried "on" structure: County highway E0460,  Year Built: 1933,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.3m (24.0ft),  Curb-To-Curb Width: 5.2m (17.1ft),  Out-to-Out Width: 5.9m (19.4ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Poor,  Channel: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.05m (10.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $156,000,  Roadway Improvement Cost: $86,000,  Total Project Cost: $246,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 3833,  Location: 2.7N 6E OF WAUKOMIS (Lat: 36.318114,  Lng: -97.791969),  Route carried "on" structure: County highway E0480,  Year Built: 1933,  Status: Open,  Structure Length: 0.68m (2.23ft),  Average Daily Traffic: 25 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 40 (year 2040),  Design Load: H 15,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.6m (21.7ft),  Curb-To-Curb Width: 6.0m (19.7ft),  Out-to-Out Width: 6.6m (21.7ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Fair,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.79m (9.15ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $143,000,  Roadway Improvement Cost: $78,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 5415,  Location: 11.7 MI E MAJOR C/L (Lat: 36.390769,  Lng: -97.896167),  Route carried "on" structure: US 60,  Year Built: 1937,  Year Reconstructed: 1960,  Status: Open,  Structure Length: 1.30m (4.27ft),  Average Daily Traffic: 20,800 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 33,280 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 18.569,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 19.5m (64.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 19.5m (64.0ft),  Out-to-Out Width: 27.5m (90.2ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 54.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 5823,  Location: 2S .3E OF US412/IMO RD (Lat: 36.361750,  Lng: -97.973883),  Route carried "on" structure: City street E0450,  Year Built: 1938,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.4m (21.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.0m (26.2ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Gravel
Find on map >>   Show street view

Structure Number: 643,  Location: AT US 64/54 ST (Lat: 36.390533,  Lng: -97.797803),  Route carried "on" structure: City street E0430,  Year Built: 1938,  Status: Open,  Structure Length: 1.58m (5.18ft),  Average Daily Traffic: 250 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 400 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 15.5m (50.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Satisfactory,  Operating Rating: 55.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.40m (14.44ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $225,000,  Roadway Improvement Cost: $124,000,  Total Project Cost: $357,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 829,  Location: 1.5 W .1 N OF I-40 (Lat: 35.449744,  Lng: -94.831839),  Route carried "on" structure: County highway N4600,  Year Built: 1940,  Status: Posted for load,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 300 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 480 (year 2040),  Design Load: HS 20,  Features Intersected: SHILOH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.0m (23.0ft),  Out-to-Out Width: 7.6m (24.9ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.63m (11.91ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $185,000,  Roadway Improvement Cost: $102,000,  Total Project Cost: $294,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 10878,  Location: .9N OF US412 ON IMO RD. (Lat: 36.403819,  Lng: -97.979603),  Route carried "on" structure: City street N2820,  Year Built: 1948,  Status: Posted for load,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 100 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 160 (year 2040),  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.161,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 6.3m (20.7ft),  Out-to-Out Width: 6.5m (21.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 12.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 7.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 4.08m (13.39ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $208,000,  Roadway Improvement Cost: $115,000,  Total Project Cost: $331,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 12591,  Location: 1.7 S JCT US 60 ENID (Lat: 36.366064,  Lng: -97.889828),  Route carried "on" structure: US 81,  Year Built: 1951,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 1.83m (6.00ft),  Average Daily Traffic: 10,500 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 16,800 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 22.333,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 20.1m (65.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 51.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.01m (6.59ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $252,000,  Roadway Improvement Cost: $415,000,  Total Project Cost: $704,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 13642,  Location: .5S OF US412 (Lat: 36.386483,  Lng: -97.907950),  Route carried "on" structure: City street N2860,  Year Built: 1966,  Year Reconstructed: 2009,  Status: Open,  Structure Length: 5.55m (18.21ft),  Average Daily Traffic: 4,700 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 7,520 (year 2040),  Design Load: HS 20,  Features Intersected: BOGGY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.96m (19.55ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $304,000,  Roadway Improvement Cost: $167,000,  Total Project Cost: $485,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13643,  Location: .8S OF US412 IN ENID (Lat: 36.380000,  Lng: -97.908056),  Route carried "on" structure: City street N2860,  Year Built: 1956,  Year Reconstructed: 2009,  Status: Open,  Structure Length: 2.77m (9.09ft),  Average Daily Traffic: 4,700 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,520 (year 2040),  Design Load: HS 20,  Features Intersected: WEST BOGGY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.541,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.96m (19.55ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $304,000,  Roadway Improvement Cost: $167,000,  Total Project Cost: $485,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 13799,  Location: .2 MI N OF WILLOW ST (Lat: 36.425169,  Lng: -97.836919),  Route carried "on" structure: City street N2900,  Year Built: 1957,  Status: Open,  Structure Length: 2.68m (8.79ft),  Average Daily Traffic: 1,400 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 2,240 (year 2040),  Design Load: H 15,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.148,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.8m (42.0ft)

Condition: Channel: Poor,  Culverts: Satisfactory,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.75m (15.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 13941,  Location: .3E.3N3E3.8N OF DRUMMOND (Lat: 36.358892,  Lng: -97.979469),  Route carried "on" structure: County highway N2820,  Year Built: 1958,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 475 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 760 (year 2040),  Design Load: HS 20,  Features Intersected: TURKEY CREEK TRIB.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 9.333,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.72m (8.92ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 14025,  Location: 2.9 MI N JCT US 412 (Lat: 36.432511,  Lng: -97.887483),  Route carried "on" structure: US 60,  Year Built: 1958,  Status: Open,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 4,400 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,040 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.649,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 39.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 14062,  Location: 4 MI N JCT US 412 (Lat: 36.445194,  Lng: -97.872047),  Route carried "on" structure: US 60,  Year Built: 1958,  Status: Open,  Structure Length: 1.21m (3.97ft),  Average Daily Traffic: 2,500 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,000 (year 2040),  Design Load: HS 20,  Features Intersected: SKELETON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.645,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 20.7m (67.9ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $281,000,  Roadway Improvement Cost: $464,000,  Total Project Cost: $787,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 14063,  Location: 4 MI N JCT US 412 (Lat: 36.445289,  Lng: -97.873903),  Route carried "on" structure: US 60,  Year Built: 1958,  Status: Open,  Structure Length: 1.21m (3.97ft),  Average Daily Traffic: 2,750 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,400 (year 2040),  Design Load: HS 20,  Features Intersected: SKELETON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.645,  Lanes on structure: 2,  Base Highway Network: Yes (Inventory Route: 2400005H,  Subroute: 3),  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 14266,  Location: AT US 60 & BRECKINRIDGE (Lat: 36.434400,  Lng: -97.859536),  Route carried "on" structure: City street E0400,  Year Built: 1959,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 1,000 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 1,600 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.127,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 14267,  Location: AT US 81 & BRECKINRIDGE (Lat: 36.434186,  Lng: -97.837619),  Route carried "on" structure: City street E0400,  Year Built: 1959,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 1,200 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 1,920 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.9m (39.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.1m (26.6ft)

Condition: Channel: Satisfactory,  Culverts: Serious,  Operating Rating: 37.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 14827,  Location: 0.3E OF VAN BUREN ON WILL (Lat: 36.419825,  Lng: -97.886050),  Route carried "on" structure: City street E0410,  Year Built: 1960,  Status: Open,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 13,700 (year 2020),  Truck Traffic: 10%,  Average Future Daily Traffic: 21,920 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.483,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 14.6m (47.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 15.1m (49.5ft),  Out-to-Out Width: 15.8m (51.8ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 55.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.41m (11.19ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1503,  Location: 10.6 MI E MAJOR C/L (Lat: 36.390642,  Lng: -97.911772),  Route carried "on" structure: US 60,  Year Built: 1960,  Status: Open,  Structure Length: 1.89m (6.20ft),  Average Daily Traffic: 20,800 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 33,280 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.185,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 19.4m (63.6ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 3.8m (12.5ft),  Curb-To-Curb Width: 19.4m (63.6ft),  Out-to-Out Width: 26.4m (86.6ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.95m (6.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $366,000,  Roadway Improvement Cost: $603,000,  Total Project Cost: $1,024,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15135,  Location: .9S OF US412 (Lat: 36.377042,  Lng: -97.872683),  Route carried "on" structure: City street N2880,  Year Built: 1960,  Status: Open,  Structure Length: 5.33m (17.49ft),  Average Daily Traffic: 200 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 320 (year 2040),  Design Load: HS 20,  Features Intersected: BOGGY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.448,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Fair,  Channel: Fair,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.38m (27.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $428,000,  Roadway Improvement Cost: $235,000,  Total Project Cost: $665,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 15363,  Location: 0.1 MI S OF US64 (Lat: 36.390414,  Lng: -97.836972),  Route carried "on" structure: City street N2900,  Year Built: 1961,  Status: Open,  Structure Length: 5.55m (18.21ft),  Average Daily Traffic: 4,200 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 6,720 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.058,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.56m (28.08ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $437,000,  Roadway Improvement Cost: $240,000,  Total Project Cost: $680,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 157,  Location: 0.6 W JCT SH-72 (Lat: 35.507342,  Lng: -95.645297),  Route carried "on" structure: US 266,  Year Built: 1963,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Daily Traffic: 1,100 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 1,760 (year 2040),  Design Load: HS 20,  Features Intersected: ELM CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.058,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.28m (4.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $342,000,  Roadway Improvement Cost: $564,000,  Total Project Cost: $957,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15889,  Location: 5.9 MI E JCT US 81 (Lat: 36.397200,  Lng: -97.802478),  Route carried "on" structure: US 64,  Year Built: 1964,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 9,300 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 14,880 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.203,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Inventory Rating: 58.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 1589,  Location: 5.2 MI E JCT US 81 (Lat: 36.397261,  Lng: -97.797472),  Route carried "on" structure: US 64,  Year Built: 1964,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 8,200 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 13,120 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.652,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 60.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.70m (2.30ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15894,  Location: 6.9 MI E JCT US 81 (Lat: 36.397353,  Lng: -97.766461),  Route carried "on" structure: US 64,  Year Built: 1964,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 8,000 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 12,800 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 6.404,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 56.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.67m (2.20ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2020,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15931,  Location: 5.7 MI E JCT US 81 (Lat: 36.397308,  Lng: -97.788200),  Route carried "on" structure: US 64,  Year Built: 1964,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 0.97m (3.18ft),  Average Daily Traffic: 8,200 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 13,120 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.472,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Number Of Approach Spans: 1,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 68.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.04m (3.41ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $340,000,  Roadway Improvement Cost: $561,000,  Total Project Cost: $952,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 15977,  Location: 6.2 MI E JCT US 81 (Lat: 36.397344,  Lng: -97.778783),  Route carried "on" structure: US 64,  Year Built: 1964,  Year Reconstructed: 1973,  Status: Open,  Structure Length: 1.71m (5.61ft),  Average Daily Traffic: 8,000 (year 2020),  Truck Traffic: 25%,  Average Future Daily Traffic: 12,800 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 5.325,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 21.9m (71.9ft),  Skew: 14 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $362,000,  Roadway Improvement Cost: $598,000,  Total Project Cost: $1,015,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16044,  Location: 4.3 MI E JCT US 81 (Lat: 36.397222,  Lng: -97.814167),  Route carried "on" structure: US 64,  Year Built: 1964,  Status: Open,  Structure Length: 4.31m (14.14ft),  Average Daily Traffic: 4,650 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,440 (year 2040),  Design Load: HL 93,  Features Intersected: SKELETON CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.157,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.3m (60.0ft),  Curb-To-Curb Width: 12.7m (41.7ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 46.3 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor (LRFR),  Inventory Rating: 35.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor (LRFR),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.47m (24.51ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $959,000,  Roadway Improvement Cost: $1,582,000,  Total Project Cost: $2,684,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 16207,  Location: 0.6 MI S OF WILLOW (Lat: 36.411847,  Lng: -97.879964),  Route carried "on" structure: City street N2876,  Year Built: 1950,  Status: Open,  Structure Length: 1.13m (3.71ft),  Average Daily Traffic: 5,000 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 8,000 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.058,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 10.9m (35.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 47.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 3.17m (10.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 16366,  Location: 6.4W 5.1N OF DOUGLAS (Lat: 36.333781,  Lng: -97.783100),  Route carried "on" structure: County highway N2930,  Year Built: 1965,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 400 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 640 (year 2040),  Design Load: HS 20,  Features Intersected: SKELETON CREEK TRIB.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 16.251,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 10.5m (34.4ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.83m (12.57ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2020,  Bridge Improvement Cost: $100,000,  Roadway Improvement Cost: $75,000,  Total Project Cost: $225,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16597,  Location: 0.1 MI E OF CLEVELAND (Lat: 36.376264,  Lng: -97.905828),  Route carried "on" structure: City street E0440,  Year Built: 1965,  Status: Open,  Structure Length: 6.46m (21.19ft),  Average Daily Traffic: 2,800 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 4,480 (year 2040),  Design Load: H 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.770,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 10.7m (35.1ft),  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Fair,  Channel: Good,  Operating Rating: 32.7 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 19.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.28m (30.45ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $474,000,  Roadway Improvement Cost: $261,000,  Total Project Cost: $738,000 ( Estimate for 2015),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 16844,  Location: 7.2 MI E MAJOR C/L (Lat: 36.390661,  Lng: -97.970144),  Route carried "on" structure: US 60,  Year Built: 1967,  Year Reconstructed: 1975,  Status: Open,  Structure Length: 0.76m (2.49ft),  Average Daily Traffic: 9,400 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 15,040 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 12.117,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 22.6m (74.1ft),  Skew: 19 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 2.4m (7.9ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 44.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 0.76m (2.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Find on map >>   Show street view

Structure Number: 16874,  Location: 8.6 MI E MAJOR C/L (Lat: 36.390556,  Lng: -97.948333),  Route carried "on" structure: US 60,  Year Built: 1967,  Year Reconstructed: 1969,  Status: Open,  Structure Length: 0.97m (3.18ft),  Average Daily Traffic: 10,600 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 16,960 (year 2040),  Design Load: HS 20,  Features Intersected: CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 13.934,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 24.4m (80.1ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 67.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 40.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.01m (3.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $230,000,  Roadway Improvement Cost: $380,000,  Total Project Cost: $644,000 ( Estimate for 2015)
Discuss Enid, Oklahoma (OK) on our hugely popular Oklahoma forum.