Bridge Statistics for Decatur, Alabama (AL)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 115Number of bridges
  • 3,763ft / 1,147mTotal length
  • $417,653,000Total costs
  • 1,430,724Total average daily traffic
  • 205,848Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Decatur
  • No street view available for this location

New bridges in Decatur, AL - historical statistics
  • New bridges - historical statistics
  • 51920-1929
  • 51930-1939
  • 131950-1959
  • 231960-1969
  • 231970-1979
  • 151980-1989
  • 181990-1999
  • 82000-2009
  • 52010-2019
Reconstructed bridges in Decatur, AL - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11940-1949
  • 41950-1959
  • 11960-1969
  • 21970-1979
  • 01980-1989
  • 21990-1999
  • 12000-2009
Average Bridge Daily Traffic in Decatur, AL
Average Bridge Truck Traffic in Decatur, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 10.6%Very good
  • 34.0%Good
  • 36.2%Satisfactory
  • 17.0%Fair
  • 2.1%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 14.9%Very good
  • 36.2%Good
  • 36.2%Satisfactory
  • 8.5%Fair
  • 4.3%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 12.8%Very good
  • 40.4%Good
  • 29.8%Satisfactory
  • 14.9%Fair
  • 2.1%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 16.3%Very good
  • 43.8%Good
  • 21.3%Satisfactory
  • 17.5%Fair
  • 1.3%Poor
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 9.3%Very good
  • 22.2%Good
  • 33.3%Satisfactory
  • 35.2%Fair
Find on map >>   Show street view

Structure Number: 15675,  Location: JCT MAGNOLIA * BRUSH CK (Lat: 34.578200,  Lng: -86.973500),  Route carried "on" structure: City street ,  Year Built: 1987,  Status: Open,  Structure Length: 0.73m (2.40ft),  Average Daily Traffic: 4,176 (year 2009),  Truck Traffic: 20%,  Average Future Daily Traffic: 4,177 (year 2030),  Design Load: H 15,  Features Intersected: BRUSH CREEK,  Facility Carried by Structure: MAGNOLIA STREET
Minimum Vertical Clearance: 7.56m (24.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.7m (12.1ft),  Curb-To-Curb Width: 7.8m (25.6ft),  Out-to-Out Width: 26.6m (87.3ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 57.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.38m (4.53ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $692,000,  Roadway Improvement Cost: $69,000,  Total Project Cost: $761,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 15677,  Location: JCT FAIRGRD RD*CLARKS SPG (Lat: 34.559300,  Lng: -87.007000),  Route carried "on" structure: City street ,  Year Built: 1989,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 9,753 (year 2009),  Truck Traffic: 20%,  Average Future Daily Traffic: 6,017 (year 2030),  Design Load: H 10,  Features Intersected: CLARKS SPRINGS,  Facility Carried by Structure: FAIRGROUND ROAD S
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.4m (11.2ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 18.2m (59.7ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 54.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $775,000,  Roadway Improvement Cost: $78,000,  Total Project Cost: $853,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 16284,  Location: JCT BETTY ST * DRY BRANCH (Lat: 34.578400,  Lng: -87.013800),  Route carried "on" structure: City street ,  Year Built: 1995,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 6,920 (year 2005),  Truck Traffic: 15%,  Average Future Daily Traffic: 9,115 (year 2028),  Design Load: HS 20,  Features Intersected: BETTY ST SW * DRY BRANCH,  Facility Carried by Structure: BETTY ST SW
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 1.2m (3.9ft),  Curb or Sidewalk Widths: Left: 0.1m (0.3ft),  Right: 0.1m (0.3ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 14.2m (46.6ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.44m (4.72ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $300,000,  Roadway Improvement Cost: $30,000,  Total Project Cost: $330,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1631,  Location: 1 M N JCT SR 3 & SR 20 (Lat: 34.619369,  Lng: -86.966181),  Route carried "on" structure: US 31,  Year Built: 1997,  Status: Open,  Structure Length: 11.43m (37.50ft),  Average Daily Traffic: 25,465 (year 2021),  Truck Traffic: 7%,  Average Future Daily Traffic: 32,711 (year 2033),  Design Load: HS 20,  Features Intersected: Tennessee River Relief,  Facility Carried by Structure: SR 3
Minimum Vertical Clearance: 7.56m (24.80ft),  Kilometerpoint: 578.059,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 10 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 18.9m (62.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 12.30m (40.35ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Underwater Inspection Date: July 2021,  Bridge Improvement Cost: $3,543,000,  Roadway Improvement Cost: $354,000,  Total Project Cost: $3,897,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 16311,  Location: 1 M N JCT SR 3 & SR 20 (Lat: 34.619194,  Lng: -86.965956),  Route carried "on" structure: US 31,  Year Built: 1995,  Status: Open,  Structure Length: 11.43m (37.50ft),  Average Daily Traffic: 25,465 (year 2021),  Truck Traffic: 7%,  Average Future Daily Traffic: 32,711 (year 2033),  Design Load: HS 20,  Features Intersected: Tennessee River Relief,  Facility Carried by Structure: SR 3
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 578.059,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 10 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 18.9m (62.0ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 51.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 12.30m (40.35ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Underwater Inspection Date: July 2021,  Bridge Improvement Cost: $3,628,000,  Roadway Improvement Cost: $363,000,  Total Project Cost: $3,991,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 16368,  Location: 0.1 M N JCT SR 3 & SR 20 (Lat: 34.611072,  Lng: -86.974731),  Route carried "on" structure: US 31,  Year Built: 1996,  Status: Open,  Structure Length: 79.10m (259.51ft),  Average Daily Traffic: 20,045 (year 2021),  Truck Traffic: 7%,  Average Future Daily Traffic: 25,749 (year 2033),  Design Load: HS 20,  Features Intersected: TN River & CSX RR,  Facility Carried by Structure: SR 3
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 576.974,  Lanes on structure: 3,  Lanes under structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 10 degrees,  Navigation Control: Yes ( Vertical Clearance: 17.4m (57.1ft), Horizontal Clearance: 106.7m (350.1ft)),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 13,  Length of Maximum Span: 109.7m (359.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.1m (43.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 50.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 79.10m (259.51ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Underwater Inspection Date: July 2021,  Bridge Improvement Cost: $23,322,000,  Roadway Improvement Cost: $2,332,000,  Total Project Cost: $25,654,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 17334,  Location: 0.5MI WEST OF NEEL (Lat: 34.462889,  Lng: -87.067742),  Route carried "on" structure: County highway 4,  Year Built: 1999,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 2,400 (year 1998),  Truck Traffic: 2%,  Average Future Daily Traffic: 5,517 (year 2040),  Design Load: HS 20,  Features Intersected: NEEL CREEK
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb-To-Curb Width: 12.6m (41.3ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 65.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $409,000,  Roadway Improvement Cost: $41,000,  Total Project Cost: $450,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 17336,  Location: 1.2 KM.OF HWY.72 WEST (Lat: 34.634400,  Lng: -87.094900),  Route carried "on" structure: Business City street ,  Year Built: 1996,  Status: Open,  Structure Length: 1.08m (3.54ft),  Average Daily Traffic: 741 (year 2005),  Truck Traffic: 25%,  Average Future Daily Traffic: 780 (year 2030),  Design Load: HS 20,  Features Intersected: TRICO.BLVD./CREEK,  Facility Carried by Structure: TRICO.BLVD.
Minimum Vertical Clearance: 7.56m (24.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 21.0m (68.9ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 21.2m (69.6ft),  Out-to-Out Width: 59.1m (193.9ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 67.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 1.75m (5.74ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: August 2021,  Bridge Improvement Cost: $1,952,000,  Roadway Improvement Cost: $195,000,  Total Project Cost: $2,147,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 17337,  Location: JCT.BASSETT AVE/CLARK SPG (Lat: 34.572778,  Lng: -86.966667),  Route carried "on" structure: Bypass City street ,  Year Built: 1996,  Status: Open,  Structure Length: 2.73m (8.96ft),  Average Daily Traffic: 854 (year 2007),  Truck Traffic: 25%,  Average Future Daily Traffic: 1,560 (year 2033),  Design Load: HS 20,  Features Intersected: BASSETT AVE./CLARK SPGS.,  Facility Carried by Structure: BASSETT AVE.
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.5m (41.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 27.0m (88.6ft),  Curb or Sidewalk Widths: Left: 27.0m (88.6ft),  Right: 26.4m (86.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 12.5m (41.0ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 48.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.65m (11.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $885,000,  Roadway Improvement Cost: $89,000,  Total Project Cost: $974,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1742,  Location: .4 KM. WEST OF SPRING AVE (Lat: 34.558983,  Lng: -87.004975),  Route carried "on" structure: Business City street 5,  Year Built: 1998,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 764 (year 2005),  Truck Traffic: 10%,  Average Future Daily Traffic: 624 (year 2028),  Design Load: HS 20,  Features Intersected: WIMBERLY DR./BRUSH CREEK,  Facility Carried by Structure: WIMBERLY DR.
Minimum Vertical Clearance: 0.00m,  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.7m (28.5ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.7m (15.4ft),  Curb or Sidewalk Widths: Left: 14.0m (45.9ft),  Right: 14.0m (45.9ft),  Curb-To-Curb Width: 8.7m (28.5ft),  Out-to-Out Width: 8.7m (28.5ft)

Condition: Channel: Satisfactory,  Culverts: Good,  Operating Rating: 84.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.07m (6.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,401,000,  Roadway Improvement Cost: $140,000,  Total Project Cost: $1,541,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 17586,  Location: 1.5 M N JCT SR 67 & SR 3 (Lat: 34.559739,  Lng: -87.000022),  Route carried "on" structure: Business State highway 67,  Year Built: 1965,  Year Reconstructed: 2001,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 31,030 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 40,256 (year 2033),  Design Load: HS 20,  Features Intersected: CLARK SPRING,  Facility Carried by Structure: SPRING AVENUE
Minimum Vertical Clearance: 7.56m (24.80ft),  Kilometerpoint: 65.098,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 58.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.84m (6.04ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $1,474,000,  Roadway Improvement Cost: $147,000,  Total Project Cost: $1,621,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 17593,  Location: 2.35MI NORTH OF OAK RIDGE (Lat: 34.503842,  Lng: -86.984550),  Route carried "on" structure: County highway 106,  Year Built: 2000,  Status: Open,  Structure Length: 4.15m (13.62ft),  Average Daily Traffic: 1,375 (year 2004),  Truck Traffic: 3%,  Average Future Daily Traffic: 2,754 (year 2040),  Design Load: HS 20,  Features Intersected: FLINT CREEK RELIEF,  Facility Carried by Structure: NORRIS MILL ROAD
Minimum Vertical Clearance: 6.00m (19.69ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 10.4m (34.1ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Fair,  Operating Rating: 71.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 5.12m (16.80ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $1,018,000,  Roadway Improvement Cost: $102,000,  Total Project Cost: $1,120,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 17756,  Location: 0.1 MI WEST SR24 (Lat: 34.598464,  Lng: -87.047569),  Route carried "on" structure: County highway 420,  Year Built: 1952,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 4,500 (year 1999),  Truck Traffic: 8%,  Average Future Daily Traffic: 8,933 (year 2041),  Design Load: H 15,  Features Intersected: BAKERS CREEK,  Facility Carried by Structure: OLD HWY 24
Minimum Vertical Clearance: 10.00m (32.81ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.7m (12.1ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 64.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $648,000,  Roadway Improvement Cost: $65,000,  Total Project Cost: $713,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 17997,  Location: 2.0 MI NE COUNTY LINE (Lat: 34.531717,  Lng: -87.081067),  Route carried "on" structure: County highway 1087,  Year Built: 2001,  Status: Open,  Structure Length: 2.05m (6.73ft),  Average Daily Traffic: 4,050 (year 2008),  Truck Traffic: 5%,  Average Future Daily Traffic: 7,939 (year 2042),  Design Load: HS 20,  Features Intersected: MUD TAVERN CREEK,  Facility Carried by Structure: OLD MOULTON ROAD
Minimum Vertical Clearance: 9.14m (29.99ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.9m (16.1ft),  Curb-To-Curb Width: 12.8m (42.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Channel: Good,  Culverts: Very good,  Operating Rating: 85.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 51.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.82m (9.25ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $829,000,  Roadway Improvement Cost: $83,000,  Total Project Cost: $912,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 18791,  Location: 1 MI SOUTH SR 67 (Lat: 34.533992,  Lng: -86.921064),  Route carried "on" structure: County highway 1242,  Year Built: 2004,  Status: Open,  Structure Length: 1.47m (4.82ft),  Average Daily Traffic: 50 (year 2004),  Truck Traffic: 2%,  Average Future Daily Traffic: 102 (year 2040),  Design Load: HS 20,  Features Intersected: TRIB OF FLINT CREEK,  Facility Carried by Structure: RURAL GROVE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.5m (11.5ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 12.9m (42.3ft),  Out-to-Out Width: 13.5m (44.3ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 63.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.15m (7.05ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $632,000,  Roadway Improvement Cost: $63,000,  Total Project Cost: $695,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 18802,  Location: 3.5 MI EAST OF CO. LINE (Lat: 34.604958,  Lng: -87.045994),  Route carried "on" structure: County highway 1220,  Year Built: 2003,  Status: Open,  Structure Length: 5.18m (16.99ft),  Average Daily Traffic: 1,033 (year 2000),  Average Future Daily Traffic: 2,235 (year 2039),  Design Load: HS 20,  Features Intersected: BAKERS CREEK,  Facility Carried by Structure: OLD TRINITY ROAD
Minimum Vertical Clearance: 12.19m (39.99ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 10.4m (34.1ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 75.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.21m (20.37ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $1,277,000,  Roadway Improvement Cost: $128,000,  Total Project Cost: $1,405,000 ( Estimate for 2022),  Deck Structure Type: Concrete Precast Panels
Find on map >>   Show street view

Structure Number: 18979,  Location: 600 FT N. POOLE VALLEY RD (Lat: 34.534200,  Lng: -86.982800),  Route carried "on" structure: Bypass City street ,  Year Built: 2002,  Status: Open,  Structure Length: 1.16m (3.81ft),  Average Daily Traffic: 399 (year 2005),  Truck Traffic: 25%,  Average Future Daily Traffic: 455 (year 2028),  Features Intersected: CENTRAL PARKWAY/DITCH,  Facility Carried by Structure: CENTRAL PARKWAY
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.016,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.5m (11.5ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 17.1m (56.1ft),  Out-to-Out Width: 17.1m (56.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 62.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.83m (6.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $402,000,  Roadway Improvement Cost: $40,000,  Total Project Cost: $442,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1898,  Location: 1MI. EAST S.CHAPEL HILL (Lat: 34.515900,  Lng: -87.349900),  Route carried "on" structure: Bypass City street ,  Year Built: 2002,  Status: Open,  Structure Length: 1.95m (6.40ft),  Average Daily Traffic: 228 (year 2005),  Truck Traffic: 20%,  Average Future Daily Traffic: 325 (year 2028),  Features Intersected: MUD TAVERN ROAD/DITCH,  Facility Carried by Structure: MUD TAVERN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.6m (15.1ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 14.3m (46.9ft),  Out-to-Out Width: 14.3m (46.9ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 62.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 37.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 2.69m (8.83ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $730,000,  Roadway Improvement Cost: $73,000,  Total Project Cost: $803,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1913,  Location: SEC 29 T4S R4W (Lat: 34.658542,  Lng: -86.971856),  Route carried "on" structure: County highway 45,  Year Built: 2004,  Status: Open,  Structure Length: 1.22m (4.00ft),  Average Daily Traffic: 1,428 (year 2014),  Truck Traffic: 9%,  Average Future Daily Traffic: 2,122 (year 2034),  Design Load: HS 20,  Features Intersected: PRYOR BRANCH,  Facility Carried by Structure: HARRIS STATION RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.016,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.2m (40.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 55.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.89m (6.20ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 48 months,  Inspection Date: October 2020,  Underwater Inspection Date: October 2018,  Bridge Improvement Cost: $389,000,  Roadway Improvement Cost: $39,000,  Total Project Cost: $428,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 2016,  Location: 1.0 MI S HWY 72/20 (Lat: 34.608375,  Lng: -87.045169),  Route carried "on" structure: County highway 1585,  Year Built: 2008,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 1,520 (year 1999),  Truck Traffic: 10%,  Average Future Daily Traffic: 3,040 (year 2042),  Design Load: HS 20,  Features Intersected: BAKERS CREEK,  Facility Carried by Structure: IPSCO ROAD
Minimum Vertical Clearance: 8.99m (29.49ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 10.6m (34.8ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 1.8m (5.9ft)

Condition: Channel: Satisfactory,  Culverts: Very good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.45m (4.76ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2022,  Bridge Improvement Cost: $502,000,  Roadway Improvement Cost: $50,000,  Total Project Cost: $552,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 20234,  Location: 20 MIN CO RD 1072 (Lat: 34.483825,  Lng: -87.059453),  Route carried "on" structure: County highway 1075,  Year Built: 2010,  Status: Open,  Structure Length: 0.80m (2.62ft),  Average Daily Traffic: 690 (year 2009),  Truck Traffic: 10%,  Average Future Daily Traffic: 1,165 (year 2038),  Design Load: HS 20,  Features Intersected: CRAWFORD CREEK,  Facility Carried by Structure: NEEL SCHOOL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.5m (21.3ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft)

Condition: Channel: Very good,  Culverts: Very good,  Operating Rating: 36.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.46m (4.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2020,  Bridge Improvement Cost: $371,000,  Roadway Improvement Cost: $37,000,  Total Project Cost: $408,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 20292,  Location: 1 MI S JCT SR 67 & SR 20 (Lat: 34.609278,  Lng: -87.030972),  Route carried "on" structure: State highway 67,  Year Built: 2012,  Status: Open,  Structure Length: 8.99m (29.49ft),  Average Daily Traffic: 14,820 (year 2021),  Truck Traffic: 10%,  Average Future Daily Traffic: 19,226 (year 2033),  Design Load: HS 20,  Features Intersected: SOUTHERN RR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 71.745,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 30.4m (99.7ft),  Skew: 35 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 35.1m (115.2ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 38.3m (125.7ft),  Out-to-Out Width: 39.0m (128.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 63.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.96m (32.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $8,744,000,  Roadway Improvement Cost: $874,000,  Total Project Cost: $9,618,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 20556,  Location: 1 mi S Decatur City Limit (Lat: 34.494239,  Lng: -87.026178),  Route carried "on" structure: County highway 1004,  Year Built: 2015,  Status: Open,  Structure Length: 9.75m (31.99ft),  Average Daily Traffic: 3,270 (year 2013),  Truck Traffic: 6%,  Average Future Daily Traffic: 5,582 (year 2040),  Design Load: HS 20,  Features Intersected: FLINT CREEK,  Facility Carried by Structure: Danville Road
Minimum Vertical Clearance: 12.19m (39.99ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 30.5m (100.1ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Satisfactory,  Operating Rating: 70.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 10.69m (35.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $3,080,000,  Roadway Improvement Cost: $308,000,  Total Project Cost: $3,388,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 20568,  Location: 0.4 MI N JCT SR 67 & SR 3 (Lat: 34.561722,  Lng: -86.980556),  Route carried "on" structure: State highway 67,  Year Built: 2013,  Status: Open,  Structure Length: 5.94m (19.49ft),  Average Daily Traffic: 16,610 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 21,548 (year 2033),  Design Load: HS 20,  Features Intersected: CSX Railroad
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 63.220,  Lanes on structure: 3,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 15.8m (51.8ft),  Skew: 10 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 19.8m (65.0ft),  Curb-To-Curb Width: 15.8m (51.8ft),  Out-to-Out Width: 16.7m (54.8ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Operating Rating: 77.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 54.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Better than present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.98m (22.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $2,586,000,  Roadway Improvement Cost: $259,000,  Total Project Cost: $2,845,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 20851,  Location: 1.5mi South CR 087 (Lat: 34.511642,  Lng: -87.077606),  Route carried "on" structure: County highway 1019,  Year Built: 2016,  Status: Open,  Structure Length: 12.19m (39.99ft),  Average Daily Traffic: 2,350 (year 2015),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,856 (year 2040),  Design Load: HS 20,  Features Intersected: West Flint Creek,  Facility Carried by Structure: Kirby Bridge Road
Minimum Vertical Clearance: 30.18m (99.02ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 7,  Length of Maximum Span: 36.6m (120.1ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 73.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 44.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 13.04m (42.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $3,755,000,  Roadway Improvement Cost: $376,000,  Total Project Cost: $4,131,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 732,  Location: 0.1 M N JCT SR 3 & SR 20 (Lat: 34.613333,  Lng: -86.973333),  Route carried "under" structure: City street ,  Year Built: 1961,  Structure Length: 0. m,  Average Daily Traffic: 1,605 (year 2003),  Truck Traffic: 7%,  Features Intersected: TN RIVER & CSX RR,  Facility Carried by Structure: SR 3
Minimum Vertical Clearance: 6.55m (21.49ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Lanes under structure: 2,  Material/Design: Steel continuous,  Design/Construction: Truss - Thru,  Length of Maximum Span: 109.7m (359.9ft)

Find on map >>   Show street view

Structure Number: 8733,  Location: JCT SR 20 & SR 3 (Lat: 34.629303,  Lng: -86.952672),  Route carried "under" structure: US 31,  Year Built: 1965,  Structure Length: 0. m,  Average Daily Traffic: 50,930 (year 2020),  Truck Traffic: 7%,  Features Intersected: SR 3,  Facility Carried by Structure: SR 20
Minimum Vertical Clearance: 5.21m (17.09ft),  Kilometerpoint: 579.927,  Lanes on structure: 2,  Lanes under structure: 3,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 27.7m (90.9ft)

Find on map >>   Show street view

Structure Number: 8746,  Location: 2.3 MI E JCT SR67 * SR24 (Lat: 34.601667,  Lng: -86.870000),  Route carried "under" structure: City street ,  Year Built: 1965,  Structure Length: 0. m,  Average Daily Traffic: 4,020 (year 1998),  Truck Traffic: 5%,  Features Intersected: L*N RR;1ST AV NE *1ST SE,  Facility Carried by Structure: SR 24
Minimum Vertical Clearance: 4.88m (16.01ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 30.5m (100.1ft)

Find on map >>   Show street view

Structure Number: 8746,  Location: 2.3 MI E JCT SR67 * SR24 (Lat: 34.601667,  Lng: -86.870000),  Route carried "under" structure: City street ,  Year Built: 1965,  Structure Length: 0. m,  Average Daily Traffic: 4,024 (year 1998),  Truck Traffic: 4%,  Features Intersected: L*N RR;1ST AV NE *1ST SE,  Facility Carried by Structure: SR 24
Minimum Vertical Clearance: 4.85m (15.91ft),  Kilometerpoint: 0.000,  Lanes on structure: 4,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 30.5m (100.1ft)

Find on map >>   Show street view

Structure Number: 9404,  Location: JCT L*N RR * 14TH ST SE (Lat: 34.578333,  Lng: -86.981667),  Route carried "under" structure: City street ,  Year Built: 1967,  Structure Length: 0. m,  Average Daily Traffic: 9,459 (year 1995),  Truck Traffic: 20%,  Features Intersected: L*N RR * 4TH AVE SE,  Facility Carried by Structure: 14TH ST SE
Minimum Vertical Clearance: 7.24m (23.75ft),  Kilometerpoint: 0.010,  Lanes on structure: 4,  Lanes under structure: 2,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 22.3m (73.2ft)

Find on map >>   Show street view

Structure Number: 10189,  Location: JCT I 65 & I 565 (Lat: 34.627361,  Lng: -86.901306),  Route carried "under" structure: State highway 20,  Year Built: 1970,  Structure Length: 0. m,  Average Daily Traffic: 39,060 (year 2020),  Truck Traffic: 9%,  Features Intersected: I 565,  Facility Carried by Structure: I 65
Minimum Vertical Clearance: 5.28m (17.32ft),  Kilometerpoint: 118.276,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 41.5m (136.2ft)

Find on map >>   Show street view

Structure Number: 1019,  Location: JCT I 65 & I 565 (Lat: 34.627472,  Lng: -86.901056),  Route carried "under" structure: State highway 20,  Year Built: 1970,  Structure Length: 0. m,  Average Daily Traffic: 39,060 (year 2020),  Truck Traffic: 9%,  Features Intersected: I 565,  Facility Carried by Structure: I 65
Minimum Vertical Clearance: 5.44m (17.85ft),  Kilometerpoint: 118.292,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 41.5m (136.2ft)

Find on map >>   Show street view

Structure Number: 10687,  Location: 2 MI N JCT I 565 & I 65 (Lat: 34.657417,  Lng: -86.912944),  Route carried "under" structure: Interstate 65,  Year Built: 1972,  Structure Length: 0. m,  Average Daily Traffic: 25,660 (year 2020),  Truck Traffic: 39%,  Features Intersected: I 65,  Facility Carried by Structure: GARRETT RD
Minimum Vertical Clearance: 5.33m (17.49ft),  Kilometerpoint: 550.653,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 30.5m (100.1ft)

Find on map >>   Show street view

Structure Number: 1278,  Location: JCT SR 24 & SR 67 (Lat: 34.601717,  Lng: -87.031883),  Route carried "under" structure: State highway 67,  Year Built: 1982,  Structure Length: 0. m,  Average Daily Traffic: 19,750 (year 2020),  Truck Traffic: 7%,  Features Intersected: SR 67,  Facility Carried by Structure: SR 24
Minimum Vertical Clearance: 5.72m (18.77ft),  Kilometerpoint: 70.829,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 26.5m (86.9ft)

Find on map >>   Show street view

Structure Number: 12781,  Location: JCT SR 24 & SR 67 (Lat: 34.601497,  Lng: -87.031864),  Route carried "under" structure: State highway 67,  Year Built: 1982,  Structure Length: 0. m,  Average Daily Traffic: 19,750 (year 2020),  Truck Traffic: 7%,  Features Intersected: SR 67,  Facility Carried by Structure: SR 24
Minimum Vertical Clearance: 5.66m (18.57ft),  Kilometerpoint: 70.829,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 26.5m (86.9ft)

Find on map >>   Show street view

Structure Number: 15043,  Location: JCT I 65 & I 565 (Lat: 34.627750,  Lng: -86.900861),  Route carried "under" structure: Ramp Interstate 565,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 5,318 (year 2020),  Truck Traffic: 12%,  Features Intersected: I 565,  Facility Carried by Structure: I 65
Minimum Vertical Clearance: 5.31m (17.42ft),  Kilometerpoint: 0.805,  Lanes on structure: 2,  Lanes under structure: 6,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 41.8m (137.1ft)

Find on map >>   Show street view

Structure Number: 15669,  Location: JCT I 565 & I 65 (Lat: 34.629806,  Lng: -86.901889),  Route carried "under" structure: Interstate 65,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 25,660 (year 2021),  Truck Traffic: 39%,  Features Intersected: I 65
Minimum Vertical Clearance: 5.00m (16.40ft),  Kilometerpoint: 547.430,  Lanes on structure: 2,  Lanes under structure: 7,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 27.1m (88.9ft)

Find on map >>   Show street view

Structure Number: 1567,  Location: JCT I 65 & I 565 (Lat: 34.627331,  Lng: -86.903619),  Route carried "under" structure: Spur Interstate 565,  Year Built: 1990,  Structure Length: 0. m,  Average Daily Traffic: 44,033 (year 2021),  Truck Traffic: 10%,  Features Intersected: I 565,  Facility Carried by Structure: I 65
Minimum Vertical Clearance: 6.68m (21.92ft),  Kilometerpoint: 547.338,  Lanes on structure: 2,  Lanes under structure: 4,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 43.3m (142.1ft)

Find on map >>   Show street view

Structure Number: 16368,  Location: 0.1 M N JCT SR 3 & SR 20 (Lat: 34.611072,  Lng: -86.974731),  Route carried "under" structure: City street ,  Year Built: 1996,  Structure Length: 0. m,  Average Daily Traffic: 1,445 (year 2021),  Truck Traffic: 7%,  Features Intersected: TN River & CSX RR,  Facility Carried by Structure: SR 3
Minimum Vertical Clearance: 6.10m (20.01ft),  Kilometerpoint: 0.000,  Lanes on structure: 3,  Lanes under structure: 2,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Length of Maximum Span: 109.7m (359.9ft)

Discuss Decatur, Alabama (AL) on our hugely popular Alabama forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.