Jump to a detailed profile or search site with Google Custom Search

Bridge Statistics for Talladega, Alabama (AL)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 53Number of bridges
  • 528ft / 161mTotal length
  • $60,401,000Total costs
  • 169,132Total average daily traffic
  • 9,706Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Talladega
  • No street view available for this location

New bridges in Talladega, AL - historical statistics
  • New bridges - historical statistics
  • 31920-1929
  • 51930-1939
  • 141940-1949
  • 51950-1959
  • 11960-1969
  • 21970-1979
  • 91980-1989
  • 21990-1999
  • 82000-2009
  • 42010-2019
Reconstructed bridges in Talladega, AL - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11930-1939
  • 11940-1949
  • 01950-1959
  • 01960-1969
  • 01970-1979
  • 11980-1989
  • 31990-1999
Average Bridge Daily Traffic in Talladega, AL
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 3.7%Excellent
  • 14.8%Very good
  • 29.6%Good
  • 33.3%Satisfactory
  • 18.5%Fair
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 14.8%Very good
  • 33.3%Good
  • 22.2%Satisfactory
  • 22.2%Fair
  • 7.4%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 25.9%Very good
  • 25.9%Good
  • 7.4%Satisfactory
  • 29.6%Fair
  • 7.4%Poor
  • 3.7%Serious
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 2.0%Excellent
  • 20.0%Very good
  • 34.0%Good
  • 30.0%Satisfactory
  • 12.0%Fair
  • 2.0%Poor
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 36.0%Good
  • 52.0%Satisfactory
  • 12.0%Fair
Find on map >>   Show street view

Structure Number: 229,  Location: U S 411 * BIG WILLS CK (Lat: 33.990222,  Lng: -86.004250),  Route carried "on" structure: US 411,  Year Built: 1924,  Status: Open,  Structure Length: 7.77m (25.49ft),  Average Daily Traffic: 17,116 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 23,963 (year 2039),  Design Load: H 15,  Features Intersected: BIG WILLS CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 347.940,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 9.4m (30.8ft),  Skew: 10 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 6,  Length of Maximum Span: 13.1m (43.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 50.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.78m (28.81ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Underwater Inspection Date: May 2020,  Bridge Improvement Cost: $1,807,000,  Roadway Improvement Cost: $181,000,  Total Project Cost: $1,988,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 739,  Location: TALLADEGA (Lat: 33.433300,  Lng: -86.083400),  Route carried "on" structure: City street ,  Year Built: 1930,  Status: Open,  Structure Length: 0.61m (2.00ft),  Average Daily Traffic: 1,000 (year 2011),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,486 (year 2041),  Design Load: H 15,  Features Intersected: ISBELL BRANCH,  Facility Carried by Structure: COURT STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.299,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.5m (34.4ft),  Material/Design: Masonry,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 0.0m

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.22m (4.00ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $422,000,  Roadway Improvement Cost: $42,000,  Total Project Cost: $464,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 865,  Location: 0.5 MI E CO RT 005 (Lat: 33.491464,  Lng: -86.028850),  Route carried "on" structure: County highway 82,  Year Built: 1930,  Status: Posted for load,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 515 (year 2018),  Truck Traffic: 1%,  Average Future Daily Traffic: 672 (year 2038),  Features Intersected: KELLEY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Steel,  Design/Construction: Truss - Thru,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 2,  Length of Maximum Span: 24.4m (80.1ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 6.0m (19.7ft)

Condition: Deck: Fair,  Superstructure: Poor,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 2.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 1.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: High priority of corrective action,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 3.31m (10.86ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: January 2022,  Critical Feature Inspection Date: January 2022,  Other Special Inspection Date: January 2022,  Bridge Improvement Cost: $431,000,  Roadway Improvement Cost: $43,000,  Total Project Cost: $474,000 ( Estimate for 2022),  Deck Structure Type: Corrugated Steel,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 1102,  Location: CITY OF TALLADEGA (Lat: 33.433422,  Lng: -86.109286),  Route carried "on" structure: US 231,  Year Built: 1934,  Status: Open,  Structure Length: 1.41m (4.63ft),  Average Daily Traffic: 5,359 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 7,503 (year 2039),  Design Load: H 15,  Features Intersected: TOWN CREEK,  Facility Carried by Structure: AL 21
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 370.201,  Lanes on structure: 4,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 24.4m (80.1ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.3m (10.8ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 54.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.08m (6.82ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,046,000,  Roadway Improvement Cost: $105,000,  Total Project Cost: $1,151,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2005,  Location: 2 MI S JCT CO RD 1 (Lat: 34.024919,  Lng: -87.535778),  Route carried "on" structure: County highway 347,  Year Built: 1939,  Status: Posted for load,  Structure Length: 1.04m (3.41ft),  Average Daily Traffic: 100 (year 1991),  Average Future Daily Traffic: 250 (year 2033),  Features Intersected: BLACKWATER CREEK
Minimum Vertical Clearance: 7.56m (24.80ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb-To-Curb Width: 4.4m (14.4ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Channel: Poor,  Operating Rating: 2.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 1.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Meets minimum limits,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.71m (5.61ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: October 2020,  Other Special Inspection Date: October 2021,  Bridge Improvement Cost: $187,000,  Roadway Improvement Cost: $19,000,  Total Project Cost: $206,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 2039,  Location: JCT SR 34 * SR 77 (Lat: 33.476583,  Lng: -86.120272),  Route carried "on" structure: State highway 77,  Year Built: 1939,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 0.95m (3.12ft),  Average Daily Traffic: 16,094 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 22,532 (year 2039),  Design Load: H 15,  Features Intersected: POORHOUSE BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 109.163,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 19.6m (64.3ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 79.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 47.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.62m (5.31ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $1,649,000,  Roadway Improvement Cost: $165,000,  Total Project Cost: $1,814,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 2127,  Location: 0.45 Mi S of CR-78 (Lat: 33.078428,  Lng: -86.266383),  Route carried "on" structure: County highway ,  Year Built: 1940,  Status: Posted for load,  Structure Length: 2.10m (6.89ft),  Average Daily Traffic: 33 (year 2021),  Average Future Daily Traffic: 98 (year 2041),  Features Intersected: Shelton Creek,  Facility Carried by Structure: Hardy Lane
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 3.7m (12.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 21.0m (68.9ft),  Curb-To-Curb Width: 3.4m (11.2ft),  Out-to-Out Width: 3.8m (12.5ft)

Condition: Deck: Excellent,  Superstructure: Fair,  Substructure: Fair,  Channel: Excellent,  Operating Rating: 18.1 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 13.5 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.88m (9.45ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: Febuary 2021,  Other Special Inspection Date: Febuary 2022,  Bridge Improvement Cost: $237,000,  Roadway Improvement Cost: $24,000,  Total Project Cost: $261,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 2283,  Location: TALLADEGA (Lat: 33.434406,  Lng: -86.109217),  Route carried "on" structure: City street ,  Year Built: 1940,  Status: Posted for load,  Structure Length: 0.84m (2.76ft),  Average Daily Traffic: 350 (year 2012),  Truck Traffic: 5%,  Average Future Daily Traffic: 520 (year 2041),  Design Load: H 15,  Features Intersected: ISBELL BRANCH,  Facility Carried by Structure: NORTH STREET WEST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.200,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 3.8m (12.5ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 4.7m (15.4ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Poor,  Channel: Fair,  Operating Rating: 2.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 1.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.50m (4.92ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: November 2021,  Other Special Inspection Date: November 2021,  Bridge Improvement Cost: $164,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $180,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 229,  Location: TALLADEGA (Lat: 33.436142,  Lng: -86.107692),  Route carried "on" structure: City street ,  Year Built: 1940,  Status: Posted for load,  Structure Length: 0.74m (2.43ft),  Average Daily Traffic: 125 (year 2012),  Average Future Daily Traffic: 175 (year 2041),  Features Intersected: ISBELL BRANCH,  Facility Carried by Structure: CANAAN WAY(GARVIN)
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.100,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.5m (14.8ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.4m (24.3ft),  Curb-To-Curb Width: 5.5m (18.0ft),  Out-to-Out Width: 5.8m (19.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Serious,  Channel: Fair,  Operating Rating: 2.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 1.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.39m (4.56ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 3 months,  Inspection Date: November 2021,  Other Special Inspection Date: Febuary 2022,  Bridge Improvement Cost: $181,000,  Roadway Improvement Cost: $18,000,  Total Project Cost: $199,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 2497,  Location: 0.4 MI N CO 385 LAKE ELLI (Lat: 33.440422,  Lng: -86.027250),  Route carried "on" structure: County highway 385,  Year Built: 1940,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Daily Traffic: 720 (year 2020),  Truck Traffic: 15%,  Average Future Daily Traffic: 845 (year 2040),  Design Load: HS 20,  Features Intersected: DRY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 0.2m (0.7ft),  Right: 0.2m (0.7ft),  Curb-To-Curb Width: 8.0m (26.2ft),  Out-to-Out Width: 8.5m (27.9ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 39.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 23.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.95m (6.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Bridge Improvement Cost: $316,000,  Roadway Improvement Cost: $32,000,  Total Project Cost: $348,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 263,  Location: 0.2 MI S JCT CO 91 (Lat: 33.472889,  Lng: -86.029944),  Route carried "on" structure: State highway 21,  Year Built: 1923,  Year Reconstructed: 1942,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 5,633 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,886 (year 2039),  Design Load: H 15,  Features Intersected: KELLY CREEK RELIEF
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 379.244,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.2m (17.1ft),  Curb-To-Curb Width: 9.1m (29.9ft),  Out-to-Out Width: 9.8m (32.2ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 44.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $389,000,  Roadway Improvement Cost: $39,000,  Total Project Cost: $428,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 268,  Location: CITY OF TALLADEGA (Lat: 33.469422,  Lng: -86.033369),  Route carried "on" structure: State highway 21,  Year Built: 1942,  Status: Open,  Structure Length: 2.74m (8.99ft),  Average Daily Traffic: 3,260 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 4,564 (year 2039),  Design Load: H 15,  Features Intersected: KELLY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 378.745,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 6.7m (22.0ft),  Curb-To-Curb Width: 8.2m (26.9ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 31.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.66m (12.01ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $728,000,  Roadway Improvement Cost: $73,000,  Total Project Cost: $801,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 2681,  Location: 0.6 MI N JCT CO 96 (Lat: 33.499389,  Lng: -86.007306),  Route carried "on" structure: State highway 21,  Year Built: 1942,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 11,265 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 15,771 (year 2039),  Design Load: H 15,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 382.955,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 81.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.26m (4.13ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $437,000,  Roadway Improvement Cost: $44,000,  Total Project Cost: $481,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 2811,  Location: 2.1 MI S OF AL 21 (Lat: 33.402694,  Lng: -86.102944),  Route carried "on" structure: City street ,  Year Built: 1945,  Status: Open,  Structure Length: 1.10m (3.61ft),  Average Daily Traffic: 1,275 (year 2011),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,894 (year 2041),  Design Load: HS 20,  Features Intersected: TALLADEGA CREEK BRANCH,  Facility Carried by Structure: ALLISON MILL RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.099,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.1m (20.0ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.5m (18.0ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 46.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.77m (5.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $420,000,  Roadway Improvement Cost: $42,000,  Total Project Cost: $462,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 3153,  Location: 0.2 MI W JCT CO RD 94 (Lat: 33.493700,  Lng: -86.139500),  Route carried "on" structure: State highway 34,  Year Built: 1921,  Year Reconstructed: 1948,  Status: Closed,  Structure Length: 2.18m (7.15ft),  Average Daily Traffic: 3,725 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 5,215 (year 2039),  Design Load: H 15,  Features Intersected: POOR HOUSE BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 17.917,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 5.5m (18.0ft),  Curb or Sidewalk Widths: Left: 0.4m (1.3ft),  Right: 0.4m (1.3ft),  Curb-To-Curb Width: 6.6m (21.7ft),  Out-to-Out Width: 7.9m (25.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Fair,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 2.97m (9.74ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $510,000,  Roadway Improvement Cost: $51,000,  Total Project Cost: $561,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 447,  Location: 4.0 MI E TALLADEGA ON CO (Lat: 33.389275,  Lng: -86.111094),  Route carried "on" structure: County highway 211,  Year Built: 1952,  Status: Posted for load,  Structure Length: 10.61m (34.81ft),  Average Daily Traffic: 670 (year 2018),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,175 (year 2038),  Design Load: H 15,  Features Intersected: TALLADEGA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.9m (25.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 10.4m (34.1ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 7.0m (23.0ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Poor,  Channel: Good,  Operating Rating: 9.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 6.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of replacement,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 11.52m (37.80ft),  Designated Inspection Frequency: Every 24 months,  Underwater Inspection Frequency: Every 48 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2020,  Underwater Inspection Date: May 2020,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $1,816,000,  Roadway Improvement Cost: $182,000,  Total Project Cost: $1,998,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 5133,  Location: SOUTH STREET W (Lat: 33.431389,  Lng: -86.110308),  Route carried "on" structure: City street ,  Year Built: 1955,  Status: Open,  Structure Length: 2.67m (8.76ft),  Average Daily Traffic: 2,011 (year 2008),  Truck Traffic: 4%,  Average Future Daily Traffic: 2,986 (year 2041),  Design Load: H 15,  Features Intersected: ISBELL BRANCH,  Facility Carried by Structure: CITY STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.299,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 6.8m (22.3ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 5.5m (18.0ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.59m (11.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $1,201,000,  Roadway Improvement Cost: $120,000,  Total Project Cost: $1,321,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 568,  Location: 1.0 S AL 21 (Lat: 33.448333,  Lng: -86.026667),  Route carried "on" structure: County highway 321,  Year Built: 1956,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 695 (year 2018),  Truck Traffic: 12%,  Average Future Daily Traffic: 890 (year 2038),  Design Load: H 15,  Features Intersected: COLBERT-BRANCH OFF KELLY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 14 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.0m (29.5ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 61.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $274,000,  Roadway Improvement Cost: $27,000,  Total Project Cost: $301,000 ( Estimate for 2022),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 8086,  Location: 1.0 MI W INT CO 509* 303 (Lat: 33.371519,  Lng: -86.092728),  Route carried "on" structure: County highway 303,  Year Built: 1963,  Status: Posted for load,  Structure Length: 4.05m (13.29ft),  Average Daily Traffic: 670 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 910 (year 2038),  Design Load: H 15,  Features Intersected: DRY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Concrete,  Design/Construction: Channel Beam,  Number Of Spans In Main Unit: 7,  Length of Maximum Span: 5.8m (19.0ft),  Curb-To-Curb Width: 6.4m (21.0ft),  Out-to-Out Width: 6.7m (22.0ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 11.8 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 9.1 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 5.01m (16.44ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2021,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $756,000,  Roadway Improvement Cost: $76,000,  Total Project Cost: $832,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 1044,  Location: 1.5 MI N STATE ROAD 21 (Lat: 33.510286,  Lng: -86.015825),  Route carried "on" structure: County highway 399,  Year Built: 1970,  Status: Posted for load,  Structure Length: 7.83m (25.69ft),  Average Daily Traffic: 927 (year 2018),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,215 (year 2038),  Design Load: H 15,  Features Intersected: CHEAHA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Number Of Approach Spans: 6,  Length of Maximum Span: 16.8m (55.1ft),  Curb or Sidewalk Widths: Left: 0.5m (1.6ft),  Right: 0.5m (1.6ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 8.2m (26.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 35.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 8.84m (29.00ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: March 2020,  Other Special Inspection Date: March 2021,  Bridge Improvement Cost: $1,577,000,  Roadway Improvement Cost: $158,000,  Total Project Cost: $1,735,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 12838,  Location: 0.3 MI S CO302 AT BERNEYS (Lat: 33.343003,  Lng: -86.134247),  Route carried "on" structure: County highway 211,  Year Built: 1982,  Status: Posted for load,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 440 (year 2018),  Average Future Daily Traffic: 490 (year 2038),  Design Load: H 10,  Features Intersected: WEEWOKA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.010,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Wood or Timber,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.6m (15.1ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 7.5m (24.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 16.6 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 12.2 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Meets minimum limits,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.18m (3.87ft),  Designated Inspection Frequency: Every 24 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: June 2020,  Other Special Inspection Date: June 2021,  Bridge Improvement Cost: $195,000,  Roadway Improvement Cost: $20,000,  Total Project Cost: $215,000 ( Estimate for 2016),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 14023,  Location: CITY OF TALLADEGA (Lat: 33.416500,  Lng: -86.133100),  Route carried "on" structure: Bypass State highway 275,  Year Built: 1986,  Status: Open,  Structure Length: 1.56m (5.12ft),  Average Daily Traffic: 8,944 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 12,522 (year 2039),  Design Load: HS 20,  Features Intersected: TOWN CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.0m (13.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.25m (7.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $1,207,000,  Roadway Improvement Cost: $121,000,  Total Project Cost: $1,328,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 14024,  Location: CITY OF TALLADEGA (Lat: 33.436653,  Lng: -86.132519),  Route carried "on" structure: Bypass State highway 275,  Year Built: 1986,  Status: Open,  Structure Length: 1.51m (4.95ft),  Average Daily Traffic: 10,387 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 14,542 (year 2039),  Design Load: HS 20,  Features Intersected: BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.061,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.6m (11.8ft)

Condition: Channel: Satisfactory,  Culverts: Fair,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 88.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.20m (7.22ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $2,371,000,  Roadway Improvement Cost: $237,000,  Total Project Cost: $2,608,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 14025,  Location: CITY OF TALLADEGA (Lat: 33.437042,  Lng: -86.132297),  Route carried "on" structure: Bypass State highway 275,  Year Built: 1986,  Status: Open,  Structure Length: 5.27m (17.29ft),  Average Daily Traffic: 10,387 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 14,542 (year 2039),  Design Load: HS 20,  Features Intersected: NORFOLK SOUTHERN R/R
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.225,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 4 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 22.3m (73.2ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 14.3m (46.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 61.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 6.30m (20.67ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $1,986,000,  Roadway Improvement Cost: $199,000,  Total Project Cost: $2,185,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 14026,  Location: CITY OF TALLADEGA (Lat: 33.441050,  Lng: -86.129233),  Route carried "on" structure: Bypass State highway 275,  Year Built: 1986,  Status: Open,  Structure Length: 6.22m (20.41ft),  Average Daily Traffic: 10,837 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 15,172 (year 2039),  Design Load: HS 20,  Features Intersected: CSX R.R.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 3.708,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 5 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.6m (84.0ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 14.3m (46.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 56.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Underclear: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 7.26m (23.82ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $2,290,000,  Roadway Improvement Cost: $229,000,  Total Project Cost: $2,519,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 14218,  Location: CITY OF TALLADEGA (Lat: 33.405383,  Lng: -86.136047),  Route carried "on" structure: State highway 21,  Year Built: 1987,  Status: Open,  Structure Length: 12.50m (41.01ft),  Average Daily Traffic: 5,405 (year 2020),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,567 (year 2040),  Design Load: HS 20,  Features Intersected: TALLADEGA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 366.274,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 11,  Length of Maximum Span: 21.3m (69.9ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 14.3m (46.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 48.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 13.34m (43.77ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $4,207,000,  Roadway Improvement Cost: $421,000,  Total Project Cost: $4,628,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 14219,  Location: CITY OF TALLADEGA (Lat: 33.421639,  Lng: -86.119056),  Route carried "on" structure: US 231,  Year Built: 1987,  Status: Open,  Structure Length: 2.02m (6.63ft),  Average Daily Traffic: 3,695 (year 2019),  Truck Traffic: 9%,  Average Future Daily Traffic: 5,173 (year 2039),  Design Load: HS 20,  Features Intersected: TOWN CREEK,  Facility Carried by Structure: AL 21
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 368.694,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.9m (16.1ft)

Condition: Channel: Satisfactory,  Culverts: Satisfactory,  Operating Rating: 71.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.77m (9.09ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: June 2021,  Bridge Improvement Cost: $1,408,000,  Roadway Improvement Cost: $141,000,  Total Project Cost: $1,549,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 16279,  Location: INT AL 34 * AL 77 (Lat: 33.476889,  Lng: -86.121411),  Route carried "on" structure: State highway 34,  Year Built: 1994,  Status: Open,  Structure Length: 0.95m (3.12ft),  Average Daily Traffic: 3,725 (year 2019),  Truck Traffic: 2%,  Average Future Daily Traffic: 5,215 (year 2039),  Design Load: HS 20,  Features Intersected: POORHOUSE BRANCH
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 20.864,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 88.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 87.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.63m (5.35ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: July 2021,  Bridge Improvement Cost: $789,000,  Roadway Improvement Cost: $79,000,  Total Project Cost: $868,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 16957,  Location: CITY OF TALLADEGA (Lat: 33.469667,  Lng: -86.033472),  Route carried "on" structure: State highway 21,  Year Built: 2007,  Status: Open,  Structure Length: 5.00m (16.40ft),  Average Daily Traffic: 3,539 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 4,955 (year 2040),  Design Load: HS 20,  Features Intersected: KELLY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 378.745,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.3m (37.1ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 30.2m (99.1ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.9m (42.3ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 71.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 6.02m (19.75ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2022,  Bridge Improvement Cost: $1,732,000,  Roadway Improvement Cost: $173,000,  Total Project Cost: $1,905,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 16958,  Location: CITY OF TALLADEGA (Lat: 33.469000,  Lng: -86.060500),  Route carried "on" structure: State highway 275,  Year Built: 2007,  Status: Open,  Structure Length: 1.34m (4.40ft),  Average Daily Traffic: 7,253 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 10,154 (year 2039),  Design Load: HS 20,  Features Intersected: STREAM
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 11.264,  Lanes on structure: 4,  Owner: State Highway Agency,  Approaching Roadway Width: 21.6m (70.9ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 50.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.02m (6.63ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $2,282,000,  Roadway Improvement Cost: $228,000,  Total Project Cost: $2,510,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 16959,  Location: CITY OF TALLADEGA (Lat: 33.473111,  Lng: -86.030139),  Route carried "on" structure: State highway 21,  Year Built: 2007,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Daily Traffic: 3,260 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 4,564 (year 2039),  Design Load: HS 20,  Features Intersected: KELLY CREEK RELIEF
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 379.186,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.0m (9.8ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 40.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.96m (6.43ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2021,  Bridge Improvement Cost: $599,000,  Roadway Improvement Cost: $60,000,  Total Project Cost: $659,000 ( Estimate for 2022)
Find on map >>   Show street view

Structure Number: 1709,  Location: 1.1MI W AL 275 (Lat: 33.427431,  Lng: -86.151281),  Route carried "on" structure: City street ,  Year Built: 1999,  Status: Open,  Structure Length: 7.93m (26.02ft),  Average Daily Traffic: 3,000 (year 2017),  Average Future Daily Traffic: 6,000 (year 2041),  Design Load: HS 20,  Features Intersected: NS RR & STREAM,  Facility Carried by Structure: RENFROE RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.770,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 19.8m (65.0ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.3m (30.5ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 43.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Meets minimum limits,  Underclear: Equal to present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 8.94m (29.33ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2021,  Bridge Improvement Cost: $1,839,000,  Roadway Improvement Cost: $184,000,  Total Project Cost: $2,023,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 17601,  Location: 0.2 MILES STH. HWY 148 (Lat: 33.167092,  Lng: -86.201647),  Route carried "on" structure: County highway 127,  Year Built: 1950,  Status: Posted for load,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 77 (year 2018),  Average Future Daily Traffic: 328 (year 2038),  Design Load: H 10,  Features Intersected: CREEK,  Facility Carried by Structure: BRICKYARD RD.
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: County Highway Agency,  Approaching Roadway Width: 6.0m (19.7ft),  Material/Design: Steel,  Design/Construction: Girder and Floorbeam System,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.2m (26.9ft),  Curb-To-Curb Width: 3.5m (11.5ft),  Out-to-Out Width: 3.7m (12.1ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Good,  Channel: Good,  Operating Rating: 8.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 6.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: High priority of replacement,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Length Of Structure Improvement: 1.58m (5.18ft),  Designated Inspection Frequency: Every 24 months,  Critical Feature Inspection Frequency: Every 12 months,  Other Special Inspection Frequency: Every 12 months,  Inspection Date: Febuary 2022,  Critical Feature Inspection Date: Febuary 2022,  Other Special Inspection Date: Febuary 2022,  Bridge Improvement Cost: $130,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $143,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Other,  Membrane: Other,  Deck Protection: Other
Find on map >>   Show street view

Structure Number: 17604,  Location: 0.2 MI EST. AL 21 (Lat: 33.397778,  Lng: -86.138611),  Route carried "on" structure: County highway 294,  Year Built: 1952,  Status: Open,  Structure Length: 0.78m (2.56ft),  Average Daily Traffic: 104 (year 2018),  Average Future Daily Traffic: 330 (year 2038),  Design Load: H 10,  Features Intersected: CREEK,  Facility Carried by Structure: OLD TALL. HWY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 5.5m (18.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.6m (24.9ft),  Curb-To-Curb Width: 4.9m (16.1ft),  Out-to-Out Width: 4.9m (16.1ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Fair,  Channel: Good,  Operating Rating: 39.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.43m (4.69ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $157,000,  Roadway Improvement Cost: $16,000,  Total Project Cost: $173,000 ( Estimate for 2022),  Deck Structure Type: Wood or Timber,  Wearing Surface/Protective System: Wearing Surface: Wood or Timber
Find on map >>   Show street view

Structure Number: 18405,  Location: CITY OF TALLADEGA (Lat: 33.405356,  Lng: -86.135739),  Route carried "on" structure: State highway 21,  Year Built: 2004,  Status: Open,  Structure Length: 10.30m (33.79ft),  Average Daily Traffic: 5,496 (year 2019),  Truck Traffic: 6%,  Average Future Daily Traffic: 7,694 (year 2039),  Design Load: HS 20,  Features Intersected: TALLADEGA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 366.274,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 42.1m (138.1ft),  Curb-To-Curb Width: 12.1m (39.7ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 76.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 11.22m (36.81ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $3,231,000,  Roadway Improvement Cost: $323,000,  Total Project Cost: $3,554,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 18851,  Location: 9.0 MI N ST. 21 @ TURNERS (Lat: 33.535000,  Lng: -86.041667),  Route carried "on" structure: County highway 5,  Year Built: 2004,  Status: Open,  Structure Length: 8.23m (27.00ft),  Average Daily Traffic: 2,225 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 3,010 (year 2038),  Design Load: HS 20,  Features Intersected: CHEAHA CREEK,  Facility Carried by Structure: EASTABOGA ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 41.1m (134.8ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.2m (36.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 62.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 34.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 9.23m (30.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,278,000,  Roadway Improvement Cost: $228,000,  Total Project Cost: $2,506,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 18852,  Location: .3 MILES SOUTH CO.RD. 302 (Lat: 33.365572,  Lng: -86.089525),  Route carried "on" structure: County highway 234,  Year Built: 2004,  Status: Open,  Structure Length: 2.44m (8.01ft),  Average Daily Traffic: 395 (year 2016),  Truck Traffic: 3%,  Average Future Daily Traffic: 440 (year 2038),  Design Load: HS 20,  Features Intersected: DRY CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 6.7m (22.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 23.0m (75.5ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Channel: Very good,  Operating Rating: 79.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 3.31m (10.86ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021,  Bridge Improvement Cost: $680,000,  Roadway Improvement Cost: $68,000,  Total Project Cost: $748,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 18853,  Location: 3.0 MILES STH JCT. I-20 (Lat: 33.544400,  Lng: -86.041533),  Route carried "on" structure: County highway 5,  Year Built: 1946,  Year Reconstructed: 2004,  Status: Open,  Structure Length: 12.34m (40.49ft),  Average Daily Traffic: 2,280 (year 2018),  Truck Traffic: 10%,  Average Future Daily Traffic: 3,010 (year 2038),  Design Load: HS 20,  Features Intersected: CHOCCOLOCCO CREEK,  Facility Carried by Structure: EASTABOGA ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Toll: Toll bridge is a segment,  Owner: County Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 3 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 41.1m (134.8ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 11.0m (36.1ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 77.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 13.19m (43.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $3,255,000,  Roadway Improvement Cost: $326,000,  Total Project Cost: $3,581,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 18854,  Location: AT INT.W/TAYLOR"S MILL RD (Lat: 33.386667,  Lng: -86.080000),  Route carried "on" structure: County highway 303,  Year Built: 2004,  Status: Open,  Structure Length: 7.32m (24.02ft),  Average Daily Traffic: 695 (year 2018),  Truck Traffic: 12%,  Average Future Daily Traffic: 1,128 (year 2038),  Design Load: HS 20,  Features Intersected: TALLADEGA CREEK
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Toll: Toll bridge is a segment,  Owner: County Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Number Of Approach Spans: 2,  Length of Maximum Span: 24.4m (80.1ft),  Curb-To-Curb Width: 8.5m (27.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Very good,  Superstructure: Good,  Substructure: Very good,  Channel: Good,  Operating Rating: 75.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 8.34m (27.36ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Bridge Improvement Cost: $1,716,000,  Roadway Improvement Cost: $172,000,  Total Project Cost: $1,888,000 ( Estimate for 2022),  Deck Structure Type: Concrete Cast-file-Place
Find on map >>   Show street view

Structure Number: 19397,  Location: .1 MI. N OF JCT ALA 34 (Lat: 33.488417,  Lng: -86.132917),  Route carried "on" structure: County highway 371,  Year Built: 1982,  Year Reconstructed: 2004,  Status: Posted for load,  Structure Length: 0.77m (2.53ft),  Average Daily Traffic: 470 (year 2014),  Truck Traffic: 6%,  Average Future Daily Traffic: 685 (year 2036),  Design Load: HS 20,  Features Intersected: A SMALL PERIODIC STREAM,  Facility Carried by Structure: NEW LINCOLN ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: County Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Aluminum, Iron,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.7m (25.3ft)

Condition: Channel: Good,  Culverts: Good,  Operating Rating: 59.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 35.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 0.1 - 9.9% below),  Length Of Structure Improvement: 1.42m (4.66ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $329,000,  Roadway Improvement Cost: $33,000,  Total Project Cost: $362,000 ( Estimate for 2022),  Deck Structure Type: Aluminum
Discuss Talladega, Alabama (AL) on our hugely popular Alabama forum.


City-data.com does not guarantee the accuracy or timeliness of any information on this site.  Use at your own risk.
Some parts © 2024 Advameg, Inc.