Bridge Statistics for Denver, Colorado (CO)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 639Number of bridges
  • 25,479ft / 7,766mTotal length
  • $98,973,000Total costs
  • 26,880,358Total average daily traffic
  • 1,763,899Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for Denver
  • No street view available for this location

New bridges in Denver, CO - historical statistics
  • New bridges - historical statistics
  • 11910-1919
  • 41920-1929
  • 21930-1939
  • 31940-1949
  • 341950-1959
  • 551960-1969
  • 511970-1979
  • 811980-1989
  • 1701990-1999
  • 952000-2009
  • 1012010-2019
  • 412020-2022
Reconstructed bridges in Denver, CO - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11950-1959
  • 41960-1969
  • 41970-1979
  • 81980-1989
  • 131990-1999
  • 72000-2009
  • 42010-2019
Average Bridge Truck Traffic in Denver, CO
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 11.8%Very good
  • 41.7%Good
  • 38.9%Satisfactory
  • 6.5%Fair
  • 1.0%Poor
  • 0.3%Serious
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 16.8%Very good
  • 49.0%Good
  • 25.4%Satisfactory
  • 8.0%Fair
  • 0.8%Poor
  • 0.3%Serious
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 17.1%Very good
  • 51.5%Good
  • 26.1%Satisfactory
  • 4.8%Fair
  • 0.5%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 58.6%Very good
  • 30.3%Good
  • 9.4%Satisfactory
  • 1.6%Fair
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 2.2%Very good
  • 27.2%Good
  • 58.7%Satisfactory
  • 10.9%Fair
  • 1.1%Poor
Find on map >>   Show street view

Structure Number: D-10-HC-24,  Location: YALE W OF QUEBEC ST (Lat: 39.667619,  Lng: -104.904703),  Route carried "on" structure: City street ,  Year Built: 1964,  Status: Open,  Structure Length: 1.40m (4.59ft),  Average Daily Traffic: 12,726 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 14,126 (year 2041),  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: YALE AVE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.995,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.8m (42.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 17.1m (56.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Very good,  Operating Rating: 33.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D-10-HC-261,  Location: QUEBEC ST AT WESLEY AVE (Lat: 39.674511,  Lng: -104.903622),  Route carried "on" structure: City street ,  Year Built: 1981,  Status: Open,  Structure Length: 0.94m (3.08ft),  Average Daily Traffic: 22,939 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 25,462 (year 2041),  Design Load: HS 20,  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: QUEBEC ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.246,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 18.3m (60.0ft),  Skew: 21 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.5m (27.9ft),  Curb or Sidewalk Widths: Left: 1.4m (4.6ft),  Right: 1.4m (4.6ft),  Curb-To-Curb Width: 18.3m (60.0ft),  Out-to-Out Width: 26.7m (87.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Good,  Operating Rating: 80.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D-10-HC-28,  Location: .1 MI N OF CORNELL (Lat: 39.664228,  Lng: -104.884625),  Route carried "on" structure: City street ,  Year Built: 1979,  Status: Open,  Structure Length: 0.86m (2.82ft),  Average Daily Traffic: 1,520 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 1,687 (year 2041),  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: YOSEMITE ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.237,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.6m (28.2ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 4.6m (15.1ft),  Curb-To-Curb Width: 31.4m (103.0ft),  Out-to-Out Width: 32.0m (105.0ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-10-HC-29,  Location: 0.1 MI NORTH OF CORNELL (Lat: 39.662553,  Lng: -104.879950),  Route carried "on" structure: City street ,  Year Built: 1983,  Status: Open,  Structure Length: 1.28m (4.20ft),  Average Future Daily Traffic: 1 (year 2041),  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: BOSTON ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.8m (25.6ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.8m (32.2ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.0m,  Curb-To-Curb Width: 7.6m (24.9ft),  Out-to-Out Width: 9.4m (30.8ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 32.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 19.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: D-10-HC-295,  Location: 0.3 MI W OF PARKER ROAD (Lat: 39.689339,  Lng: -104.894581),  Route carried "on" structure: City street ,  Year Built: 1994,  Status: Open,  Structure Length: 1.52m (4.99ft),  Average Daily Traffic: 10,425 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 11,572 (year 2041),  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: FLORIDA AVENUE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.554,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.3m (43.6ft),  Skew: 2 degrees,  Material/Design: Concrete continuous,  Design/Construction: Slab,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 8.8m (28.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 6.7m (22.0ft),  Out-to-Out Width: 9.1m (29.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 45.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 26.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.52m (4.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $279,000,  Roadway Improvement Cost: $28,000,  Total Project Cost: $307,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D-10-HC-326,  Location: .5 MI N MISSISSIPPI AVE (Lat: 39.704644,  Lng: -104.890100),  Route carried "on" structure: City street ,  Year Built: 1995,  Year Reconstructed: 2012,  Status: Open,  Structure Length: 0.69m (2.26ft),  Average Daily Traffic: 6,297 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 6,989 (year 2041),  Design Load: HS 20+Mod,  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: VALENTIA ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.111,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 16.5m (54.1ft),  Skew: 1 degrees,  Material/Design: Aluminum, Iron,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 16.5m (54.1ft),  Out-to-Out Width: 20.5m (67.3ft)

Condition: Channel: Very good,  Culverts: Good,  Inventory Rating: 71.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-10-HC-33,  Location: DAYTON AT E KENTUCKY RD (Lat: 39.700311,  Lng: -104.875353),  Route carried "on" structure: City street ,  Year Built: 1972,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 10,288 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 11,420 (year 2041),  Features Intersected: HIGHLINE CANAL,  Facility Carried by Structure: DAYTON ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.966,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Tee Beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.1m (29.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 17.1m (56.1ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Very good,  Operating Rating: 36.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 22.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: D-10-HC-38,  Location: JUST N OF 53RD AVE (Lat: 39.793817,  Lng: -104.796856),  Route carried "on" structure: City street ,  Year Built: 2003,  Status: Open,  Structure Length: 1.69m (5.54ft),  Average Daily Traffic: 2,821 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 3,131 (year 2041),  Design Load: HS 20,  Features Intersected: IRONDALE GULCH,  Facility Carried by Structure: MEMPHIS STREET
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 1.654,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 16.5m (54.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.0m (13.1ft),  Curb or Sidewalk Widths: Left: 2.3m (7.5ft),  Right: 2.3m (7.5ft),  Curb-To-Curb Width: 16.5m (54.1ft),  Out-to-Out Width: 21.7m (71.2ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 52.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 31.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-10-HC-39,  Location: 0.2 MI EAST OF CHAMBERS (Lat: 39.794453,  Lng: -104.804594),  Route carried "on" structure: City street ,  Year Built: 2001,  Status: Open,  Structure Length: 0.63m (2.07ft),  Average Daily Traffic: 1,198 (year 2021),  Average Future Daily Traffic: 1,330 (year 2041),  Features Intersected: IRONDALE GULCH,  Facility Carried by Structure: MAXWELL PLACE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 2.842,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 2.4m (7.9ft),  Out-to-Out Width: 30.5m (100.1ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-10-HC-395,  Location: JUST EAST OF CHAMBERS RD (Lat: 39.798111,  Lng: -104.807892),  Route carried "on" structure: City street ,  Year Built: 2000,  Status: Open,  Structure Length: 1.93m (6.33ft),  Average Daily Traffic: 17,525 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 19,453 (year 2041),  Design Load: HS 20,  Features Intersected: IRONDALE GULCH,  Facility Carried by Structure: 56TH AVENUE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 6.548,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 7.6m (24.9ft),  Skew: 6 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 6.1m (20.0ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 3.0m (9.8ft),  Out-to-Out Width: 58.8m (192.9ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 75.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-005,  Location: JUST E OF MONACO PKWY (Lat: 39.690419,  Lng: -104.912386),  Route carried "on" structure: City street ,  Year Built: 1995,  Status: Open,  Structure Length: 0.79m (2.59ft),  Average Daily Traffic: 7,921 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 8,792 (year 2041),  Features Intersected: STORM DRAINAGE,  Facility Carried by Structure: CHERRY CK DR
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.035,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 1.5m (4.9ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 3.7m (12.1ft),  Out-to-Out Width: 21.9m (71.9ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-010A,  Location: E OF MONACO PKWY (Lat: 39.689731,  Lng: -104.911464),  Route carried "on" structure: City street ,  Year Built: 1960,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.36m (4.46ft),  Average Daily Traffic: 7,921 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 8,792 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: CHERRY CREEK DR
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.140,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.8m (12.5ft),  Curb-To-Curb Width: 10.9m (35.8ft),  Out-to-Out Width: 20.3m (66.6ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 88.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 53.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: D-11-GG-04,  Location: E OF MONACO PKWY (Lat: 39.685717,  Lng: -104.912178),  Route carried "on" structure: City street ,  Year Built: 1966,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 1,158 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,286 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: MEXICO AVE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.871,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 3.4m (11.2ft),  Right: 3.4m (11.2ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 18.5m (60.7ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 49.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-050A,  Location: AT COLO DR & JEWELL (Lat: 39.681997,  Lng: -104.913250),  Route carried "on" structure: City street ,  Year Built: 1965,  Year Reconstructed: 1995,  Status: Open,  Structure Length: 1.36m (4.46ft),  Average Daily Traffic: 15,005 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 16,656 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: MONACO PARKWAY
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.203,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 16.5m (54.1ft),  Skew: 9 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 4.3m (14.1ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 2.6m (8.5ft),  Out-to-Out Width: 38.6m (126.6ft)

Condition: Channel: Very good,  Culverts: Fair,  Operating Rating: 55.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 33.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-07,  Location: JEWELL AT MONACO PKWY (Lat: 39.682086,  Lng: -104.913339),  Route carried "on" structure: City street ,  Year Built: 1972,  Status: Open,  Structure Length: 1.01m (3.31ft),  Average Daily Traffic: 2,421 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 2,687 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: JEWELL AVENUE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 2.266,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.9m (16.1ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.9m (52.2ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 48.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-075,  Location: JUST SO OF JEWELL AVE (Lat: 39.681497,  Lng: -104.912703),  Route carried "on" structure: City street ,  Year Built: 1996,  Status: Open,  Structure Length: 0.87m (2.85ft),  Average Daily Traffic: 24,382 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 27,064 (year 2041),  Features Intersected: RETENTION POND DRAINAGE,  Facility Carried by Structure: MONACO PARKWAY
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.261,  Lanes on structure: 6,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 21.5m (70.5ft),  Skew: 20 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 2.4m (7.9ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 4.9m (16.1ft),  Curb-To-Curb Width: 21.5m (70.5ft),  Out-to-Out Width: 32.4m (106.3ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 47.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-08,  Location: AT EVANS AVE (Lat: 39.679047,  Lng: -104.913117),  Route carried "on" structure: City street ,  Year Built: 1966,  Status: Open,  Structure Length: 1.36m (4.46ft),  Average Daily Traffic: 26,351 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 29,250 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: MONACO PKWY
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.538,  Lanes on structure: 5,  Base Highway Network: Yes,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 17.4m (57.1ft),  Skew: 4 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 6.6m (21.7ft),  Curb or Sidewalk Widths: Left: 2.6m (8.5ft),  Right: 3.5m (11.5ft),  Out-to-Out Width: 60.0m (196.9ft)

Condition: Channel: Good,  Culverts: Fair,  Operating Rating: 46.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-09,  Location: E OF MONACO PKWY (Lat: 39.674731,  Lng: -104.911133),  Route carried "on" structure: City street ,  Year Built: 1971,  Status: Open,  Structure Length: 0.93m (3.05ft),  Average Daily Traffic: 1,550 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,720 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: ILIFF AVE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.998,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.5m (14.8ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.2m (3.9ft),  Out-to-Out Width: 23.5m (77.1ft)

Condition: Channel: Very good,  Culverts: Good,  Operating Rating: 87.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 52.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-11-GG-100A,  Location: AT ONEIDA STREET (Lat: 39.667631,  Lng: -104.906150),  Route carried "on" structure: City street ,  Year Built: 1995,  Status: Open,  Structure Length: 0.81m (2.66ft),  Average Daily Traffic: 15,901 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 17,650 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: YALE AVE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.864,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.3m (43.6ft),  Skew: 3 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.3m (17.4ft),  Curb or Sidewalk Widths: Left: 3.6m (11.8ft),  Right: 3.1m (10.2ft),  Curb-To-Curb Width: 13.3m (43.6ft),  Out-to-Out Width: 33.5m (109.9ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 88.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 53.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-11-GG-120A,  Location: JUST W OF TAMARAC DRIVE (Lat: 39.660358,  Lng: -104.904086),  Route carried "on" structure: City street ,  Year Built: 1971,  Year Reconstructed: 1996,  Status: Open,  Structure Length: 2.16m (7.09ft),  Average Daily Traffic: 2,767 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,072 (year 2041),  Design Load: HS 20,  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: CORNELL AVENUE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.824,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.7m (28.5ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 5,  Length of Maximum Span: 4.3m (14.1ft),  Curb or Sidewalk Widths: Left: 2.7m (8.9ft),  Right: 0.0m,  Out-to-Out Width: 56.7m (186.0ft)

Condition: Channel: Fair,  Culverts: Fair,  Operating Rating: 47.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 28.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Waterway Adequacy: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-11-GG-13,  Location: JUST W OF TAMARAC DR (Lat: 39.656714,  Lng: -104.902428),  Route carried "on" structure: City street ,  Year Built: 1978,  Status: Open,  Structure Length: 1.46m (4.79ft),  Average Daily Traffic: 3,301 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 3,665 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: EASTMAN AVENUE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.185,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Skew: 1 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 3.8m (12.5ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 21.4m (70.2ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 27.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-11-GG-170A,  Location: JUST W OF TAMARAC DRIVE (Lat: 39.649000,  Lng: -104.898139),  Route carried "on" structure: City street ,  Year Built: 1985,  Status: Open,  Structure Length: 1.03m (3.38ft),  Average Daily Traffic: 2,030 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,253 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: ROSEMARY WAY
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.052,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.0m (16.4ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 17.5m (57.4ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-11-GG-180A,  Location: W OF TAMARAC DRIVE (Lat: 39.643303,  Lng: -104.894169),  Route carried "on" structure: City street ,  Year Built: 1985,  Status: Open,  Structure Length: 1.02m (3.35ft),  Average Daily Traffic: 2,176 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 2,415 (year 2041),  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: PRINCETON AVE
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 1.344,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 14.0m (45.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 5.0m (16.4ft),  Curb or Sidewalk Widths: Left: 1.9m (6.2ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 13.7m (44.9ft),  Out-to-Out Width: 19.3m (63.3ft)

Condition: Channel: Fair,  Culverts: Satisfactory,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020
Find on map >>   Show street view

Structure Number: D-11-GG-19,  Location: JUST NE OF TAMARAC STREET (Lat: 39.638669,  Lng: -104.894042),  Route carried "on" structure: City street ,  Year Built: 1972,  Status: Open,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 10,760 (year 2021),  Truck Traffic: 6%,  Average Future Daily Traffic: 11,944 (year 2041),  Design Load: HS 20+Mod,  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: QUINCY AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.646,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 17.3m (56.8ft),  Material/Design: Steel,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.9m (12.8ft),  Curb or Sidewalk Widths: Left: 3.4m (11.2ft),  Right: 0.6m (2.0ft),  Curb-To-Curb Width: 17.3m (56.8ft),  Out-to-Out Width: 39.9m (130.9ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: September 2021
Find on map >>   Show street view

Structure Number: D-11-GG-2,  Location: JUST E OF DTC BLVD (Lat: 39.624100,  Lng: -104.889050),  Route carried "on" structure: City street ,  Year Built: 1986,  Status: Open,  Structure Length: 1.94m (6.36ft),  Average Daily Traffic: 20,376 (year 2021),  Truck Traffic: 5%,  Average Future Daily Traffic: 22,617 (year 2041),  Design Load: HS 20,  Features Intersected: GOLDSMITH GULCH,  Facility Carried by Structure: BELLEVIEW AVE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.144,  Lanes on structure: 8,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 28.7m (94.2ft),  Skew: 32 degrees,  Material/Design: Concrete,  Design/Construction: Frame,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 18.2m (59.7ft),  Curb or Sidewalk Widths: Left: 3.2m (10.5ft),  Right: 3.2m (10.5ft),  Curb-To-Curb Width: 28.7m (94.2ft),  Out-to-Out Width: 39.1m (128.3ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Very good,  Operating Rating: 98.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of corrective action,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.94m (6.36ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Bridge Improvement Cost: $618,000,  Roadway Improvement Cost: $62,000,  Total Project Cost: $679,000 ( Estimate for 2014),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-12-S,  Location: 19.2 MI E OF JCT SH 9 (Lat: 40.084389,  Lng: -106.077983),  Route carried "on" structure: US 40A,  Year Built: 1987,  Status: Open,  Structure Length: 7.67m (25.16ft),  Average Daily Traffic: 3,400 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 4,046 (year 2040),  Design Load: HS 20,  Features Intersected: COLORADO RIVER,  Facility Carried by Structure: US 40 ML
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 326.488,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 25.5m (83.7ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Very good,  Operating Rating: 71.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Preformed Fabric,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D-12-SG-09,  Location: BTWN IOWA AND MEXICO (Lat: 39.686700,  Lng: -105.029808),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Open,  Structure Length: 0.64m (2.10ft),  Average Daily Traffic: 5,723 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 6,353 (year 2041),  Features Intersected: SANDERSON GULCH,  Facility Carried by Structure: IRVING ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 3.259,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 3.0m (9.8ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 21.9m (71.9ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 48.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-12-SG-13,  Location: JUST S OF FLORIDA AVENUE (Lat: 39.688842,  Lng: -105.015706),  Route carried "on" structure: City street ,  Year Built: 1979,  Status: Open,  Structure Length: 0.84m (2.76ft),  Average Daily Traffic: 4,930 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 5,473 (year 2041),  Features Intersected: SANDERSON GULCH,  Facility Carried by Structure: ZUNI STREET
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 1.231,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 2 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.0m (13.1ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 2.0m (6.6ft),  Out-to-Out Width: 33.8m (110.9ft)

Condition: Channel: Good,  Culverts: Satisfactory,  Operating Rating: 36.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-12-SG-160A,  Location: AT ARKANSAS AVENUE (Lat: 39.691381,  Lng: -105.001650),  Route carried "on" structure: City street ,  Year Built: 2019,  Status: Open,  Structure Length: 1.33m (4.36ft),  Average Daily Traffic: 1,123 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 1,246 (year 2041),  Design Load: HL 93,  Features Intersected: SANDERSON GULCH,  Facility Carried by Structure: LIPAN ST
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 9 degrees,  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.3m (14.1ft),  Curb or Sidewalk Widths: Left: 2.5m (8.2ft),  Right: 1.6m (5.2ft),  Out-to-Out Width: 70.2m (230.3ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 96.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 96.9 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-12-SG-170A,  Location: 0.1 MI N OF FLORIDA (Lat: 39.690181,  Lng: -104.999733),  Route carried "on" structure: City street ,  Year Built: 2020,  Status: Open,  Structure Length: 2.08m (6.82ft),  Average Daily Traffic: 2,581 (year 2021),  Truck Traffic: 4%,  Average Future Daily Traffic: 2,865 (year 2041),  Design Load: HL 93,  Features Intersected: SANDERSON GULCH,  Facility Carried by Structure: S. PLATTE RIVER DR
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.581,  Lanes on structure: 3,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 4.9m (16.1ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 9.9m (32.5ft),  Out-to-Out Width: 124.2m (407.5ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 96.9 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 92.7 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: January 2021
Find on map >>   Show street view

Structure Number: D-13-H,  Location: 3.4 MI NO OF GRANBY (Lat: 40.118239,  Lng: -105.906850),  Route carried "on" structure: US 34A,  Year Built: 1999,  Status: Open,  Structure Length: 3.00m (9.84ft),  Average Daily Traffic: 6,300 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,497 (year 2040),  Design Load: HS 20,  Features Intersected: COLORADO RIVER OVFLW,  Facility Carried by Structure: US 34 ML
Minimum Vertical Clearance: 30.45m (99.90ft),  Kilometerpoint: 5.517,  Lanes on structure: 2,  Base Highway Network: Yes,  Owner: State Highway Agency,  Approaching Roadway Width: 12.8m (42.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.2m (95.8ft),  Curb-To-Curb Width: 12.0m (39.4ft),  Out-to-Out Width: 12.7m (41.7ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Very good,  Operating Rating: 64.8 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 32.4 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Precast Panels,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: D-13-HGE-05,  Location: BTWN DOWNING AND MARION (Lat: 39.671267,  Lng: -104.972897),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load,  Structure Length: 0.92m (3.02ft),  Average Daily Traffic: 34 (year 2021),  Average Future Daily Traffic: 37 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: ALLEY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.782,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.3m (14.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.4m (27.6ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 4.6m (15.1ft),  Out-to-Out Width: 5.9m (19.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 18.4 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 11.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-06,  Location: MARION ST AND HARVARD (Lat: 39.671267,  Lng: -104.972303),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Open,  Structure Length: 0.87m (2.85ft),  Average Daily Traffic: 261 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 290 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: S MARION ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.608,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 46.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-07,  Location: BTWN MARION AND LAFF (Lat: 39.671267,  Lng: -104.971731),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Open,  Structure Length: 0.87m (2.85ft),  Average Daily Traffic: 23 (year 2021),  Average Future Daily Traffic: 25 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: ALLEY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 4.6m (15.1ft),  Out-to-Out Width: 5.9m (19.4ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 35.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 21.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-08,  Location: LAFAYETTE AT HARVARD GL (Lat: 39.671261,  Lng: -104.971150),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load-capacity,  Structure Length: 0.87m (2.85ft),  Average Daily Traffic: 258 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 286 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: LAFAYETTE ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.830,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 25.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 15.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-09,  Location: BTWN LAFAYETTE AND HUMB (Lat: 39.671256,  Lng: -104.970556),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 39 (year 2021),  Average Future Daily Traffic: 43 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: ALLEY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 4.6m (15.1ft),  Out-to-Out Width: 5.9m (19.4ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 17.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 10.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: High priority of corrective action,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-1,  Location: HUMBOLDT & E HARVARD (Lat: 39.671250,  Lng: -104.969978),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load,  Structure Length: 0.88m (2.89ft),  Average Daily Traffic: 259 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 287 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: HUMBOLDT ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.767,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 7.9m (25.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 24.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 14.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-11,  Location: FRANKLIN & E HARVARD (Lat: 39.671228,  Lng: -104.968808),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load-capacity,  Structure Length: 0.92m (3.02ft),  Average Daily Traffic: 574 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 637 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: FRANKLIN ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 2.396,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.4m (27.6ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 27.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-12,  Location: GILPIN AT HARVARD AVE (Lat: 39.671217,  Lng: -104.967617),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load,  Structure Length: 0.91m (2.99ft),  Average Daily Traffic: 295 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 327 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: GILPIN ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.576,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.4m (27.6ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 27.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 16.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Length Of Structure Improvement: 0.91m (2.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Bridge Improvement Cost: $14,000,  Roadway Improvement Cost: $13,000,  Total Project Cost: $26,000,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-13,  Location: AT E HARVARD GULCH (Lat: 39.671222,  Lng: -104.966456),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load,  Structure Length: 0.92m (3.02ft),  Average Daily Traffic: 281 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 311 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: WILLIAMS ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.542,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.4m (27.6ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Channel: Good,  Operating Rating: 25.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 15.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 20.0 - 29.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-14,  Location: BTWN WILLIAMS AND HIGH (Lat: 39.671206,  Lng: -104.965869),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 41 (year 2021),  Average Future Daily Traffic: 45 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: ALLEY
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 4.6m (15.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb or Sidewalk Widths: Left: 0.3m (1.0ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 4.6m (15.1ft),  Out-to-Out Width: 5.9m (19.4ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Channel: Good,  Operating Rating: 18.9 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 11.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Meets minimum limits,  Deck Geometry: Better than present minimum criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: > 39.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up
Find on map >>   Show street view

Structure Number: D-13-HGE-15,  Location: 1 BLK N of VASSAR (Lat: 39.671203,  Lng: -104.965272),  Route carried "on" structure: City street ,  Year Built: 1967,  Status: Posted for load-capacity,  Structure Length: 0.96m (3.15ft),  Average Daily Traffic: 222 (year 2021),  Truck Traffic: 2%,  Average Future Daily Traffic: 247 (year 2041),  Features Intersected: EAST HARVARD GULCH,  Facility Carried by Structure: HIGH ST
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.463,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Material/Design: Concrete,  Design/Construction: Slab,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 8.8m (28.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 0.3m (1.0ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 13.6m (44.6ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Good,  Channel: Satisfactory,  Operating Rating: 30.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 18.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present desirable criteria,  Waterway Adequacy: Equal to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Bridge Posting: Required (Relationship of Operating Rating to Maximum Legal Load: 10.0 - 19.9% below),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2020,  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous,  Membrane: Built-up