Bridge Statistics for New York, New York (NY)
Condition, Traffic, Stress, Structural Evaluation, Project Costs
- National Bridge Inventory (NBI) Statistics
- 2,992Number of bridges
- 68,865ft / 20,990mTotal length
- $41,847,025,000Total costs
- 106,047,317Total average daily traffic
- 3,057,321Total average daily truck traffic
- National Bridge Inventory (NBI) Registered Bridges for New York
- No street view available for this location
- New bridges - historical statistics
- 47Before 1900
- 1961900-1909
- 1711910-1919
- 1241920-1929
- 3951930-1939
- 2541940-1949
- 4641950-1959
- 7351960-1969
- 1551970-1979
- 881980-1989
- 731990-1999
- 1432000-2009
- 1242010-2019
- 232020-2022
- Reconstructed bridges - Historical Statistics
- 11920-1929
- 121930-1939
- 01940-1949
- 71950-1959
- 81960-1969
- 491970-1979
- 1441980-1989
- 1731990-1999
- 982000-2009
- 652010-2019
- 52020-2022
- Bridge Condition - Deck
- 9.4%Excellent
- 13.0%Very good
- 23.3%Good
- 29.7%Satisfactory
- 20.6%Fair
- 4.0%Poor
- Bridge Condition - Superstructure
- 9.1%Excellent
- 12.8%Very good
- 20.5%Good
- 34.5%Satisfactory
- 19.5%Fair
- 3.5%Poor
- Bridge Condition - Substructure
- 5.9%Excellent
- 9.8%Very good
- 24.0%Good
- 39.8%Satisfactory
- 18.9%Fair
- 1.7%Poor
- Bridge Condition - Channel
- 8.6%Excellent
- 19.0%Very good
- 24.5%Good
- 30.7%Satisfactory
- 10.4%Fair
- 4.9%Poor
- 1.8%Serious
- Bridge Condition - Culverts
- 9.5%Very good
- 14.3%Good
- 47.6%Satisfactory
- 28.6%Fair
Find on map >> Show street view
Structure Number: 2231329, Location: .5MI NW SHORE PKY+CROPSEY (Lat: 40.589781, Lng: -73.992858), Route carried "on" structure: City street 907C, Year Built: 1941, Status: Open, Structure Length: 2.47m (8.10ft), Average Daily Traffic: 124,775 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 153,847 (year 2040), Design Load: H 20, Features Intersected: 26 AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 9.413, Lanes on structure: 6, Lanes under structure: 2, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 20.7m (67.9ft), Skew: 20 degrees, Material/Design: Concrete, Design/Construction: Frame, Number Of Spans In Main Unit: 1, Length of Maximum Span: 21.6m (70.9ft), Curb or Sidewalk Widths: Left: 0.9m (3.0ft), Right: 1.4m (4.6ft), Curb-To-Curb Width: 20.7m (67.9ft), Out-to-Out Width: 25.2m (82.7ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Satisfactory, Operating Rating: 60.5 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 23.5 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 2.46m (8.07ft), Designated Inspection Frequency: Every 24 months, Inspection Date: March 2020, Bridge Improvement Cost: $4,421,000, Roadway Improvement Cost: $2,589,000, Total Project Cost: $7,010,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Structure Number: 2231329, Location: .5MI NW SHORE PKY+CROPSEY (Lat: 40.589781, Lng: -73.992858), Route carried "on" structure: City street 907C, Year Built: 1941, Status: Open, Structure Length: 2.47m (8.10ft), Average Daily Traffic: 124,775 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 153,847 (year 2040), Design Load: H 20, Features Intersected: 26 AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 9.413, Lanes on structure: 6, Lanes under structure: 2, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 20.7m (67.9ft), Skew: 20 degrees, Material/Design: Concrete, Design/Construction: Frame, Number Of Spans In Main Unit: 1, Length of Maximum Span: 21.6m (70.9ft), Curb or Sidewalk Widths: Left: 0.9m (3.0ft), Right: 1.4m (4.6ft), Curb-To-Curb Width: 20.7m (67.9ft), Out-to-Out Width: 25.2m (82.7ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Satisfactory, Operating Rating: 60.5 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 23.5 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 2.46m (8.07ft), Designated Inspection Frequency: Every 24 months, Inspection Date: March 2020, Bridge Improvement Cost: $4,421,000, Roadway Improvement Cost: $2,589,000, Total Project Cost: $7,010,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >> Show street view
Structure Number: 223134, Location: JCT SHORE PKY+CROPSEY AVE (Lat: 40.584142, Lng: -73.986911), Route carried "on" structure: Business City street , Year Built: 1941, Year Reconstructed: 1990, Status: Open, Structure Length: 3.93m (12.89ft), Average Daily Traffic: 23,012 (year 2019), Truck Traffic: 7%, Average Future Daily Traffic: 23,120 (year 2040), Design Load: H 20, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: CROPSEY AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.579, Lanes on structure: 6, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.5m (77.1ft), Skew: 24 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 19.2m (63.0ft), Curb or Sidewalk Widths: Left: 3.6m (11.8ft), Right: 3.3m (10.8ft), Curb-To-Curb Width: 23.5m (77.1ft), Out-to-Out Width: 31.1m (102.0ft)
Condition: Deck: Fair, Superstructure: Good, Substructure: Good, Operating Rating: 67.1 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 39.9 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Somewhat better than minimum adequacy, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 3.93m (12.89ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: April 2020, Critical Feature Inspection Date: April 2020, Bridge Improvement Cost: $9,115,000, Roadway Improvement Cost: $5,338,000, Total Project Cost: $14,453,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Structure Number: 223134, Location: JCT SHORE PKY+CROPSEY AVE (Lat: 40.584142, Lng: -73.986911), Route carried "on" structure: Business City street , Year Built: 1941, Year Reconstructed: 1990, Status: Open, Structure Length: 3.93m (12.89ft), Average Daily Traffic: 23,012 (year 2019), Truck Traffic: 7%, Average Future Daily Traffic: 23,120 (year 2040), Design Load: H 20, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: CROPSEY AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.579, Lanes on structure: 6, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.5m (77.1ft), Skew: 24 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 19.2m (63.0ft), Curb or Sidewalk Widths: Left: 3.6m (11.8ft), Right: 3.3m (10.8ft), Curb-To-Curb Width: 23.5m (77.1ft), Out-to-Out Width: 31.1m (102.0ft)
Condition: Deck: Fair, Superstructure: Good, Substructure: Good, Operating Rating: 67.1 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 39.9 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Somewhat better than minimum adequacy, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 3.93m (12.89ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: April 2020, Critical Feature Inspection Date: April 2020, Bridge Improvement Cost: $9,115,000, Roadway Improvement Cost: $5,338,000, Total Project Cost: $14,453,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >> Show street view
Structure Number: 2231359, Location: .7 MI W SHORE PKY+OCEAN P (Lat: 40.582794, Lng: -73.974497), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1988, Status: Open, Structure Length: 83.52m (274.02ft), Average Daily Traffic: 116,826 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 144,046 (year 2040), Design Load: HS 20, Features Intersected: SHELL ROAD, STILLWELL AV
Minimum Vertical Clearance: 4.22m (13.85ft), Kilometerpoint: 10.442, Lanes on structure: 6, Lanes under structure: 8, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 22.6m (74.1ft), Skew: 21 degrees, Material/Design: Steel, Design/Construction: Girder and Floorbeam System, Number Of Spans In Main Unit: 37, Length of Maximum Span: 34.4m (112.9ft), Curb-To-Curb Width: 21.3m (69.9ft), Out-to-Out Width: 23.9m (78.4ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Fair, Operating Rating: 82.7 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 32.7 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 83.51m (273.98ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 12 months, Inspection Date: December 2021, Critical Feature Inspection Date: December 2021, Bridge Improvement Cost: $84,896,000, Roadway Improvement Cost: $49,715,000, Total Project Cost: $134,611,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231359, Location: .7 MI W SHORE PKY+OCEAN P (Lat: 40.582794, Lng: -73.974497), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1988, Status: Open, Structure Length: 83.52m (274.02ft), Average Daily Traffic: 116,826 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 144,046 (year 2040), Design Load: HS 20, Features Intersected: SHELL ROAD, STILLWELL AV
Minimum Vertical Clearance: 4.22m (13.85ft), Kilometerpoint: 10.442, Lanes on structure: 6, Lanes under structure: 8, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 22.6m (74.1ft), Skew: 21 degrees, Material/Design: Steel, Design/Construction: Girder and Floorbeam System, Number Of Spans In Main Unit: 37, Length of Maximum Span: 34.4m (112.9ft), Curb-To-Curb Width: 21.3m (69.9ft), Out-to-Out Width: 23.9m (78.4ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Fair, Operating Rating: 82.7 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 32.7 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 83.51m (273.98ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 12 months, Inspection Date: December 2021, Critical Feature Inspection Date: December 2021, Bridge Improvement Cost: $84,896,000, Roadway Improvement Cost: $49,715,000, Total Project Cost: $134,611,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 223136, Location: JCT SHORE PK & OCEAN PKWY (Lat: 40.583928, Lng: -73.966686), Route carried "on" structure: Interstate 907C, Year Built: 2004, Status: Open, Structure Length: 6.77m (22.21ft), Average Daily Traffic: 116,826 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 144,046 (year 2040), Design Load: HS 25 or greater, Features Intersected: OCEAN PARKWAY
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 11.955, Lanes on structure: 8, Lanes under structure: 12, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 40.8m (133.9ft), Skew: 21 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 32.9m (107.9ft), Curb-To-Curb Width: 39.2m (128.6ft), Out-to-Out Width: 40.7m (133.5ft)
Condition: Deck: Very good, Superstructure: Very good, Substructure: Good, Inventory Rating: 45.0 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Superior to present desirable criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 6.76m (22.18ft), Designated Inspection Frequency: Every 24 months, Inspection Date: April 2020, Bridge Improvement Cost: $15,993,000, Roadway Improvement Cost: $9,366,000, Total Project Cost: $25,359,000 ( Estimate for 2021), Deck Structure Type: Concrete Precast Panels, Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Structure Number: 223136, Location: JCT SHORE PK & OCEAN PKWY (Lat: 40.583928, Lng: -73.966686), Route carried "on" structure: Interstate 907C, Year Built: 2004, Status: Open, Structure Length: 6.77m (22.21ft), Average Daily Traffic: 116,826 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 144,046 (year 2040), Design Load: HS 25 or greater, Features Intersected: OCEAN PARKWAY
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 11.955, Lanes on structure: 8, Lanes under structure: 12, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 40.8m (133.9ft), Skew: 21 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 32.9m (107.9ft), Curb-To-Curb Width: 39.2m (128.6ft), Out-to-Out Width: 40.7m (133.5ft)
Condition: Deck: Very good, Superstructure: Very good, Substructure: Good, Inventory Rating: 45.0 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Superior to present desirable criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 6.76m (22.18ft), Designated Inspection Frequency: Every 24 months, Inspection Date: April 2020, Bridge Improvement Cost: $15,993,000, Roadway Improvement Cost: $9,366,000, Total Project Cost: $25,359,000 ( Estimate for 2021), Deck Structure Type: Concrete Precast Panels, Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >> Show street view
Structure Number: 223137, Location: .3MI E BELT PKY+OCEAN PKY (Lat: 40.584408, Lng: -73.961578), Route carried "on" structure: Ramp State highway 907C, Year Built: 2012, Status: Open, Structure Length: 8.90m (29.20ft), Truck Traffic: 1%, Design Load: HS 25 or greater, Features Intersected: RTE 907C, RTE 907C, SERV
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.113, Lanes on structure: 1, Lanes under structure: 7, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 7.3m (24.0ft), Skew: 4 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 25.0m (82.0ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.1m (10.2ft), Curb-To-Curb Width: 7.2m (23.6ft), Out-to-Out Width: 11.3m (37.1ft)
Condition: Deck: Very good, Superstructure: Excellent, Substructure: Very good, Operating Rating: 87.0 metric tons, Method Used To Determine Operating Rating: Allowable Stress (AS), Inventory Rating: 45.0 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Equal to present desirable criteria, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 8.90m (29.20ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2020, Bridge Improvement Cost: $5,489,000, Roadway Improvement Cost: $3,214,000, Total Project Cost: $8,704,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 223137, Location: .3MI E BELT PKY+OCEAN PKY (Lat: 40.584408, Lng: -73.961578), Route carried "on" structure: Ramp State highway 907C, Year Built: 2012, Status: Open, Structure Length: 8.90m (29.20ft), Truck Traffic: 1%, Design Load: HS 25 or greater, Features Intersected: RTE 907C, RTE 907C, SERV
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.113, Lanes on structure: 1, Lanes under structure: 7, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 7.3m (24.0ft), Skew: 4 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 25.0m (82.0ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.1m (10.2ft), Curb-To-Curb Width: 7.2m (23.6ft), Out-to-Out Width: 11.3m (37.1ft)
Condition: Deck: Very good, Superstructure: Excellent, Substructure: Very good, Operating Rating: 87.0 metric tons, Method Used To Determine Operating Rating: Allowable Stress (AS), Inventory Rating: 45.0 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Equal to present desirable criteria, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 8.90m (29.20ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2020, Bridge Improvement Cost: $5,489,000, Roadway Improvement Cost: $3,214,000, Total Project Cost: $8,704,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 223138, Location: .4MI E BELT PKY+OCEAN PKY (Lat: 40.584639, Lng: -73.960183), Route carried "on" structure: Business City street , Year Built: 1942, Year Reconstructed: 2001, Status: Open, Structure Length: 9.17m (30.09ft), Average Daily Traffic: 11,038 (year 2011), Truck Traffic: 7%, Average Future Daily Traffic: 11,089 (year 2040), Design Load: HS 25 or greater, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: CONEY ISLAND AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.965, Lanes on structure: 4, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 14.0m (45.9ft), Skew: 20 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 24.6m (80.7ft), Curb or Sidewalk Widths: Left: 2.4m (7.9ft), Right: 2.4m (7.9ft), Curb-To-Curb Width: 14.0m (45.9ft), Out-to-Out Width: 20.1m (65.9ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Good, Inventory Rating: 55.3 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 9.17m (30.09ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: October 2021, Critical Feature Inspection Date: October 2021, Bridge Improvement Cost: $9,162,000, Roadway Improvement Cost: $5,365,000, Total Project Cost: $14,527,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Latex Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 223138, Location: .4MI E BELT PKY+OCEAN PKY (Lat: 40.584639, Lng: -73.960183), Route carried "on" structure: Business City street , Year Built: 1942, Year Reconstructed: 2001, Status: Open, Structure Length: 9.17m (30.09ft), Average Daily Traffic: 11,038 (year 2011), Truck Traffic: 7%, Average Future Daily Traffic: 11,089 (year 2040), Design Load: HS 25 or greater, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: CONEY ISLAND AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.965, Lanes on structure: 4, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 14.0m (45.9ft), Skew: 20 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 24.6m (80.7ft), Curb or Sidewalk Widths: Left: 2.4m (7.9ft), Right: 2.4m (7.9ft), Curb-To-Curb Width: 14.0m (45.9ft), Out-to-Out Width: 20.1m (65.9ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Good, Inventory Rating: 55.3 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 9.17m (30.09ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: October 2021, Critical Feature Inspection Date: October 2021, Bridge Improvement Cost: $9,162,000, Roadway Improvement Cost: $5,365,000, Total Project Cost: $14,527,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Latex Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 223139, Location: .5MI E BELT PKY+OCEAN PKY (Lat: 40.584997, Lng: -73.957547), Route carried "on" structure: City street , Year Built: 1942, Year Reconstructed: 1988, Status: Open, Structure Length: 8.26m (27.10ft), Truck Traffic: 4%, Design Load: H 20, Features Intersected: RTE 907C, RTE 907C, RTE, Facility Carried by Structure: E 12TH ST
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 4.811, Lanes on structure: 2, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 11.9m (39.0ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 22.5m (73.8ft), Curb or Sidewalk Widths: Left: 1.5m (4.9ft), Right: 2.1m (6.9ft), Curb-To-Curb Width: 11.7m (38.4ft), Out-to-Out Width: 17.9m (58.7ft)
Condition: Deck: Satisfactory, Superstructure: Satisfactory, Substructure: Satisfactory, Operating Rating: 41.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 24.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Superior to present desirable criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 8.26m (27.10ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: April 2020, Critical Feature Inspection Date: April 2020, Bridge Improvement Cost: $7,543,000, Roadway Improvement Cost: $4,417,000, Total Project Cost: $11,961,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Structure Number: 223139, Location: .5MI E BELT PKY+OCEAN PKY (Lat: 40.584997, Lng: -73.957547), Route carried "on" structure: City street , Year Built: 1942, Year Reconstructed: 1988, Status: Open, Structure Length: 8.26m (27.10ft), Truck Traffic: 4%, Design Load: H 20, Features Intersected: RTE 907C, RTE 907C, RTE, Facility Carried by Structure: E 12TH ST
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 4.811, Lanes on structure: 2, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 11.9m (39.0ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 22.5m (73.8ft), Curb or Sidewalk Widths: Left: 1.5m (4.9ft), Right: 2.1m (6.9ft), Curb-To-Curb Width: 11.7m (38.4ft), Out-to-Out Width: 17.9m (58.7ft)
Condition: Deck: Satisfactory, Superstructure: Satisfactory, Substructure: Satisfactory, Operating Rating: 41.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 24.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Superior to present desirable criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 8.26m (27.10ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: April 2020, Critical Feature Inspection Date: April 2020, Bridge Improvement Cost: $7,543,000, Roadway Improvement Cost: $4,417,000, Total Project Cost: $11,961,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >> Show street view
Structure Number: 2231409, Location: .8MI E BELT PKY+OCEAN PKY (Lat: 40.584689, Lng: -73.951094), Route carried "on" structure: Interstate 907C, Year Built: 1942, Status: Open, Structure Length: 2.41m (7.91ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: SHEEPSHEAD BAY RD
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 13.339, Lanes on structure: 6, Lanes under structure: 2, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 21.0m (68.9ft), Skew: 23 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 23.1m (75.8ft), Curb-To-Curb Width: 20.9m (68.6ft), Out-to-Out Width: 26.2m (86.0ft)
Condition: Deck: Poor, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 70.8 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 42.6 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: Meets minimum limits, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.40m (7.87ft), Designated Inspection Frequency: Every 24 months, Inspection Date: March 2020, Bridge Improvement Cost: $5,442,000, Roadway Improvement Cost: $3,187,000, Total Project Cost: $8,629,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Structure Number: 2231409, Location: .8MI E BELT PKY+OCEAN PKY (Lat: 40.584689, Lng: -73.951094), Route carried "on" structure: Interstate 907C, Year Built: 1942, Status: Open, Structure Length: 2.41m (7.91ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: SHEEPSHEAD BAY RD
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 13.339, Lanes on structure: 6, Lanes under structure: 2, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 21.0m (68.9ft), Skew: 23 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 23.1m (75.8ft), Curb-To-Curb Width: 20.9m (68.6ft), Out-to-Out Width: 26.2m (86.0ft)
Condition: Deck: Poor, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 70.8 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 42.6 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: Meets minimum limits, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.40m (7.87ft), Designated Inspection Frequency: Every 24 months, Inspection Date: March 2020, Bridge Improvement Cost: $5,442,000, Roadway Improvement Cost: $3,187,000, Total Project Cost: $8,629,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >> Show street view
Structure Number: 2231419, Location: .9 MI E BELT PKY &OCN PKY (Lat: 40.584539, Lng: -73.948606), Route carried "on" structure: City street 907C, Year Built: 1942, Year Reconstructed: 2010, Status: Open, Structure Length: 5.06m (16.60ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: OCEAN AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 13.532, Lanes on structure: 6, Lanes under structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.8m (78.1ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 21.3m (69.9ft), Curb or Sidewalk Widths: Left: 0.5m (1.6ft), Right: 0.5m (1.6ft), Curb-To-Curb Width: 23.8m (78.1ft), Out-to-Out Width: 25.7m (84.3ft)
Condition: Deck: Poor, Superstructure: Satisfactory, Substructure: Satisfactory, Operating Rating: 41.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 24.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 5.05m (16.57ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: March 2020, Critical Feature Inspection Date: March 2020, Bridge Improvement Cost: $6,483,000, Roadway Improvement Cost: $3,796,000, Total Project Cost: $10,279,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Structure Number: 2231419, Location: .9 MI E BELT PKY &OCN PKY (Lat: 40.584539, Lng: -73.948606), Route carried "on" structure: City street 907C, Year Built: 1942, Year Reconstructed: 2010, Status: Open, Structure Length: 5.06m (16.60ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: OCEAN AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 13.532, Lanes on structure: 6, Lanes under structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.8m (78.1ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 21.3m (69.9ft), Curb or Sidewalk Widths: Left: 0.5m (1.6ft), Right: 0.5m (1.6ft), Curb-To-Curb Width: 23.8m (78.1ft), Out-to-Out Width: 25.7m (84.3ft)
Condition: Deck: Poor, Superstructure: Satisfactory, Substructure: Satisfactory, Operating Rating: 41.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 24.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 5.05m (16.57ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: March 2020, Critical Feature Inspection Date: March 2020, Bridge Improvement Cost: $6,483,000, Roadway Improvement Cost: $3,796,000, Total Project Cost: $10,279,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >> Show street view
Structure Number: 2231429, Location: IN SHEEPSHEAD BAY (Lat: 40.584928, Lng: -73.943789), Route carried "on" structure: City street 907C, Year Built: 1942, Status: Open, Structure Length: 4.36m (14.30ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: BEDFORD AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 13.934, Lanes on structure: 6, Lanes under structure: 4, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.8m (78.1ft), Skew: 30 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 16.1m (52.8ft), Curb or Sidewalk Widths: Left: 0.8m (2.6ft), Right: 0.7m (2.3ft), Curb-To-Curb Width: 23.8m (78.1ft), Out-to-Out Width: 25.5m (83.7ft)
Condition: Deck: Fair, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 42.6 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 25.4 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.35m (14.27ft), Designated Inspection Frequency: Every 24 months, Inspection Date: March 2020, Bridge Improvement Cost: $7,748,000, Roadway Improvement Cost: $4,537,000, Total Project Cost: $12,285,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Structure Number: 2231429, Location: IN SHEEPSHEAD BAY (Lat: 40.584928, Lng: -73.943789), Route carried "on" structure: City street 907C, Year Built: 1942, Status: Open, Structure Length: 4.36m (14.30ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: BEDFORD AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 13.934, Lanes on structure: 6, Lanes under structure: 4, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.8m (78.1ft), Skew: 30 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 16.1m (52.8ft), Curb or Sidewalk Widths: Left: 0.8m (2.6ft), Right: 0.7m (2.3ft), Curb-To-Curb Width: 23.8m (78.1ft), Out-to-Out Width: 25.5m (83.7ft)
Condition: Deck: Fair, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 42.6 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 25.4 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.35m (14.27ft), Designated Inspection Frequency: Every 24 months, Inspection Date: March 2020, Bridge Improvement Cost: $7,748,000, Roadway Improvement Cost: $4,537,000, Total Project Cost: $12,285,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >> Show street view
Structure Number: 2231439, Location: 1.5MI E BELT PKY+OCEAN PY (Lat: 40.585617, Lng: -73.939147), Route carried "on" structure: City street 907C, Year Built: 1942, Status: Open, Structure Length: 4.36m (14.30ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: NOSTRAND AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 14.336, Lanes on structure: 6, Lanes under structure: 4, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.8m (78.1ft), Skew: 30 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 16.1m (52.8ft), Curb or Sidewalk Widths: Left: 0.6m (2.0ft), Right: 0.6m (2.0ft), Curb-To-Curb Width: 20.7m (67.9ft), Out-to-Out Width: 23.8m (78.1ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Fair, Operating Rating: 39.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 23.6 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.35m (14.27ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: May 2020, Critical Feature Inspection Date: May 2020, Bridge Improvement Cost: $5,668,000, Roadway Improvement Cost: $3,319,000, Total Project Cost: $8,987,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Structure Number: 2231439, Location: 1.5MI E BELT PKY+OCEAN PY (Lat: 40.585617, Lng: -73.939147), Route carried "on" structure: City street 907C, Year Built: 1942, Status: Open, Structure Length: 4.36m (14.30ft), Average Daily Traffic: 115,587 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 142,518 (year 2040), Design Load: H 20, Features Intersected: NOSTRAND AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 14.336, Lanes on structure: 6, Lanes under structure: 4, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 23.8m (78.1ft), Skew: 30 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 16.1m (52.8ft), Curb or Sidewalk Widths: Left: 0.6m (2.0ft), Right: 0.6m (2.0ft), Curb-To-Curb Width: 20.7m (67.9ft), Out-to-Out Width: 23.8m (78.1ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Fair, Operating Rating: 39.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 23.6 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.35m (14.27ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: May 2020, Critical Feature Inspection Date: May 2020, Bridge Improvement Cost: $5,668,000, Roadway Improvement Cost: $3,319,000, Total Project Cost: $8,987,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >> Show street view
Structure Number: 2231449, Location: 1.9MI E BELT PKY+OCEAN PY (Lat: 40.585650, Lng: -73.931242), Route carried "on" structure: Business City street , Year Built: 1942, Year Reconstructed: 1978, Status: Open, Structure Length: 3.20m (10.50ft), Average Daily Traffic: 12,728 (year 2019), Truck Traffic: 5%, Average Future Daily Traffic: 12,787 (year 2040), Design Load: H 20, Features Intersected: RTE 907C, 907C907CX2M140, Facility Carried by Structure: KNAPP STREET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.161, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 18.3m (60.0ft), Skew: 23 degrees, Material/Design: Steel, Design/Construction: Girder and Floorbeam System, Number Of Spans In Main Unit: 1, Length of Maximum Span: 31.0m (101.7ft), Curb or Sidewalk Widths: Left: 3.3m (10.8ft), Right: 3.3m (10.8ft), Curb-To-Curb Width: 18.3m (60.0ft), Out-to-Out Width: 27.3m (89.6ft)
Condition: Deck: Good, Superstructure: Satisfactory, Substructure: Good, Operating Rating: 74.7 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 27.0 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Somewhat better than minimum adequacy, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 3.20m (10.50ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: March 2020, Critical Feature Inspection Date: March 2020, Bridge Improvement Cost: $6,567,000, Roadway Improvement Cost: $3,846,000, Total Project Cost: $10,413,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Structure Number: 2231449, Location: 1.9MI E BELT PKY+OCEAN PY (Lat: 40.585650, Lng: -73.931242), Route carried "on" structure: Business City street , Year Built: 1942, Year Reconstructed: 1978, Status: Open, Structure Length: 3.20m (10.50ft), Average Daily Traffic: 12,728 (year 2019), Truck Traffic: 5%, Average Future Daily Traffic: 12,787 (year 2040), Design Load: H 20, Features Intersected: RTE 907C, 907C907CX2M140, Facility Carried by Structure: KNAPP STREET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.161, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 18.3m (60.0ft), Skew: 23 degrees, Material/Design: Steel, Design/Construction: Girder and Floorbeam System, Number Of Spans In Main Unit: 1, Length of Maximum Span: 31.0m (101.7ft), Curb or Sidewalk Widths: Left: 3.3m (10.8ft), Right: 3.3m (10.8ft), Curb-To-Curb Width: 18.3m (60.0ft), Out-to-Out Width: 27.3m (89.6ft)
Condition: Deck: Good, Superstructure: Satisfactory, Substructure: Good, Operating Rating: 74.7 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 27.0 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Somewhat better than minimum adequacy, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 3.20m (10.50ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: March 2020, Critical Feature Inspection Date: March 2020, Bridge Improvement Cost: $6,567,000, Roadway Improvement Cost: $3,846,000, Total Project Cost: $10,413,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >> Show street view
Structure Number: 223145, Location: 2.9MI E BELT PKY+OCEAN PY (Lat: 40.586244, Lng: -73.911742), Route carried "on" structure: City street 907C, Year Built: 2017, Status: Open, Structure Length: 15.12m (49.61ft), Average Daily Traffic: 125,219 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 154,395 (year 2040), Design Load: HS 20, Features Intersected: GERRITSEN INLET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 16.669, Lanes on structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 31.4m (103.0ft), Skew: 20 degrees, Navigation Control: Yes ( Vertical Clearance: 999.9m (3,280.5ft), Horizontal Clearance: 34.4m (112.9ft)), Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 59.7m (195.9ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.7m (12.1ft), Curb-To-Curb Width: 31.4m (103.0ft), Out-to-Out Width: 36.9m (121.1ft)
Condition: Deck: Very good, Superstructure: Excellent, Substructure: Excellent, Channel: Good, Operating Rating: 89.8 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 53.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Superior to present desirable criteria, Waterway Adequacy: Superior to present desirable criteria, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 15.11m (49.57ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: August 2020, Underwater Inspection Date: August 2020, Bridge Improvement Cost: $25,556,000, Roadway Improvement Cost: $14,965,000, Total Project Cost: $40,521,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Galvanized Reinforcing
Structure Number: 223145, Location: 2.9MI E BELT PKY+OCEAN PY (Lat: 40.586244, Lng: -73.911742), Route carried "on" structure: City street 907C, Year Built: 2017, Status: Open, Structure Length: 15.12m (49.61ft), Average Daily Traffic: 125,219 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 154,395 (year 2040), Design Load: HS 20, Features Intersected: GERRITSEN INLET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 16.669, Lanes on structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 31.4m (103.0ft), Skew: 20 degrees, Navigation Control: Yes ( Vertical Clearance: 999.9m (3,280.5ft), Horizontal Clearance: 34.4m (112.9ft)), Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 59.7m (195.9ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.7m (12.1ft), Curb-To-Curb Width: 31.4m (103.0ft), Out-to-Out Width: 36.9m (121.1ft)
Condition: Deck: Very good, Superstructure: Excellent, Substructure: Excellent, Channel: Good, Operating Rating: 89.8 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 53.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Superior to present desirable criteria, Waterway Adequacy: Superior to present desirable criteria, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 15.11m (49.57ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: August 2020, Underwater Inspection Date: August 2020, Bridge Improvement Cost: $25,556,000, Roadway Improvement Cost: $14,965,000, Total Project Cost: $40,521,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Galvanized Reinforcing
Find on map >> Show street view
Structure Number: 223146, Location: 8.4 MI SW I678+BELT PKWY (Lat: 40.596514, Lng: -73.907964), Route carried "on" structure: City street , Year Built: 1941, Year Reconstructed: 2001, Status: Open, Structure Length: 4.33m (14.21ft), Average Daily Traffic: 35,417 (year 2020), Truck Traffic: 2%, Average Future Daily Traffic: 35,583 (year 2040), Design Load: HS 25 or greater, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: FLATBUSH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 2.301, Lanes on structure: 6, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 21.9m (71.9ft), Skew: 32 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 21.0m (68.9ft), Curb or Sidewalk Widths: Left: 3.1m (10.2ft), Right: 3.1m (10.2ft), Curb-To-Curb Width: 21.9m (71.9ft), Out-to-Out Width: 30.2m (99.1ft)
Condition: Deck: Satisfactory, Superstructure: Good, Substructure: Good, Operating Rating: 90.7 metric tons, Method Used To Determine Operating Rating: Allowable Stress (AS), Inventory Rating: 45.4 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.32m (14.17ft), Designated Inspection Frequency: Every 24 months, Inspection Date: November 2021, Bridge Improvement Cost: $8,736,000, Roadway Improvement Cost: $5,116,000, Total Project Cost: $13,852,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 223146, Location: 8.4 MI SW I678+BELT PKWY (Lat: 40.596514, Lng: -73.907964), Route carried "on" structure: City street , Year Built: 1941, Year Reconstructed: 2001, Status: Open, Structure Length: 4.33m (14.21ft), Average Daily Traffic: 35,417 (year 2020), Truck Traffic: 2%, Average Future Daily Traffic: 35,583 (year 2040), Design Load: HS 25 or greater, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: FLATBUSH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 2.301, Lanes on structure: 6, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 21.9m (71.9ft), Skew: 32 degrees, Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 21.0m (68.9ft), Curb or Sidewalk Widths: Left: 3.1m (10.2ft), Right: 3.1m (10.2ft), Curb-To-Curb Width: 21.9m (71.9ft), Out-to-Out Width: 30.2m (99.1ft)
Condition: Deck: Satisfactory, Superstructure: Good, Substructure: Good, Operating Rating: 90.7 metric tons, Method Used To Determine Operating Rating: Allowable Stress (AS), Inventory Rating: 45.4 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.32m (14.17ft), Designated Inspection Frequency: Every 24 months, Inspection Date: November 2021, Bridge Improvement Cost: $8,736,000, Roadway Improvement Cost: $5,116,000, Total Project Cost: $13,852,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231471, Location: 7.7 MI SW I678+BELT PKWY (Lat: 40.604597, Lng: -73.899022), Route carried "on" structure: City street 907, Year Built: 2017, Status: Open, Structure Length: 80.86m (265.29ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HL 93, Features Intersected: Mill Basin
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 19.115, Lanes on structure: 3, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 15.5m (50.9ft), Navigation Control: Yes ( Vertical Clearance: 999.9m (3,280.5ft), Horizontal Clearance: 50.0m (164.0ft)), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 17, Length of Maximum Span: 71.3m (233.9ft), Curb-To-Curb Width: 15.5m (50.9ft), Out-to-Out Width: 16.5m (54.1ft)
Condition: Deck: Excellent, Superstructure: Excellent, Substructure: Excellent, Channel: Very good, Operating Rating: 99.8 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 40.8 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Somewhat better than minimum adequacy, Waterway Adequacy: Superior to present desirable criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 80.86m (265.29ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: March 2020, Underwater Inspection Date: May 2021, Bridge Improvement Cost: $57,549,000, Roadway Improvement Cost: $33,701,000, Total Project Cost: $91,250,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231471, Location: 7.7 MI SW I678+BELT PKWY (Lat: 40.604597, Lng: -73.899022), Route carried "on" structure: City street 907, Year Built: 2017, Status: Open, Structure Length: 80.86m (265.29ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HL 93, Features Intersected: Mill Basin
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 19.115, Lanes on structure: 3, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 15.5m (50.9ft), Navigation Control: Yes ( Vertical Clearance: 999.9m (3,280.5ft), Horizontal Clearance: 50.0m (164.0ft)), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 17, Length of Maximum Span: 71.3m (233.9ft), Curb-To-Curb Width: 15.5m (50.9ft), Out-to-Out Width: 16.5m (54.1ft)
Condition: Deck: Excellent, Superstructure: Excellent, Substructure: Excellent, Channel: Very good, Operating Rating: 99.8 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 40.8 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Somewhat better than minimum adequacy, Waterway Adequacy: Superior to present desirable criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 80.86m (265.29ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: March 2020, Underwater Inspection Date: May 2021, Bridge Improvement Cost: $57,549,000, Roadway Improvement Cost: $33,701,000, Total Project Cost: $91,250,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231472, Location: 7.7 MI SW I678+BELT PKWY (Lat: 40.604619, Lng: -73.898378), Route carried "on" structure: State highway 907, Year Built: 2019, Status: Open, Structure Length: 80.86m (265.29ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HL 93, Features Intersected: Mill Basin
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 19.244, Lanes on structure: 3, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 18.0m (59.1ft), Navigation Control: Yes ( Vertical Clearance: 18.9m (62.0ft), Horizontal Clearance: 39.9m (130.9ft)), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 17, Length of Maximum Span: 71.3m (233.9ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 4.3m (14.1ft), Curb-To-Curb Width: 18.0m (59.1ft), Out-to-Out Width: 22.0m (72.2ft)
Condition: Deck: Very good, Superstructure: Excellent, Substructure: Very good, Channel: Very good, Operating Rating: 99.3 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 40.8 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Equal to present desirable criteria, Deck Geometry: Better than present minimum criteria, Waterway Adequacy: Superior to present desirable criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 80.86m (265.29ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: July 2021, Underwater Inspection Date: May 2021, Bridge Improvement Cost: $77,175,000, Roadway Improvement Cost: $45,194,000, Total Project Cost: $122,369,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231472, Location: 7.7 MI SW I678+BELT PKWY (Lat: 40.604619, Lng: -73.898378), Route carried "on" structure: State highway 907, Year Built: 2019, Status: Open, Structure Length: 80.86m (265.29ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HL 93, Features Intersected: Mill Basin
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 19.244, Lanes on structure: 3, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 18.0m (59.1ft), Navigation Control: Yes ( Vertical Clearance: 18.9m (62.0ft), Horizontal Clearance: 39.9m (130.9ft)), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 17, Length of Maximum Span: 71.3m (233.9ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 4.3m (14.1ft), Curb-To-Curb Width: 18.0m (59.1ft), Out-to-Out Width: 22.0m (72.2ft)
Condition: Deck: Very good, Superstructure: Excellent, Substructure: Very good, Channel: Very good, Operating Rating: 99.3 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 40.8 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Equal to present desirable criteria, Deck Geometry: Better than present minimum criteria, Waterway Adequacy: Superior to present desirable criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 80.86m (265.29ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: July 2021, Underwater Inspection Date: May 2021, Bridge Improvement Cost: $77,175,000, Roadway Improvement Cost: $45,194,000, Total Project Cost: $122,369,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231481, Location: 907C Over Paerdegat Basin (Lat: 40.621564, Lng: -73.897428), Route carried "on" structure: State highway 907, Year Built: 2013, Status: Open, Structure Length: 25.15m (82.51ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HS 25 or greater, Features Intersected: Paedergat Basin
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 21.046, Lanes on structure: 3, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 17.7m (58.1ft), Navigation Control: Yes ( Vertical Clearance: 999.9m (3,280.5ft), Horizontal Clearance: 8.8m (28.9ft)), Material/Design: Steel, Design/Construction: Box Beam or Girders - Single/Spread, Number Of Spans In Main Unit: 3, Length of Maximum Span: 95.0m (311.7ft), Curb-To-Curb Width: 17.6m (57.7ft), Out-to-Out Width: 18.6m (61.0ft)
Condition: Deck: Very good, Superstructure: Very good, Substructure: Very good, Inventory Rating: 98.9 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Equal to present desirable criteria, Deck Geometry: Better than present minimum criteria, Waterway Adequacy: Equal to present desirable criteria, Approach Roadway Alignment: Superior to present desirable criteria, Length Of Structure Improvement: 25.14m (82.48ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: September 2021, Critical Feature Inspection Date: September 2021, Underwater Inspection Date: July 2019, Bridge Improvement Cost: $18,872,000, Roadway Improvement Cost: $11,051,000, Total Project Cost: $29,923,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete, Deck Protection: Galvanized Reinforcing
Structure Number: 2231481, Location: 907C Over Paerdegat Basin (Lat: 40.621564, Lng: -73.897428), Route carried "on" structure: State highway 907, Year Built: 2013, Status: Open, Structure Length: 25.15m (82.51ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HS 25 or greater, Features Intersected: Paedergat Basin
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 21.046, Lanes on structure: 3, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 17.7m (58.1ft), Navigation Control: Yes ( Vertical Clearance: 999.9m (3,280.5ft), Horizontal Clearance: 8.8m (28.9ft)), Material/Design: Steel, Design/Construction: Box Beam or Girders - Single/Spread, Number Of Spans In Main Unit: 3, Length of Maximum Span: 95.0m (311.7ft), Curb-To-Curb Width: 17.6m (57.7ft), Out-to-Out Width: 18.6m (61.0ft)
Condition: Deck: Very good, Superstructure: Very good, Substructure: Very good, Inventory Rating: 98.9 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Equal to present desirable criteria, Deck Geometry: Better than present minimum criteria, Waterway Adequacy: Equal to present desirable criteria, Approach Roadway Alignment: Superior to present desirable criteria, Length Of Structure Improvement: 25.14m (82.48ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: September 2021, Critical Feature Inspection Date: September 2021, Underwater Inspection Date: July 2019, Bridge Improvement Cost: $18,872,000, Roadway Improvement Cost: $11,051,000, Total Project Cost: $29,923,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete, Deck Protection: Galvanized Reinforcing
Find on map >> Show street view
Structure Number: 2231482, Location: 907C Over Paedergat Basin (Lat: 40.621356, Lng: -73.896664), Route carried "on" structure: State highway 907C, Year Built: 2013, Status: Open, Structure Length: 37.28m (122.31ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HS 25 or greater, Features Intersected: Paedergat Basin
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 21.046, Lanes on structure: 3, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 15.5m (50.9ft), Navigation Control: Yes ( Vertical Clearance: 9.0m (29.5ft), Horizontal Clearance: 18.6m (61.0ft)), Material/Design: Steel, Design/Construction: Box Beam or Girders - Single/Spread, Number Of Spans In Main Unit: 5, Length of Maximum Span: 90.0m (295.3ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.6m (11.8ft), Curb-To-Curb Width: 15.6m (51.2ft), Out-to-Out Width: 20.5m (67.3ft)
Condition: Deck: Excellent, Superstructure: Excellent, Substructure: Excellent, Channel: Good, Inventory Rating: 92.5 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Somewhat better than minimum adequacy, Waterway Adequacy: Equal to present desirable criteria, Approach Roadway Alignment: Superior to present desirable criteria, Length Of Structure Improvement: 37.27m (122.28ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: November 2020, Critical Feature Inspection Date: November 2020, Underwater Inspection Date: July 2019, Bridge Improvement Cost: $29,708,000, Roadway Improvement Cost: $17,397,000, Total Project Cost: $47,105,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Galvanized Reinforcing
Structure Number: 2231482, Location: 907C Over Paedergat Basin (Lat: 40.621356, Lng: -73.896664), Route carried "on" structure: State highway 907C, Year Built: 2013, Status: Open, Structure Length: 37.28m (122.31ft), Average Daily Traffic: 63,278 (year 2019), Truck Traffic: 1%, Average Future Daily Traffic: 78,021 (year 2040), Design Load: HS 25 or greater, Features Intersected: Paedergat Basin
Minimum Vertical Clearance: 32.69m (107.25ft), Kilometerpoint: 21.046, Lanes on structure: 3, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 15.5m (50.9ft), Navigation Control: Yes ( Vertical Clearance: 9.0m (29.5ft), Horizontal Clearance: 18.6m (61.0ft)), Material/Design: Steel, Design/Construction: Box Beam or Girders - Single/Spread, Number Of Spans In Main Unit: 5, Length of Maximum Span: 90.0m (295.3ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.6m (11.8ft), Curb-To-Curb Width: 15.6m (51.2ft), Out-to-Out Width: 20.5m (67.3ft)
Condition: Deck: Excellent, Superstructure: Excellent, Substructure: Excellent, Channel: Good, Inventory Rating: 92.5 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Somewhat better than minimum adequacy, Waterway Adequacy: Equal to present desirable criteria, Approach Roadway Alignment: Superior to present desirable criteria, Length Of Structure Improvement: 37.27m (122.28ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: November 2020, Critical Feature Inspection Date: November 2020, Underwater Inspection Date: July 2019, Bridge Improvement Cost: $29,708,000, Roadway Improvement Cost: $17,397,000, Total Project Cost: $47,105,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Galvanized Reinforcing
Find on map >> Show street view
Structure Number: 2231499, Location: 5.6 MI SW I678+BELT PKWY (Lat: 40.630475, Lng: -73.886072), Route carried "on" structure: City street 907C, Year Built: 2012, Status: Open, Structure Length: 2.93m (9.61ft), Average Daily Traffic: 129,775 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 160,012 (year 2040), Design Load: H 20, Features Intersected: ROCKAWAY PARKWAY
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 22.510, Lanes on structure: 6, Lanes under structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 30.2m (99.1ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 28.0m (91.9ft), Curb-To-Curb Width: 31.9m (104.7ft), Out-to-Out Width: 32.9m (107.9ft)
Condition: Deck: Excellent, Superstructure: Excellent, Substructure: Excellent, Inventory Rating: 70.8 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Superior to present desirable criteria, Underclear: Meets minimum limits, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.92m (9.58ft), Designated Inspection Frequency: Every 24 months, Inspection Date: September 2020, Bridge Improvement Cost: $7,212,000, Roadway Improvement Cost: $4,223,000, Total Project Cost: $11,435,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231499, Location: 5.6 MI SW I678+BELT PKWY (Lat: 40.630475, Lng: -73.886072), Route carried "on" structure: City street 907C, Year Built: 2012, Status: Open, Structure Length: 2.93m (9.61ft), Average Daily Traffic: 129,775 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 160,012 (year 2040), Design Load: H 20, Features Intersected: ROCKAWAY PARKWAY
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 22.510, Lanes on structure: 6, Lanes under structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 30.2m (99.1ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 28.0m (91.9ft), Curb-To-Curb Width: 31.9m (104.7ft), Out-to-Out Width: 32.9m (107.9ft)
Condition: Deck: Excellent, Superstructure: Excellent, Substructure: Excellent, Inventory Rating: 70.8 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Superior to present desirable criteria, Deck Geometry: Superior to present desirable criteria, Underclear: Meets minimum limits, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.92m (9.58ft), Designated Inspection Frequency: Every 24 months, Inspection Date: September 2020, Bridge Improvement Cost: $7,212,000, Roadway Improvement Cost: $4,223,000, Total Project Cost: $11,435,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231509, Location: 5.0 MI SW I678+BELT PKWY (Lat: 40.638386, Lng: -73.878739), Route carried "on" structure: City street 907C, Year Built: 2013, Status: Open, Structure Length: 9.66m (31.69ft), Average Daily Traffic: 129,775 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 160,012 (year 2040), Design Load: HS 25 or greater, Features Intersected: FRESH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 23.604, Lanes on structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 32.6m (107.0ft), Skew: 22 degrees, Navigation Control: Yes ( Vertical Clearance: 6.4m (21.0ft), Horizontal Clearance: 6.5m (21.3ft)), Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 33.6m (110.2ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.8m (12.5ft), Curb-To-Curb Width: 32.5m (106.6ft), Out-to-Out Width: 38.6m (126.6ft)
Condition: Deck: Satisfactory, Superstructure: Very good, Substructure: Good, Channel: Very good, Operating Rating: 81.0 metric tons, Method Used To Determine Operating Rating: Allowable Stress (AS), Inventory Rating: 42.0 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Superior to present desirable criteria, Waterway Adequacy: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 9.66m (31.69ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: November 2021, Underwater Inspection Date: August 2019, Bridge Improvement Cost: $19,628,000, Roadway Improvement Cost: $11,494,000, Total Project Cost: $31,121,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231509, Location: 5.0 MI SW I678+BELT PKWY (Lat: 40.638386, Lng: -73.878739), Route carried "on" structure: City street 907C, Year Built: 2013, Status: Open, Structure Length: 9.66m (31.69ft), Average Daily Traffic: 129,775 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 160,012 (year 2040), Design Load: HS 25 or greater, Features Intersected: FRESH CREEK
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 23.604, Lanes on structure: 6, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 32.6m (107.0ft), Skew: 22 degrees, Navigation Control: Yes ( Vertical Clearance: 6.4m (21.0ft), Horizontal Clearance: 6.5m (21.3ft)), Material/Design: Steel continuous, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 3, Length of Maximum Span: 33.6m (110.2ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 3.8m (12.5ft), Curb-To-Curb Width: 32.5m (106.6ft), Out-to-Out Width: 38.6m (126.6ft)
Condition: Deck: Satisfactory, Superstructure: Very good, Substructure: Good, Channel: Very good, Operating Rating: 81.0 metric tons, Method Used To Determine Operating Rating: Allowable Stress (AS), Inventory Rating: 42.0 metric tons, Method Used To Determine Inventory Rating: Allowable Stress (AS), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Superior to present desirable criteria, Waterway Adequacy: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 9.66m (31.69ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: November 2021, Underwater Inspection Date: August 2019, Bridge Improvement Cost: $19,628,000, Roadway Improvement Cost: $11,494,000, Total Project Cost: $31,121,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231519, Location: 4.4 MILE SW I678&BELTPKWY (Lat: 40.643281, Lng: -73.876256), Route carried "on" structure: City street , Year Built: 1941, Year Reconstructed: 1991, Status: Open, Structure Length: 3.08m (10.10ft), Average Daily Traffic: 14,677 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 14,745 (year 2040), Design Load: HS 20, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: PENNSYLVANIA AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 13.4m (44.0ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 15.2m (49.9ft), Curb or Sidewalk Widths: Left: 2.4m (7.9ft), Right: 2.4m (7.9ft), Curb-To-Curb Width: 13.4m (44.0ft), Out-to-Out Width: 20.0m (65.6ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Good, Operating Rating: 61.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 34.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 3.07m (10.07ft), Designated Inspection Frequency: Every 24 months, Inspection Date: June 2021, Bridge Improvement Cost: $4,311,000, Roadway Improvement Cost: $2,524,000, Total Project Cost: $6,835,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231519, Location: 4.4 MILE SW I678&BELTPKWY (Lat: 40.643281, Lng: -73.876256), Route carried "on" structure: City street , Year Built: 1941, Year Reconstructed: 1991, Status: Open, Structure Length: 3.08m (10.10ft), Average Daily Traffic: 14,677 (year 2020), Truck Traffic: 1%, Average Future Daily Traffic: 14,745 (year 2040), Design Load: HS 20, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: PENNSYLVANIA AVE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 13.4m (44.0ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 15.2m (49.9ft), Curb or Sidewalk Widths: Left: 2.4m (7.9ft), Right: 2.4m (7.9ft), Curb-To-Curb Width: 13.4m (44.0ft), Out-to-Out Width: 20.0m (65.6ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Good, Operating Rating: 61.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 34.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present minimum criteria, Length Of Structure Improvement: 3.07m (10.07ft), Designated Inspection Frequency: Every 24 months, Inspection Date: June 2021, Bridge Improvement Cost: $4,311,000, Roadway Improvement Cost: $2,524,000, Total Project Cost: $6,835,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231529, Location: 907CX HENDRIX AVE (Lat: 40.646497, Lng: -73.873869), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1987, Status: Open, Structure Length: 9.27m (30.41ft), Average Daily Traffic: 130,098 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 160,410 (year 2040), Features Intersected: HENDRIX CREEK, SVE RD TO
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 24.569, Lanes on structure: 6, Lanes under structure: 1, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 23.2m (76.1ft), Skew: 22 degrees, Navigation Control: Yes ( Vertical Clearance: 14.3m (46.9ft), Horizontal Clearance: 6.0m (19.7ft)), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 7, Length of Maximum Span: 16.7m (54.8ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 2.1m (6.9ft), Curb-To-Curb Width: 22.6m (74.1ft), Out-to-Out Width: 26.7m (87.6ft)
Condition: Deck: Satisfactory, Superstructure: Satisfactory, Substructure: Fair, Channel: Satisfactory, Operating Rating: 53.5 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 32.7 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Waterway Adequacy: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 9.26m (30.38ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: August 2021, Underwater Inspection Date: June 2018, Bridge Improvement Cost: $11,243,000, Roadway Improvement Cost: $6,584,000, Total Project Cost: $17,826,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231529, Location: 907CX HENDRIX AVE (Lat: 40.646497, Lng: -73.873869), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1987, Status: Open, Structure Length: 9.27m (30.41ft), Average Daily Traffic: 130,098 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 160,410 (year 2040), Features Intersected: HENDRIX CREEK, SVE RD TO
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 24.569, Lanes on structure: 6, Lanes under structure: 1, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 23.2m (76.1ft), Skew: 22 degrees, Navigation Control: Yes ( Vertical Clearance: 14.3m (46.9ft), Horizontal Clearance: 6.0m (19.7ft)), Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 7, Length of Maximum Span: 16.7m (54.8ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 2.1m (6.9ft), Curb-To-Curb Width: 22.6m (74.1ft), Out-to-Out Width: 26.7m (87.6ft)
Condition: Deck: Satisfactory, Superstructure: Satisfactory, Substructure: Fair, Channel: Satisfactory, Operating Rating: 53.5 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 32.7 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Waterway Adequacy: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 9.26m (30.38ft), Designated Inspection Frequency: Every 24 months, Underwater Inspection Frequency: Every 60 months, Inspection Date: August 2021, Underwater Inspection Date: June 2018, Bridge Improvement Cost: $11,243,000, Roadway Improvement Cost: $6,584,000, Total Project Cost: $17,826,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231539, Location: 907CX SHERIDAN AVE (Lat: 40.654797, Lng: -73.860269), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1987, Status: Open, Structure Length: 10.27m (33.69ft), Average Daily Traffic: 116,607 (year 2018), Truck Traffic: 2%, Average Future Daily Traffic: 143,776 (year 2040), Features Intersected: FOUNTAIN AVE, BETTS CREE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.032, Lanes on structure: 6, Lanes under structure: 2, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 21.3m (69.9ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 6, Length of Maximum Span: 22.2m (72.8ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 2.2m (7.2ft), Curb-To-Curb Width: 22.6m (74.1ft), Out-to-Out Width: 26.7m (87.6ft)
Condition: Deck: Good, Superstructure: Satisfactory, Substructure: Satisfactory, Channel: Good, Operating Rating: 80.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 48.1 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Waterway Adequacy: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 10.27m (33.69ft), Designated Inspection Frequency: Every 24 months, Inspection Date: November 2020, Bridge Improvement Cost: $13,654,000, Roadway Improvement Cost: $7,996,000, Total Project Cost: $21,649,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231539, Location: 907CX SHERIDAN AVE (Lat: 40.654797, Lng: -73.860269), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1987, Status: Open, Structure Length: 10.27m (33.69ft), Average Daily Traffic: 116,607 (year 2018), Truck Traffic: 2%, Average Future Daily Traffic: 143,776 (year 2040), Features Intersected: FOUNTAIN AVE, BETTS CREE
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.032, Lanes on structure: 6, Lanes under structure: 2, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 21.3m (69.9ft), Skew: 20 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 6, Length of Maximum Span: 22.2m (72.8ft), Curb or Sidewalk Widths: Left: 0.0m, Right: 2.2m (7.2ft), Curb-To-Curb Width: 22.6m (74.1ft), Out-to-Out Width: 26.7m (87.6ft)
Condition: Deck: Good, Superstructure: Satisfactory, Substructure: Satisfactory, Channel: Good, Operating Rating: 80.7 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 48.1 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Waterway Adequacy: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 10.27m (33.69ft), Designated Inspection Frequency: Every 24 months, Inspection Date: November 2020, Bridge Improvement Cost: $13,654,000, Roadway Improvement Cost: $7,996,000, Total Project Cost: $21,649,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231549, Location: 2.6 MI W I678+BELT PKWY (Lat: 40.662461, Lng: -73.849514), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1985, Status: Open, Structure Length: 4.66m (15.29ft), Average Daily Traffic: 116,607 (year 2018), Truck Traffic: 2%, Average Future Daily Traffic: 143,776 (year 2040), Design Load: H 20, Features Intersected: 84TH STREET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 1.271, Lanes on structure: 6, Lanes under structure: 3, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 23.2m (76.1ft), Skew: 22 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 22.8m (74.8ft), Curb-To-Curb Width: 22.4m (73.5ft), Out-to-Out Width: 24.1m (79.1ft)
Condition: Deck: Satisfactory, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 98.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 58.1 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.66m (15.29ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: June 2021, Critical Feature Inspection Date: June 2021, Bridge Improvement Cost: $6,689,000, Roadway Improvement Cost: $3,917,000, Total Project Cost: $10,606,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231549, Location: 2.6 MI W I678+BELT PKWY (Lat: 40.662461, Lng: -73.849514), Route carried "on" structure: City street 907C, Year Built: 1941, Year Reconstructed: 1985, Status: Open, Structure Length: 4.66m (15.29ft), Average Daily Traffic: 116,607 (year 2018), Truck Traffic: 2%, Average Future Daily Traffic: 143,776 (year 2040), Design Load: H 20, Features Intersected: 84TH STREET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 1.271, Lanes on structure: 6, Lanes under structure: 3, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 23.2m (76.1ft), Skew: 22 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 22.8m (74.8ft), Curb-To-Curb Width: 22.4m (73.5ft), Out-to-Out Width: 24.1m (79.1ft)
Condition: Deck: Satisfactory, Superstructure: Satisfactory, Substructure: Fair, Operating Rating: 98.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 58.1 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.66m (15.29ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: June 2021, Critical Feature Inspection Date: June 2021, Bridge Improvement Cost: $6,689,000, Roadway Improvement Cost: $3,917,000, Total Project Cost: $10,606,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231559, Location: 2.1 MI W I678 & BELT PKWY (Lat: 40.666042, Lng: -73.841467), Route carried "on" structure: Other road , Year Built: 1941, Year Reconstructed: 1983, Status: Open, Structure Length: 5.43m (17.81ft), Average Daily Traffic: 45,738 (year 2018), Truck Traffic: 5%, Average Future Daily Traffic: 45,952 (year 2040), Design Load: H 20, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: CROSS BAY BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 8.093, Lanes on structure: 8, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 30.5m (100.1ft), Skew: 21 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 16.5m (54.1ft), Curb or Sidewalk Widths: Left: 3.1m (10.2ft), Right: 3.1m (10.2ft), Curb-To-Curb Width: 29.3m (96.1ft), Out-to-Out Width: 40.4m (132.5ft)
Condition: Deck: Good, Superstructure: Satisfactory, Substructure: Good, Operating Rating: 97.1 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 58.1 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 5.42m (17.78ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: May 2020, Critical Feature Inspection Date: May 2020, Bridge Improvement Cost: $13,470,000, Roadway Improvement Cost: $7,888,000, Total Project Cost: $21,359,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Latex Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231559, Location: 2.1 MI W I678 & BELT PKWY (Lat: 40.666042, Lng: -73.841467), Route carried "on" structure: Other road , Year Built: 1941, Year Reconstructed: 1983, Status: Open, Structure Length: 5.43m (17.81ft), Average Daily Traffic: 45,738 (year 2018), Truck Traffic: 5%, Average Future Daily Traffic: 45,952 (year 2040), Design Load: H 20, Features Intersected: RTE 907C, RTE 907C, Facility Carried by Structure: CROSS BAY BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 8.093, Lanes on structure: 8, Lanes under structure: 8, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 30.5m (100.1ft), Skew: 21 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 16.5m (54.1ft), Curb or Sidewalk Widths: Left: 3.1m (10.2ft), Right: 3.1m (10.2ft), Curb-To-Curb Width: 29.3m (96.1ft), Out-to-Out Width: 40.4m (132.5ft)
Condition: Deck: Good, Superstructure: Satisfactory, Substructure: Good, Operating Rating: 97.1 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 58.1 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 5.42m (17.78ft), Designated Inspection Frequency: Every 24 months, Critical Feature Inspection Frequency: Every 24 months, Inspection Date: May 2020, Critical Feature Inspection Date: May 2020, Bridge Improvement Cost: $13,470,000, Roadway Improvement Cost: $7,888,000, Total Project Cost: $21,359,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Latex Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 223156, Location: 2 MI W I678 & BELT PKWY (Lat: 40.666922, Lng: -73.838817), Route carried "on" structure: Interstate 878, Year Built: 1986, Status: Open, Structure Length: 7.13m (23.39ft), Average Daily Traffic: 22,160 (year 2018), Truck Traffic: 6%, Average Future Daily Traffic: 27,323 (year 2040), Design Load: HS 20, Features Intersected: RTE 907D, RTE 907D
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.225, Lanes on structure: 4, Lanes under structure: 7, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 19.8m (65.0ft), Skew: 4 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 37.7m (123.7ft), Curb-To-Curb Width: 19.7m (64.6ft), Out-to-Out Width: 20.6m (67.6ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Satisfactory, Operating Rating: 84.4 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 49.9 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 7.13m (23.39ft), Designated Inspection Frequency: Every 24 months, Inspection Date: June 2020, Bridge Improvement Cost: $9,940,000, Roadway Improvement Cost: $5,821,000, Total Project Cost: $15,760,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 223156, Location: 2 MI W I678 & BELT PKWY (Lat: 40.666922, Lng: -73.838817), Route carried "on" structure: Interstate 878, Year Built: 1986, Status: Open, Structure Length: 7.13m (23.39ft), Average Daily Traffic: 22,160 (year 2018), Truck Traffic: 6%, Average Future Daily Traffic: 27,323 (year 2040), Design Load: HS 20, Features Intersected: RTE 907D, RTE 907D
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.225, Lanes on structure: 4, Lanes under structure: 7, Base Highway Network: Yes, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 19.8m (65.0ft), Skew: 4 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 2, Length of Maximum Span: 37.7m (123.7ft), Curb-To-Curb Width: 19.7m (64.6ft), Out-to-Out Width: 20.6m (67.6ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Satisfactory, Operating Rating: 84.4 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 49.9 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Equal to present minimum criteria, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 7.13m (23.39ft), Designated Inspection Frequency: Every 24 months, Inspection Date: June 2020, Bridge Improvement Cost: $9,940,000, Roadway Improvement Cost: $5,821,000, Total Project Cost: $15,760,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 223157, Location: 1.8 MI W I678 & BELT PKWY (Lat: 40.666461, Lng: -73.834850), Route carried "on" structure: Business City street , Year Built: 1941, Status: Open, Structure Length: 3.44m (11.29ft), Average Daily Traffic: 6,488 (year 2017), Truck Traffic: 4%, Average Future Daily Traffic: 7,881 (year 2040), Design Load: H 20, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: COHANCY ST
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.322, Lanes on structure: 2, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 10.4m (34.1ft), Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 17.3m (56.8ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 10.4m (34.1ft), Out-to-Out Width: 17.4m (57.1ft)
Condition: Deck: Satisfactory, Superstructure: Poor, Substructure: Fair, Operating Rating: 55.0 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 22.3 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Meets minimum limits, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 3.44m (11.29ft), Designated Inspection Frequency: Every 24 months, Inspection Date: April 2020, Bridge Improvement Cost: $3,755,000, Roadway Improvement Cost: $2,199,000, Total Project Cost: $5,955,000 ( Estimate for 2021), Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Structure Number: 223157, Location: 1.8 MI W I678 & BELT PKWY (Lat: 40.666461, Lng: -73.834850), Route carried "on" structure: Business City street , Year Built: 1941, Status: Open, Structure Length: 3.44m (11.29ft), Average Daily Traffic: 6,488 (year 2017), Truck Traffic: 4%, Average Future Daily Traffic: 7,881 (year 2040), Design Load: H 20, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: COHANCY ST
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.322, Lanes on structure: 2, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 10.4m (34.1ft), Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 17.3m (56.8ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 10.4m (34.1ft), Out-to-Out Width: 17.4m (57.1ft)
Condition: Deck: Satisfactory, Superstructure: Poor, Substructure: Fair, Operating Rating: 55.0 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 22.3 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Meets minimum limits, Deck Geometry: Meets minimum limits, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 3.44m (11.29ft), Designated Inspection Frequency: Every 24 months, Inspection Date: April 2020, Bridge Improvement Cost: $3,755,000, Roadway Improvement Cost: $2,199,000, Total Project Cost: $5,955,000 ( Estimate for 2021), Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >> Show street view
Structure Number: 223158, Location: 1.6 MI W JCT I678 & BL PK (Lat: 40.665319, Lng: -73.832258), Route carried "on" structure: Ramp Other road , Year Built: 1961, Status: Open, Structure Length: 11.31m (37.11ft), Average Daily Traffic: 5,050 (year 1999), Truck Traffic: 4%, Average Future Daily Traffic: 7,070 (year 2019), Features Intersected: 907D907DX5M23018, RTE 90, Facility Carried by Structure: AQUEDUCT R T RAMP
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 2, Lanes under structure: 9, Owner: Local Toll Authority, Approaching Roadway Width: 9.8m (32.2ft), Skew: 3 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 38.1m (125.0ft), Curb or Sidewalk Widths: Left: 0.3m (1.0ft), Right: 0.3m (1.0ft), Curb-To-Curb Width: 9.8m (32.2ft), Out-to-Out Width: 11.4m (37.4ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Fair, Operating Rating: 59.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 36.3 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 11.30m (37.07ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2020, Bridge Improvement Cost: $6,606,000, Roadway Improvement Cost: $3,868,000, Total Project Cost: $10,474,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous, Membrane: Other
Structure Number: 223158, Location: 1.6 MI W JCT I678 & BL PK (Lat: 40.665319, Lng: -73.832258), Route carried "on" structure: Ramp Other road , Year Built: 1961, Status: Open, Structure Length: 11.31m (37.11ft), Average Daily Traffic: 5,050 (year 1999), Truck Traffic: 4%, Average Future Daily Traffic: 7,070 (year 2019), Features Intersected: 907D907DX5M23018, RTE 90, Facility Carried by Structure: AQUEDUCT R T RAMP
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.000, Lanes on structure: 2, Lanes under structure: 9, Owner: Local Toll Authority, Approaching Roadway Width: 9.8m (32.2ft), Skew: 3 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 38.1m (125.0ft), Curb or Sidewalk Widths: Left: 0.3m (1.0ft), Right: 0.3m (1.0ft), Curb-To-Curb Width: 9.8m (32.2ft), Out-to-Out Width: 11.4m (37.4ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Fair, Operating Rating: 59.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 36.3 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 11.30m (37.07ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2020, Bridge Improvement Cost: $6,606,000, Roadway Improvement Cost: $3,868,000, Total Project Cost: $10,474,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Bituminous, Membrane: Other
Find on map >> Show street view
Structure Number: 223159, Location: .5 MI W JCT I678 & BELT P (Lat: 40.666675, Lng: -73.810456), Route carried "on" structure: Business City street , Year Built: 1941, Status: Open, Structure Length: 2.83m (9.28ft), Average Daily Traffic: 4,826 (year 2020), Truck Traffic: 8%, Average Future Daily Traffic: 9,470 (year 2040), Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: 130TH STREET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.257, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 15.2m (49.9ft), Skew: 1 degrees, Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 14.6m (47.9ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 15.2m (49.9ft), Out-to-Out Width: 22.3m (73.2ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Good, Operating Rating: 55.9 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 21.0 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.83m (9.28ft), Designated Inspection Frequency: Every 24 months, Inspection Date: January 2020, Bridge Improvement Cost: $4,027,000, Roadway Improvement Cost: $2,358,000, Total Project Cost: $6,385,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Structure Number: 223159, Location: .5 MI W JCT I678 & BELT P (Lat: 40.666675, Lng: -73.810456), Route carried "on" structure: Business City street , Year Built: 1941, Status: Open, Structure Length: 2.83m (9.28ft), Average Daily Traffic: 4,826 (year 2020), Truck Traffic: 8%, Average Future Daily Traffic: 9,470 (year 2040), Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: 130TH STREET
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.257, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 15.2m (49.9ft), Skew: 1 degrees, Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 14.6m (47.9ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 15.2m (49.9ft), Out-to-Out Width: 22.3m (73.2ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Good, Operating Rating: 55.9 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 21.0 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: High priority of corrective action, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.83m (9.28ft), Designated Inspection Frequency: Every 24 months, Inspection Date: January 2020, Bridge Improvement Cost: $4,027,000, Roadway Improvement Cost: $2,358,000, Total Project Cost: $6,385,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >> Show street view
Structure Number: 2231601, Location: 1.1 MI E I678 & BELT PKWY (Lat: 40.667256, Lng: -73.780269), Route carried "on" structure: City street 907D, Year Built: 1988, Status: Open, Structure Length: 4.48m (14.70ft), Average Daily Traffic: 66,259 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 81,697 (year 2040), Design Load: HS 20, Features Intersected: ROCKAWAY BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 4.811, Lanes on structure: 4, Lanes under structure: 6, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 18.9m (62.0ft), Skew: 2 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 43.2m (141.7ft), Curb-To-Curb Width: 18.9m (62.0ft), Out-to-Out Width: 19.8m (65.0ft)
Condition: Deck: Good, Superstructure: Excellent, Substructure: Good, Operating Rating: 88.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 46.3 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.48m (14.70ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $6,239,000, Roadway Improvement Cost: $3,654,000, Total Project Cost: $9,893,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231601, Location: 1.1 MI E I678 & BELT PKWY (Lat: 40.667256, Lng: -73.780269), Route carried "on" structure: City street 907D, Year Built: 1988, Status: Open, Structure Length: 4.48m (14.70ft), Average Daily Traffic: 66,259 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 81,697 (year 2040), Design Load: HS 20, Features Intersected: ROCKAWAY BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 4.811, Lanes on structure: 4, Lanes under structure: 6, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 18.9m (62.0ft), Skew: 2 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 43.2m (141.7ft), Curb-To-Curb Width: 18.9m (62.0ft), Out-to-Out Width: 19.8m (65.0ft)
Condition: Deck: Good, Superstructure: Excellent, Substructure: Good, Operating Rating: 88.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 46.3 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Meets minimum limits, Underclear: Equal to present minimum criteria, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.48m (14.70ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $6,239,000, Roadway Improvement Cost: $3,654,000, Total Project Cost: $9,893,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 2231602, Location: 1.1 MI E 678I & BELT PKWY (Lat: 40.667128, Lng: -73.780158), Route carried "on" structure: City street 907D, Year Built: 1992, Status: Open, Structure Length: 4.48m (14.70ft), Average Daily Traffic: 66,259 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 81,697 (year 2040), Design Load: HS 20, Features Intersected: ROCKAWAY BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 4.811, Lanes on structure: 5, Lanes under structure: 6, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 27.1m (88.9ft), Skew: 22 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 43.2m (141.7ft), Curb-To-Curb Width: 27.1m (88.9ft), Out-to-Out Width: 28.8m (94.5ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Good, Operating Rating: 88.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 46.3 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Superior to present desirable criteria, Underclear: Somewhat better than minimum adequacy, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.48m (14.70ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $9,178,000, Roadway Improvement Cost: $5,375,000, Total Project Cost: $14,553,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Structure Number: 2231602, Location: 1.1 MI E 678I & BELT PKWY (Lat: 40.667128, Lng: -73.780158), Route carried "on" structure: City street 907D, Year Built: 1992, Status: Open, Structure Length: 4.48m (14.70ft), Average Daily Traffic: 66,259 (year 2018), Truck Traffic: 1%, Average Future Daily Traffic: 81,697 (year 2040), Design Load: HS 20, Features Intersected: ROCKAWAY BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 4.811, Lanes on structure: 5, Lanes under structure: 6, Base Highway Network: Yes, Owner: State Highway Agency, Approaching Roadway Width: 27.1m (88.9ft), Skew: 22 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 1, Length of Maximum Span: 43.2m (141.7ft), Curb-To-Curb Width: 27.1m (88.9ft), Out-to-Out Width: 28.8m (94.5ft)
Condition: Deck: Good, Superstructure: Very good, Substructure: Good, Operating Rating: 88.9 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 46.3 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: Superior to present desirable criteria, Underclear: Somewhat better than minimum adequacy, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 4.48m (14.70ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $9,178,000, Roadway Improvement Cost: $5,375,000, Total Project Cost: $14,553,000 ( Estimate for 2021), Deck Structure Type: Concrete Cast-file-Place, Wearing Surface/Protective System: Wearing Surface: Integral Concrete, Deck Protection: Epoxy Coated Reinforcing
Find on map >> Show street view
Structure Number: 223161, Location: 1.6 MI E I678 & BELT PKWY (Lat: 40.667333, Lng: -73.771022), Route carried "on" structure: Business City street , Year Built: 2003, Status: Open, Structure Length: 5.70m (18.70ft), Average Daily Traffic: 7,788 (year 2018), Truck Traffic: 14%, Average Future Daily Traffic: 15,282 (year 2040), Design Load: HS 25 or greater, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: GUY BREWER BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 1.271, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 13.4m (44.0ft), Skew: 3 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 19.8m (65.0ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 13.4m (44.0ft), Out-to-Out Width: 20.1m (65.9ft)
Condition: Deck: Very good, Superstructure: Good, Substructure: Very good, Operating Rating: 88.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 44.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 5.69m (18.67ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2020, Bridge Improvement Cost: $5,605,000, Roadway Improvement Cost: $3,282,000, Total Project Cost: $8,888,000 ( Estimate for 2021), Deck Structure Type: Closed Grating, Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Structure Number: 223161, Location: 1.6 MI E I678 & BELT PKWY (Lat: 40.667333, Lng: -73.771022), Route carried "on" structure: Business City street , Year Built: 2003, Status: Open, Structure Length: 5.70m (18.70ft), Average Daily Traffic: 7,788 (year 2018), Truck Traffic: 14%, Average Future Daily Traffic: 15,282 (year 2040), Design Load: HS 25 or greater, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: GUY BREWER BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 1.271, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 13.4m (44.0ft), Skew: 3 degrees, Material/Design: Steel, Design/Construction: Stringer/Multi-beam, Number Of Spans In Main Unit: 4, Length of Maximum Span: 19.8m (65.0ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 13.4m (44.0ft), Out-to-Out Width: 20.1m (65.9ft)
Condition: Deck: Very good, Superstructure: Good, Substructure: Very good, Operating Rating: 88.0 metric tons, Method Used To Determine Operating Rating: Load Factor (LF), Inventory Rating: 44.5 metric tons, Method Used To Determine Inventory Rating: Load Factor (LF), Structural Evaluation: Better than present minimum criteria, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 5.69m (18.67ft), Designated Inspection Frequency: Every 24 months, Inspection Date: August 2020, Bridge Improvement Cost: $5,605,000, Roadway Improvement Cost: $3,282,000, Total Project Cost: $8,888,000 ( Estimate for 2021), Deck Structure Type: Closed Grating, Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >> Show street view
Structure Number: 223162, Location: 1.8 MI E JCT I678 & BL PK (Lat: 40.666908, Lng: -73.767028), Route carried "on" structure: Business City street , Year Built: 1940, Year Reconstructed: 1994, Status: Open, Structure Length: 2.93m (9.61ft), Average Daily Traffic: 5,483 (year 2019), Truck Traffic: 10%, Average Future Daily Traffic: 5,508 (year 2040), Design Load: H 20, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: FARMERS BOULEVARD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 1.110, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 13.4m (44.0ft), Skew: 1 degrees, Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 14.9m (48.9ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 13.4m (44.0ft), Out-to-Out Width: 20.4m (66.9ft)
Condition: Deck: Satisfactory, Superstructure: Poor, Substructure: Fair, Operating Rating: 56.4 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 23.3 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Meets minimum limits, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.92m (9.58ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $3,880,000, Roadway Improvement Cost: $2,272,000, Total Project Cost: $6,152,000 ( Estimate for 2021), Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Structure Number: 223162, Location: 1.8 MI E JCT I678 & BL PK (Lat: 40.666908, Lng: -73.767028), Route carried "on" structure: Business City street , Year Built: 1940, Year Reconstructed: 1994, Status: Open, Structure Length: 2.93m (9.61ft), Average Daily Traffic: 5,483 (year 2019), Truck Traffic: 10%, Average Future Daily Traffic: 5,508 (year 2040), Design Load: H 20, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: FARMERS BOULEVARD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 1.110, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 13.4m (44.0ft), Skew: 1 degrees, Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 14.9m (48.9ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 13.4m (44.0ft), Out-to-Out Width: 20.4m (66.9ft)
Condition: Deck: Satisfactory, Superstructure: Poor, Substructure: Fair, Operating Rating: 56.4 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 23.3 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Meets minimum limits, Deck Geometry: High priority of replacement, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.92m (9.58ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $3,880,000, Roadway Improvement Cost: $2,272,000, Total Project Cost: $6,152,000 ( Estimate for 2021), Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >> Show street view
Structure Number: 223163, Location: 2.2 MI E I678+BELT PKWY (Lat: 40.665897, Lng: -73.757906), Route carried "on" structure: Business City street , Year Built: 1940, Status: Open, Structure Length: 2.99m (9.81ft), Average Daily Traffic: 14,384 (year 2019), Truck Traffic: 8%, Average Future Daily Traffic: 14,451 (year 2040), Design Load: H 20, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: SPRINGFIELD BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.740, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 18.9m (62.0ft), Skew: 21 degrees, Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 14.9m (48.9ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 18.9m (62.0ft), Out-to-Out Width: 26.5m (86.9ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Satisfactory, Operating Rating: 56.2 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 23.3 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.98m (9.78ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $5,489,000, Roadway Improvement Cost: $3,214,000, Total Project Cost: $8,703,000 ( Estimate for 2021), Wearing Surface/Protective System: Wearing Surface: Bituminous
Structure Number: 223163, Location: 2.2 MI E I678+BELT PKWY (Lat: 40.665897, Lng: -73.757906), Route carried "on" structure: Business City street , Year Built: 1940, Status: Open, Structure Length: 2.99m (9.81ft), Average Daily Traffic: 14,384 (year 2019), Truck Traffic: 8%, Average Future Daily Traffic: 14,451 (year 2040), Design Load: H 20, Features Intersected: RTE 907D, RTE 907D, Facility Carried by Structure: SPRINGFIELD BLVD
Minimum Vertical Clearance: 30+ m (98+ ft), Kilometerpoint: 0.740, Lanes on structure: 4, Lanes under structure: 6, Owner: City or Municipal Highway Agency, Approaching Roadway Width: 18.9m (62.0ft), Skew: 21 degrees, Material/Design: Concrete continuous, Design/Construction: Frame, Number Of Spans In Main Unit: 2, Length of Maximum Span: 14.9m (48.9ft), Curb or Sidewalk Widths: Left: 3.0m (9.8ft), Right: 3.0m (9.8ft), Curb-To-Curb Width: 18.9m (62.0ft), Out-to-Out Width: 26.5m (86.9ft)
Condition: Deck: Fair, Superstructure: Fair, Substructure: Satisfactory, Operating Rating: 56.2 metric tons, Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment, Inventory Rating: 23.3 metric tons, Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment, Structural Evaluation: Somewhat better than minimum adequacy, Deck Geometry: Equal to present minimum criteria, Underclear: High priority of corrective action, Approach Roadway Alignment: Equal to present desirable criteria, Length Of Structure Improvement: 2.98m (9.78ft), Designated Inspection Frequency: Every 24 months, Inspection Date: May 2020, Bridge Improvement Cost: $5,489,000, Roadway Improvement Cost: $3,214,000, Total Project Cost: $8,703,000 ( Estimate for 2021), Wearing Surface/Protective System: Wearing Surface: Bituminous