Bridge Statistics for New York, New York (NY)
Condition, Traffic, Stress, Structural Evaluation, Project Costs


  • National Bridge Inventory (NBI) Statistics
  • 2,992Number of bridges
  • 68,865ft / 20,990mTotal length
  • $41,847,025,000Total costs
  • 106,047,317Total average daily traffic
  • 3,057,321Total average daily truck traffic
  • National Bridge Inventory (NBI) Registered Bridges for New York
  • No street view available for this location

New bridges in New York, NY - historical statistics
  • New bridges - historical statistics
  • 47Before 1900
  • 1961900-1909
  • 1711910-1919
  • 1241920-1929
  • 3951930-1939
  • 2541940-1949
  • 4641950-1959
  • 7351960-1969
  • 1551970-1979
  • 881980-1989
  • 731990-1999
  • 1432000-2009
  • 1242010-2019
  • 232020-2022
Reconstructed bridges in New York, NY - Historical Statistics
  • Reconstructed bridges - Historical Statistics
  • 11920-1929
  • 121930-1939
  • 01940-1949
  • 71950-1959
  • 81960-1969
  • 491970-1979
  • 1441980-1989
  • 1731990-1999
  • 982000-2009
  • 652010-2019
  • 52020-2022
Average Bridge Daily Traffic in New York, NY
Average Bridge Truck Traffic in New York, NY
Bridge Condition - Deck
  • Bridge Condition - Deck
  • 9.4%Excellent
  • 13.0%Very good
  • 23.3%Good
  • 29.7%Satisfactory
  • 20.6%Fair
  • 4.0%Poor
Bridge Condition - Superstructure
  • Bridge Condition - Superstructure
  • 9.1%Excellent
  • 12.8%Very good
  • 20.5%Good
  • 34.5%Satisfactory
  • 19.5%Fair
  • 3.5%Poor
Bridge Condition - Substructure
  • Bridge Condition - Substructure
  • 5.9%Excellent
  • 9.8%Very good
  • 24.0%Good
  • 39.8%Satisfactory
  • 18.9%Fair
  • 1.7%Poor
Bridge Condition - Channel
  • Bridge Condition - Channel
  • 8.6%Excellent
  • 19.0%Very good
  • 24.5%Good
  • 30.7%Satisfactory
  • 10.4%Fair
  • 4.9%Poor
  • 1.8%Serious
Bridge Condition - Culverts
  • Bridge Condition - Culverts
  • 9.5%Very good
  • 14.3%Good
  • 47.6%Satisfactory
  • 28.6%Fair
Find on map >>   Show street view

Structure Number: 224904,  Location: IN FORT WADSWORTH (Lat: 40.605828,  Lng: -74.066131),  Route carried "on" structure: City street ,  Year Built: 1936,  Year Reconstructed: 1996,  Status: Open,  Structure Length: 2.99m (9.81ft),  Average Daily Traffic: 3,098 (year 2018),  Truck Traffic: 8%,  Average Future Daily Traffic: 3,763 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: TOMPKINS AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.080,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Skew: 6 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 29.2m (95.8ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 15.8m (51.8ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 48.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.98m (9.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2020,  Bridge Improvement Cost: $6,148,000,  Roadway Improvement Cost: $3,600,000,  Total Project Cost: $9,748,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 224909,  Location: IN ARLINGTON (Lat: 40.635167,  Lng: -74.145650),  Route carried "on" structure: City street ,  Year Built: 1937,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 4.79m (15.72ft),  Average Daily Traffic: 6,309 (year 2020),  Truck Traffic: 11%,  Average Future Daily Traffic: 6,338 (year 2040),  Design Load: HS 20,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: MORNINGSTAR ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.110,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 4 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 14.0m (45.9ft),  Curb or Sidewalk Widths: Left: 1.2m (3.9ft),  Right: 1.7m (5.6ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 15.4m (50.5ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 61.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 36.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 4.78m (15.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: March 2020,  Bridge Improvement Cost: $3,596,000,  Roadway Improvement Cost: $2,106,000,  Total Project Cost: $5,702,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 22491,  Location: IN ARLINGTON (Lat: 40.634258,  Lng: -74.148044),  Route carried "on" structure: City street ,  Year Built: 1937,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 4.45m (14.60ft),  Truck Traffic: 10%,  Design Load: H 20,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: GRANITE AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.724,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.3m (33.8ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 11.5m (37.7ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 4.45m (14.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,639,000,  Roadway Improvement Cost: $1,545,000,  Total Project Cost: $4,184,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224911,  Location: IN MARINERS HARBOR (Lat: 40.634019,  Lng: -74.150878),  Route carried "on" structure: ServiceCity street ,  Year Built: 1934,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 3.60m (11.81ft),  Average Daily Traffic: 1,228 (year 2017),  Truck Traffic: 3%,  Average Future Daily Traffic: 1,719 (year 2037),  Design Load: HS 20,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: LAKE AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.933,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.1m (33.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 13.7m (44.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Inventory Rating: 64.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.59m (11.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,284,000,  Roadway Improvement Cost: $1,337,000,  Total Project Cost: $3,621,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224912,  Location: 0.3 MI WEST OF BAYONNE BR (Lat: 40.634019,  Lng: -74.151903),  Route carried "on" structure: City street ,  Year Built: 1934,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 3.66m (12.01ft),  Truck Traffic: 4%,  Design Load: HS 20,  Features Intersected: EX-STATEN ISLD RR,  Facility Carried by Structure: SIMONSON AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.917,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 13.1m (43.0ft),  Curb or Sidewalk Widths: Left: 2.4m (7.9ft),  Right: 2.4m (7.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Inventory Rating: 57.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.65m (11.98ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,180,000,  Roadway Improvement Cost: $1,277,000,  Total Project Cost: $3,457,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224913,  Location: IN MARINERS HARBOR (Lat: 40.634003,  Lng: -74.153306),  Route carried "on" structure: ServiceCity street ,  Year Built: 1934,  Year Reconstructed: 1991,  Status: Open,  Structure Length: 3.63m (11.91ft),  Truck Traffic: 4%,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: VAN NAME AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.885,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 13.4m (44.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 14.0m (45.9ft)

Condition: Deck: Good,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 63.2 metric tons,  Method Used To Determine Operating Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Inventory Rating: 48.6 metric tons,  Method Used To Determine Inventory Rating: Load and Resistance Factor Rating (LRFR) rating reported by rating factor(RF) method using HL-93 loadings,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.62m (11.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $2,180,000,  Roadway Improvement Cost: $1,277,000,  Total Project Cost: $3,457,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224914,  Location: JCT VAN PELT AV &EX-B&ORR (Lat: 40.633933,  Lng: -74.155067),  Route carried "on" structure: City street ,  Year Built: 1934,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 2.93m (9.61ft),  Truck Traffic: 4%,  Design Load: HS 20,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: VAN PELT AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.000,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 10.3m (33.8ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.1m (49.5ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Satisfactory,  Operating Rating: 87.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 52.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.92m (9.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $2,566,000,  Roadway Improvement Cost: $1,503,000,  Total Project Cost: $4,069,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224916,  Location: AT MARINERS HARBOR (Lat: 40.633853,  Lng: -74.157042),  Route carried "on" structure: City street ,  Year Built: 1934,  Year Reconstructed: 1997,  Status: Open,  Structure Length: 4.05m (13.29ft),  Truck Traffic: 4%,  Design Load: HS 20,  Features Intersected: EX-STATEN ISLD RR,  Facility Carried by Structure: DE HART AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.129,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 10.9m (35.8ft),  Curb or Sidewalk Widths: Left: 2.0m (6.6ft),  Right: 2.0m (6.6ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Inventory Rating: 68.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 4.05m (13.29ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,400,000,  Roadway Improvement Cost: $1,405,000,  Total Project Cost: $3,805,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224917,  Location: IN MARINERS HARBOR (Lat: 40.633803,  Lng: -74.158139),  Route carried "on" structure: City street ,  Year Built: 1937,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 4.08m (13.39ft),  Average Daily Traffic: 2,330 (year 2017),  Truck Traffic: 4%,  Average Future Daily Traffic: 3,262 (year 2037),  Design Load: H 20,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: UNION AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.821,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 13.4m (44.0ft),  Curb or Sidewalk Widths: Left: 2.0m (6.6ft),  Right: 2.0m (6.6ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.1m (49.5ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Satisfactory,  Inventory Rating: 62.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.08m (13.39ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: April 2021,  Bridge Improvement Cost: $2,402,000,  Roadway Improvement Cost: $1,407,000,  Total Project Cost: $3,809,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224918,  Location: IN MARINERS HARBOR (Lat: 40.633744,  Lng: -74.160325),  Route carried "on" structure: City street ,  Year Built: 1935,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 4.18m (13.71ft),  Truck Traffic: 4%,  Design Load: HS 20,  Features Intersected: B&O RR- ABANDONED,  Facility Carried by Structure: HARBOR ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.611,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.5m (27.9ft),  Material/Design: Concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 11.5m (37.7ft),  Curb or Sidewalk Widths: Left: 1.7m (5.6ft),  Right: 2.2m (7.2ft),  Curb-To-Curb Width: 8.6m (28.2ft),  Out-to-Out Width: 13.0m (42.7ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Good,  Operating Rating: 77.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 45.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Better than present minimum criteria,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.17m (13.68ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $1,996,000,  Roadway Improvement Cost: $1,169,000,  Total Project Cost: $3,164,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 22492,  Location: IN ARLINGTON (Lat: 40.633528,  Lng: -74.166300),  Route carried "on" structure: City street ,  Year Built: 2001,  Status: Open,  Structure Length: 4.54m (14.90ft),  Average Daily Traffic: 7,452 (year 2018),  Truck Traffic: 16%,  Average Future Daily Traffic: 7,487 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: Arlington Yd,  Facility Carried by Structure: SOUTH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.811,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 12.2m (40.0ft),  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 18.8m (61.7ft),  Curb or Sidewalk Widths: Left: 2.3m (7.5ft),  Right: 2.3m (7.5ft),  Curb-To-Curb Width: 12.2m (40.0ft),  Out-to-Out Width: 17.4m (57.1ft)

Condition: Deck: Good,  Superstructure: Satisfactory,  Substructure: Very good,  Operating Rating: 51.7 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 4.54m (14.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: December 2021,  Bridge Improvement Cost: $3,046,000,  Roadway Improvement Cost: $1,784,000,  Total Project Cost: $4,829,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224924,  Location: AT WEST NEW BRIGHTON (Lat: 40.517167,  Lng: -74.240703),  Route carried "on" structure: City street ,  Year Built: 1939,  Status: Open,  Structure Length: 2.26m (7.41ft),  Average Daily Traffic: 10,903 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 13,244 (year 2040),  Design Load: H 20,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: ARTHUR KILL RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.981,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 5 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 22.3m (73.2ft),  Curb or Sidewalk Widths: Left: 2.3m (7.5ft),  Right: 2.3m (7.5ft),  Curb-To-Curb Width: 10.3m (33.8ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Fair,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 60.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 21.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.25m (7.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $4,457,000,  Roadway Improvement Cost: $2,610,000,  Total Project Cost: $7,066,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete
Find on map >>   Show street view

Structure Number: 2249269,  Location: AT RICHMOND VALLEY (Lat: 40.518522,  Lng: -74.234619),  Route carried "on" structure: City street ,  Year Built: 1989,  Status: Open,  Structure Length: 16.00m (52.49ft),  Average Daily Traffic: 20,245 (year 2020),  Truck Traffic: 4%,  Average Future Daily Traffic: 20,340 (year 2040),  Design Load: HS 20+Mod,  Features Intersected: SIRT SOUTH SHORE, TIDAL,  Facility Carried by Structure: PAGE AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.255,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: Local Agency,  Approaching Roadway Width: 14.0m (45.9ft),  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 42.6m (139.8ft),  Curb or Sidewalk Widths: Left: 1.6m (5.2ft),  Right: 1.6m (5.2ft),  Curb-To-Curb Width: 14.0m (45.9ft),  Out-to-Out Width: 17.8m (58.4ft)

Condition: Deck: Good,  Superstructure: Excellent,  Substructure: Very good,  Channel: Very good,  Operating Rating: 71.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 43.5 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 16.00m (52.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $13,196,000,  Roadway Improvement Cost: $7,728,000,  Total Project Cost: $20,924,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224927,  Location: AT RICHMOND VALLEY (Lat: 40.519703,  Lng: -74.228650),  Route carried "on" structure: City street ,  Year Built: 1938,  Year Reconstructed: 1993,  Status: Open,  Structure Length: 5.76m (18.90ft),  Truck Traffic: 4%,  Features Intersected: SIRT SOUTH SHORE, Creek,  Facility Carried by Structure: RICHMOND VLLEY RD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.901,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 4 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 4,  Length of Maximum Span: 15.8m (51.8ft),  Curb or Sidewalk Widths: Left: 2.2m (7.2ft),  Right: 2.2m (7.2ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 50.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 30.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 5.76m (18.90ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $6,288,000,  Roadway Improvement Cost: $3,682,000,  Total Project Cost: $9,970,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224929,  Location: IN PRINCES BAY (Lat: 40.525142,  Lng: -74.200794),  Route carried "on" structure: City street ,  Year Built: 1925,  Year Reconstructed: 1988,  Status: Open,  Structure Length: 2.13m (6.99ft),  Average Daily Traffic: 6,072 (year 2020),  Truck Traffic: 7%,  Average Future Daily Traffic: 7,376 (year 2040),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: SEGUINE AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.577,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 9.8m (32.2ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 19.8m (65.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 9.8m (32.2ft),  Out-to-Out Width: 14.1m (46.3ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 90.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 54.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.13m (6.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,261,000,  Roadway Improvement Cost: $1,324,000,  Total Project Cost: $3,585,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 22493,  Location: AT PRINCES BAY (Lat: 40.533019,  Lng: -74.192367),  Route carried "on" structure: City street ,  Year Built: 1938,  Status: Open,  Structure Length: 2.71m (8.89ft),  Average Daily Traffic: 5,480 (year 2018),  Truck Traffic: 7%,  Average Future Daily Traffic: 6,657 (year 2040),  Design Load: H 20,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: HUGUENOT AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.609,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 12.8m (42.0ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 3.4m (11.2ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 22.3m (73.2ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 46.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 27.2 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.71m (8.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $4,630,000,  Roadway Improvement Cost: $2,711,000,  Total Project Cost: $7,342,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 224932,  Location: IN ANNADALE (Lat: 40.539039,  Lng: -74.183594),  Route carried "on" structure: City street ,  Year Built: 1940,  Status: Open,  Structure Length: 3.29m (10.79ft),  Average Daily Traffic: 3,154 (year 2017),  Truck Traffic: 3%,  Average Future Daily Traffic: 4,416 (year 2037),  Design Load: H 20,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: ALBEE AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.402,  Lanes on structure: 4,  Owner: Local Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 11.2m (36.7ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 18.3m (60.0ft)

Condition: Deck: Satisfactory,  Superstructure: Fair,  Substructure: Satisfactory,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.29m (10.79ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $2,938,000,  Roadway Improvement Cost: $1,721,000,  Total Project Cost: $4,659,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224933,  Location: IN ANNADALE (Lat: 40.540619,  Lng: -74.177333),  Route carried "on" structure: City street ,  Year Built: 2006,  Status: Open,  Structure Length: 1.80m (5.91ft),  Average Daily Traffic: 4,353 (year 2013),  Truck Traffic: 6%,  Average Future Daily Traffic: 5,288 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: ANNADALE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.7m (35.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.5m (54.1ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 18.3m (60.0ft)

Condition: Deck: Good,  Superstructure: Very good,  Substructure: Very good,  Inventory Rating: 95.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 1.79m (5.87ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,873,000,  Roadway Improvement Cost: $1,683,000,  Total Project Cost: $4,556,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224936,  Location: AT GREAT KILLS (Lat: 40.551617,  Lng: -74.150514),  Route carried "on" structure: City street ,  Year Built: 1939,  Year Reconstructed: 1990,  Status: Open,  Structure Length: 1.68m (5.51ft),  Average Daily Traffic: 5,092 (year 2016),  Truck Traffic: 6%,  Average Future Daily Traffic: 6,185 (year 2040),  Design Load: H 20,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: GIFFORDS LANE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.097,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 16.4m (53.8ft),  Curb or Sidewalk Widths: Left: 2.7m (8.9ft),  Right: 2.5m (8.2ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 16.9m (55.4ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 98.0 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.67m (5.48ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $3,076,000,  Roadway Improvement Cost: $1,801,000,  Total Project Cost: $4,877,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224937,  Location: IN GREAT KILLS (Lat: 40.552639,  Lng: -74.145528),  Route carried "on" structure: City street ,  Year Built: 2002,  Status: Open,  Structure Length: 1.62m (5.31ft),  Truck Traffic: 4%,  Design Load: HS 20,  Features Intersected: SIRT SOUTH SHOR,  Facility Carried by Structure: GREAVES AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.113,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 14.9m (48.9ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Good,  Operating Rating: 65.0 metric tons,  Method Used To Determine Operating Rating: Allowable Stress (AS),  Inventory Rating: 47.0 metric tons,  Method Used To Determine Inventory Rating: Allowable Stress (AS),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 1.61m (5.28ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,769,000,  Roadway Improvement Cost: $1,622,000,  Total Project Cost: $4,391,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Integral Concrete
Find on map >>   Show street view

Structure Number: 224938,  Location: IN OAKWOOD (Lat: 40.564558,  Lng: -74.126942),  Route carried "on" structure: City street ,  Year Built: 1951,  Status: Open,  Structure Length: 3.32m (10.89ft),  Average Daily Traffic: 5,880 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 7,143 (year 2040),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: GUYON AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.274,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 14.6m (47.9ft),  Curb or Sidewalk Widths: Left: 2.7m (8.9ft),  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 19.5m (64.0ft)

Condition: Deck: Fair,  Superstructure: Fair,  Substructure: Fair,  Operating Rating: 55.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 32.7 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Equal to present minimum criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.32m (10.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,708,000,  Roadway Improvement Cost: $1,586,000,  Total Project Cost: $4,294,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 22494,  Location: IN NEW DORP (Lat: 40.571328,  Lng: -74.120017),  Route carried "on" structure: City street ,  Year Built: 1951,  Status: Open,  Structure Length: 2.32m (7.61ft),  Average Daily Traffic: 4,063 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 5,688 (year 2040),  Design Load: HS 20,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: BEACH AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.306,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 2.1m (6.9ft),  Right: 2.1m (6.9ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 65.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 2.31m (7.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,489,000,  Roadway Improvement Cost: $1,457,000,  Total Project Cost: $3,946,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224941,  Location: IN NEW DORP (Lat: 40.572417,  Lng: -74.118622),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Open,  Structure Length: 2.32m (7.61ft),  Average Daily Traffic: 1,520 (year 2017),  Truck Traffic: 1%,  Average Future Daily Traffic: 2,128 (year 2037),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: ROSS AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.290,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 2.2m (7.2ft),  Right: 2.2m (7.2ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 71.7 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 42.6 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 2.31m (7.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,619,000,  Roadway Improvement Cost: $1,533,000,  Total Project Cost: $4,152,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224942,  Location: IN NEW DORP (Lat: 40.573183,  Lng: -74.117569),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Open,  Structure Length: 2.32m (7.61ft),  Average Daily Traffic: 2,863 (year 2020),  Truck Traffic: 5%,  Average Future Daily Traffic: 5,618 (year 2040),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: ROSE AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.370,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 10.4m (34.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 2.2m (7.2ft),  Right: 2.2m (7.2ft),  Curb-To-Curb Width: 10.4m (34.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 66.2 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 2.31m (7.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2021,  Bridge Improvement Cost: $2,421,000,  Roadway Improvement Cost: $1,418,000,  Total Project Cost: $3,839,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224943,  Location: IN NEW DORP (Lat: 40.574025,  Lng: -74.116422),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Open,  Structure Length: 2.32m (7.61ft),  Average Daily Traffic: 8,956 (year 2016),  Truck Traffic: 6%,  Average Future Daily Traffic: 10,879 (year 2040),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: NEW DORP LANE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.338,  Lanes on structure: 4,  Owner: Local Agency,  Approaching Roadway Width: 16.8m (55.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 12.1m (39.7ft),  Curb or Sidewalk Widths: Left: 3.8m (12.5ft),  Right: 3.5m (11.5ft),  Curb-To-Curb Width: 16.8m (55.1ft),  Out-to-Out Width: 30.5m (100.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 67.1 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 39.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 2.31m (7.58ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $4,935,000,  Roadway Improvement Cost: $2,890,000,  Total Project Cost: $7,826,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224944,  Location: IN NEW DORP (Lat: 40.577481,  Lng: -74.111636),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Open,  Structure Length: 3.14m (10.30ft),  Truck Traffic: 4%,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: BANCROFT AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.306,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 11.0m (36.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 11.8m (38.7ft),  Curb or Sidewalk Widths: Left: 3.0m (9.8ft),  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 17.7m (58.1ft)

Condition: Deck: Satisfactory,  Superstructure: Satisfactory,  Substructure: Satisfactory,  Operating Rating: 42.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 25.4 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Superior to present desirable criteria,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.13m (10.27ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $2,594,000,  Roadway Improvement Cost: $1,519,000,  Total Project Cost: $4,113,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224946,  Location: IN NEW DORP (Lat: 40.579503,  Lng: -74.108928),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Open,  Structure Length: 1.37m (4.49ft),  Average Daily Traffic: 4,786 (year 2020),  Truck Traffic: 2%,  Average Future Daily Traffic: 5,814 (year 2040),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: LINCOLN AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 4,  Owner: Local Agency,  Approaching Roadway Width: 16.8m (55.1ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 12.4m (40.7ft),  Curb or Sidewalk Widths: Left: 3.8m (12.5ft),  Right: 3.6m (11.8ft),  Curb-To-Curb Width: 16.8m (55.1ft),  Out-to-Out Width: 30.5m (100.1ft)

Condition: Deck: Fair,  Superstructure: Satisfactory,  Substructure: Very good,  Operating Rating: 81.6 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.0 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 1.37m (4.49ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $5,228,000,  Roadway Improvement Cost: $3,061,000,  Total Project Cost: $8,289,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224947,  Location: IN GRANT CITY (Lat: 40.580642,  Lng: -74.107367),  Route carried "on" structure: City street ,  Year Built: 1952,  Status: Open,  Structure Length: 1.25m (4.10ft),  Average Daily Traffic: 4,254 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 4,273 (year 2040),  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: MIDLAND AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.290,  Lanes on structure: 4,  Owner: Local Agency,  Approaching Roadway Width: 15.2m (49.9ft),  Skew: 1 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 11.8m (38.7ft),  Curb or Sidewalk Widths: Left: 3.1m (10.2ft),  Right: 3.1m (10.2ft),  Curb-To-Curb Width: 15.2m (49.9ft),  Out-to-Out Width: 21.9m (71.9ft)

Condition: Deck: Satisfactory,  Superstructure: Good,  Substructure: Good,  Operating Rating: 63.5 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 38.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of corrective action,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Superior to present desirable criteria,  Length Of Structure Improvement: 1.24m (4.07ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $3,766,000,  Roadway Improvement Cost: $2,205,000,  Total Project Cost: $5,971,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224948,  Location: IN ROSEBANK (Lat: 40.601644,  Lng: -74.085147),  Route carried "on" structure: City street ,  Year Built: 1932,  Year Reconstructed: 1997,  Status: Open,  Structure Length: 3.23m (10.60ft),  Average Daily Traffic: 3,739 (year 2018),  Truck Traffic: 4%,  Average Future Daily Traffic: 4,542 (year 2040),  Design Load: H 20,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: WEST FINGERBOARD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.628,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 11.6m (38.1ft),  Skew: 4 degrees,  Material/Design: Steel continuous,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 15.2m (49.9ft),  Curb or Sidewalk Widths: Left: 1.5m (4.9ft),  Right: 1.5m (4.9ft),  Curb-To-Curb Width: 11.6m (38.1ft),  Out-to-Out Width: 15.2m (49.9ft)

Condition: Deck: Excellent,  Superstructure: Excellent,  Substructure: Good,  Operating Rating: 89.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 58.1 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.23m (10.60ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $4,415,000,  Roadway Improvement Cost: $2,585,000,  Total Project Cost: $7,000,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224949,  Location: AT GRASMERE (Lat: 40.603803,  Lng: -74.083544),  Route carried "on" structure: City street ,  Year Built: 1932,  Year Reconstructed: 1994,  Status: Open,  Structure Length: 3.63m (11.91ft),  Average Daily Traffic: 6,617 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 6,648 (year 2040),  Design Load: HS 25 or greater,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: CLOVE ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.628,  Lanes on structure: 2,  Owner: Local Agency,  Approaching Roadway Width: 7.3m (24.0ft),  Skew: 3 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 3,  Length of Maximum Span: 12.2m (40.0ft),  Curb or Sidewalk Widths: Left: 2.2m (7.2ft),  Right: 2.9m (9.5ft),  Curb-To-Curb Width: 7.3m (24.0ft),  Out-to-Out Width: 13.4m (44.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 85.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: High priority of replacement,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.62m (11.88ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $4,479,000,  Roadway Improvement Cost: $2,623,000,  Total Project Cost: $7,102,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Latex Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224951,  Location: 1 MI NW OF VERZ - NAR BRG (Lat: 40.616906,  Lng: -74.074517),  Route carried "on" structure: City street ,  Year Built: 1931,  Year Reconstructed: 1989,  Status: Open,  Structure Length: 2.99m (9.81ft),  Average Daily Traffic: 7,612 (year 2018),  Truck Traffic: 7%,  Average Future Daily Traffic: 9,247 (year 2040),  Design Load: HS 20,  Features Intersected: WILLOW AVENUE, SIRT SOUT,  Facility Carried by Structure: TOMPKINS AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.644,  Lanes on structure: 2,  Lanes under structure: 2,  Owner: City or Municipal Highway Agency,  Maintenance Responsibility: Local Agency,  Approaching Roadway Width: 13.1m (43.0ft),  Skew: 2 degrees,  Material/Design: Prestressed concrete continuous,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 16.4m (53.8ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 2.7m (8.9ft),  Curb-To-Curb Width: 13.1m (43.0ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Satisfactory,  Operating Rating: 94.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 49.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present minimum criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 2.98m (9.78ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $3,823,000,  Roadway Improvement Cost: $2,239,000,  Total Project Cost: $6,062,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224952,  Location: IN TOMPKINSVILLE (Lat: 40.636231,  Lng: -74.074675),  Route carried "on" structure: City street ,  Year Built: 1935,  Year Reconstructed: 1987,  Status: Open,  Structure Length: 10.18m (33.40ft),  Average Daily Traffic: 3,637 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 5,092 (year 2037),  Design Load: HS 20+Mod,  Features Intersected: SIRT SOUTH SHORE,  Facility Carried by Structure: HANNAH STREET
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.322,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 9.1m (29.9ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 10,  Length of Maximum Span: 10.9m (35.8ft),  Curb or Sidewalk Widths: Left: 1.1m (3.6ft),  Right: 1.2m (3.9ft),  Curb-To-Curb Width: 8.8m (28.9ft),  Out-to-Out Width: 12.2m (40.0ft)

Condition: Deck: Good,  Superstructure: Good,  Substructure: Good,  Operating Rating: 50.8 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 29.9 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Better than present minimum criteria,  Deck Geometry: Meets minimum limits,  Underclear: High priority of corrective action,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 10.18m (33.40ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: October 2020,  Bridge Improvement Cost: $5,351,000,  Roadway Improvement Cost: $3,134,000,  Total Project Cost: $8,485,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete
Find on map >>   Show street view

Structure Number: 224976,  Location: IN CLOVE LAKES PARK (Lat: 40.622792,  Lng: -74.118369),  Route carried "on" structure: City street ,  Year Built: 1929,  Status: Open,  Structure Length: 2.74m (8.99ft),  Average Daily Traffic: 9,588 (year 2020),  Truck Traffic: 3%,  Average Future Daily Traffic: 11,647 (year 2040),  Features Intersected: RICHMOND LAKE DAM,  Facility Carried by Structure: MARTLING AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.499,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.4m (44.0ft),  Material/Design: Concrete,  Design/Construction: Culvert,  Number Of Spans In Main Unit: 2,  Length of Maximum Span: 4.8m (15.7ft),  Curb or Sidewalk Widths: Left: 4.8m (15.7ft),  Right: 4.8m (15.7ft),  Curb-To-Curb Width: 13.4m (44.0ft),  Out-to-Out Width: 23.9m (78.4ft)

Condition: Channel: Very good,  Culverts: Satisfactory,  Operating Rating: 50.6 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 22.0 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: High priority of replacement,  Waterway Adequacy: Equal to present minimum criteria,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 2.74m (8.99ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $3,465,000,  Roadway Improvement Cost: $2,029,000,  Total Project Cost: $5,495,000 ( Estimate for 2021)
Find on map >>   Show street view

Structure Number: 22498,  Location: IN CLOVE LAKES PARK (Lat: 40.627344,  Lng: -74.122664),  Route carried "on" structure: City street ,  Year Built: 1906,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 11,618 (year 2019),  Truck Traffic: 4%,  Average Future Daily Traffic: 11,672 (year 2040),  Features Intersected: CLOVE LK PK STRM,  Facility Carried by Structure: FOREST AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.956,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 10.7m (35.1ft),  Material/Design: Concrete,  Design/Construction: Arch - Deck,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 6.7m (22.0ft),  Curb or Sidewalk Widths: Left: 1.8m (5.9ft),  Right: 1.8m (5.9ft),  Curb-To-Curb Width: 10.7m (35.1ft),  Out-to-Out Width: 15.3m (50.2ft)

Condition: Superstructure: Satisfactory,  Substructure: Fair,  Channel: Good,  Operating Rating: 52.3 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 24.5 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Somewhat better than minimum adequacy,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present minimum criteria,  Length Of Structure Improvement: 0.97m (3.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: November 2021,  Bridge Improvement Cost: $625,000,  Roadway Improvement Cost: $366,000,  Total Project Cost: $991,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 224981,  Location: PRINCES BAY (Lat: 40.517672,  Lng: -74.201108),  Route carried "on" structure: City street ,  Year Built: 1989,  Status: Open,  Structure Length: 3.47m (11.38ft),  Average Daily Traffic: 12,848 (year 2019),  Truck Traffic: 8%,  Average Future Daily Traffic: 12,908 (year 2040),  Design Load: HS 20,  Features Intersected: LEMON CREEK,  Facility Carried by Structure: HYLAN BOULEVARD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 4.666,  Lanes on structure: 4,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 21.3m (69.9ft),  Skew: 20 degrees,  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 33.2m (108.9ft),  Curb or Sidewalk Widths: Left: 4.3m (14.1ft),  Right: 4.3m (14.1ft),  Curb-To-Curb Width: 21.3m (69.9ft),  Out-to-Out Width: 30.5m (100.1ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Channel: Very good,  Operating Rating: 85.3 metric tons,  Method Used To Determine Operating Rating: Load Factor (LF),  Inventory Rating: 50.8 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Superior to present desirable criteria,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Equal to present desirable criteria,  Length Of Structure Improvement: 3.47m (11.38ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2020,  Bridge Improvement Cost: $7,066,000,  Roadway Improvement Cost: $4,138,000,  Total Project Cost: $11,204,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete,  Deck Protection: Epoxy Coated Reinforcing
Find on map >>   Show street view

Structure Number: 224982,  Location: AT RICHMOND VALLEY (Lat: 40.520033,  Lng: -74.239822),  Route carried "on" structure: City street ,  Year Built: 1945,  Status: Open,  Structure Length: 0.98m (3.22ft),  Average Daily Traffic: 10,903 (year 2017),  Truck Traffic: 6%,  Average Future Daily Traffic: 13,244 (year 2040),  Features Intersected: ARTHUR KILL STRM,  Facility Carried by Structure: ARTHUR KILL ROAD
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 1.287,  Lanes on structure: 2,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 8.2m (26.9ft),  Material/Design: Steel,  Design/Construction: Stringer/Multi-beam,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 9.4m (30.8ft),  Curb or Sidewalk Widths: Left: 0.6m (2.0ft),  Right: 1.1m (3.6ft),  Curb-To-Curb Width: 11.0m (36.1ft),  Out-to-Out Width: 14.9m (48.9ft)

Condition: Deck: Satisfactory,  Superstructure: Poor,  Substructure: Fair,  Channel: Satisfactory,  Operating Rating: 65.2 metric tons,  Method Used To Determine Operating Rating: Field evaluation and documented engineering judgment,  Inventory Rating: 25.3 metric tons,  Method Used To Determine Inventory Rating: Field evaluation and documented engineering judgment,  Structural Evaluation: Meets minimum limits,  Deck Geometry: Meets minimum limits,  Waterway Adequacy: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Better than present minimum criteria,  Length Of Structure Improvement: 0.97m (3.18ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: May 2021,  Bridge Improvement Cost: $985,000,  Roadway Improvement Cost: $577,000,  Total Project Cost: $1,562,000 ( Estimate for 2021),  Deck Structure Type: Concrete Cast-file-Place,  Wearing Surface/Protective System: Wearing Surface: Bituminous
Find on map >>   Show street view

Structure Number: 224984,  Location: AT CLIFTON (Lat: 40.617428,  Lng: -74.074883),  Route carried "on" structure: City street ,  Year Built: 1931,  Year Reconstructed: 1992,  Status: Open,  Structure Length: 1.49m (4.89ft),  Average Daily Traffic: 7,612 (year 2018),  Truck Traffic: 7%,  Average Future Daily Traffic: 9,247 (year 2040),  Design Load: HS 20,  Features Intersected: GREENFIELD AVENUE,  Facility Carried by Structure: TOMPKINS AVENUE
Minimum Vertical Clearance: 30+ m (98+ ft),  Kilometerpoint: 0.676,  Lanes on structure: 2,  Lanes under structure: 1,  Owner: City or Municipal Highway Agency,  Approaching Roadway Width: 13.1m (43.0ft),  Skew: 1 degrees,  Material/Design: Prestressed concrete,  Design/Construction: Box Beam or Girders - Multiple,  Number Of Spans In Main Unit: 1,  Length of Maximum Span: 13.7m (44.9ft),  Curb or Sidewalk Widths: Left: 0.0m,  Right: 3.0m (9.8ft),  Curb-To-Curb Width: 13.1m (43.0ft),  Out-to-Out Width: 16.6m (54.5ft)

Condition: Deck: Very good,  Superstructure: Very good,  Substructure: Very good,  Inventory Rating: 55.3 metric tons,  Method Used To Determine Inventory Rating: Load Factor (LF),  Structural Evaluation: Equal to present desirable criteria,  Deck Geometry: Somewhat better than minimum adequacy,  Underclear: Somewhat better than minimum adequacy,  Approach Roadway Alignment: Somewhat better than minimum adequacy,  Length Of Structure Improvement: 1.49m (4.89ft),  Designated Inspection Frequency: Every 24 months,  Inspection Date: Febuary 2020,  Bridge Improvement Cost: $2,360,000,  Roadway Improvement Cost: $1,382,000,  Total Project Cost: $3,742,000 ( Estimate for 2021),  Wearing Surface/Protective System: Wearing Surface: Monolithic Concrete